NCDOT contract C204711 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #060009 OVER BLOUNTS CREEK ON SR-1112 (MOUTH OF THE CREEK ROAD). Let by North Carolina DOT on October 21, 2025, Beaufort. 8 bids received; low bid $11,018,000 by Sanford Contractors Inc.
- Owner
- North Carolina DOT
- Letting
- 21 OCT 2025
- Pay items
- 124
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sanford Contractors Inc | $11,018,000 | Low |
| 2 | S T Wooten Corporation | $11,464,553 | +4.0% |
| 3 | Balfour Beatty Infrastructure Inc | $14,118,902 | +28% |
| 4 | Zachry Construction Corporation | $15,558,569 | +41% |
| 5 | Conti Civil LLC | $16,303,442 | +48% |
| 6 | Caton Construction Group Inc | $16,415,770 | +49% |
| 7 | S & C Construction LLC | $16,718,044 | +52% |
| 8 | SJ Hamill Construction, LLC | $16,967,629 | +54% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sanford Contractors Inc | 2. S T Wooten Corporation | 3. Balfour Beatty Infrastructure Inc | 4. Zachry Construction Corporation | 5. Conti Civil LLC | 6. Caton Construction Group Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $550,900 | $570,000 | $705,945 | $777,928 | $810,000 | $820,856 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $155,000 | $67,000 | $787,464 | $250,000 | $300,000 | $59,406 |
| 0003 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $0.01 | $615.00 | $15,000 | $10,000 | $660.00 | $15,000 |
| 0004 | Undercut excavation (0057000000-E) | CY | 3,300 | $59.00 | $61.50 | $29.29 | $25.13 | $52.00 | $55.07 |
| 0005 | Grading (0063000000-N) | LS | 1 | $385,000 | $350,000 | $91,561 | $500,000 | $345,049 | $250,000 |
| 0006 | Borrow excavation (0106000000-E) | CY | 10,145 | $47.00 | $26.25 | $61.12 | $12.96 | $27.00 | $45.75 |
| 0007 | Embankment settlement gauges (0127000000-N) | EACH | 2 | $3,500.00 | $1,000.00 | $1,133.64 | $803.93 | $1,075.00 | $4,000.00 |
| 0008 | Drainage ditch excavation (0134000000-E) | CY | 10 | $15.00 | $36.55 | $114.18 | $8.86 | $10.00 | $30.00 |
| 0009 | Select granular material, class III (0194000000-E) | CY | 3,300 | $72.00 | $30.80 | $49.36 | $65.69 | $45.00 | $115.00 |
| 0010 | Geotextile for soil stabilization (0196000000-E) | SY | 1,300 | $7.00 | $2.75 | $2.40 | $3.67 | $3.00 | $7.13 |
| 0011 | Generic grading item (LS) - type 1 bridge approach fill, sta 22+57.00 -L- (0248000000-N) | LS | 1 | $48,704 | $50,000 | $50,984 | $26,395 | $25,000 | $61,250 |
| 0012 | Foundation conditioning material, minor structures (0318000000-E) | TON | 40 | $45.25 | $53.40 | $79.39 | $59.23 | $60.00 | $94.96 |
| 0013 | FND condit geotextile (4A) (0321000000-E) | SY | 120 | $3.75 | $2.85 | $3.30 | $5.57 | $3.00 | $7.00 |
| 0014 | 15" drainage pipe (0335200000-E) | LF | 72 | $179.61 | $155.25 | $86.58 | $92.37 | $98.00 | $208.98 |
| 0015 | **" drainage pipe elbow - (15") (0335850000-E) | EACH | 2 | $508.25 | $880.00 | $417.95 | $1,268.85 | $945.00 | $500.00 |
| 0016 | 15" side drain pipe (0343000000-E) | LF | 80 | $79.07 | $71.75 | $82.08 | $84.79 | $77.00 | $229.74 |
| 0017 | 18" RC pipe culverts, class III (0372000000-E) | LF | 76 | $174.02 | $83.65 | $110.66 | $125.59 | $90.00 | $316.37 |
| 0018 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 56 | $224.70 | $88.10 | $108.97 | $115.37 | $95.00 | $367.56 |
| 0019 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 52 | $253.51 | $100.85 | $126.31 | $125.18 | $108.00 | $383.95 |
| 0020 | Pipe removal (0995000000-E) | LF | 58 | $10.00 | $17.00 | $55.55 | $103.79 | $18.50 | $112.62 |
| 0021 | Aggregate base course (1121000000-E) | TON | 115 | $58.05 | $58.95 | $104.88 | $68.79 | $63.00 | $250.00 |
| 0022 | Incidental stone base (1220000000-E) | TON | 120 | $35.25 | $50.75 | $80.99 | $43.48 | $55.00 | $240.81 |
| 0023 | Prime coat (1275000000-E) | GAL | 15 | $42.00 | $5.78 | $50.00 | $55.43 | $52.50 | $50.00 |
| 0024 | Incidental milling (1330000000-E) | SY | 475 | $16.00 | $21.09 | $25.55 | $28.77 | $14.70 | $24.05 |
| 0025 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 1,040 | $125.00 | $115.00 | $115.00 | $117.00 | $121.00 | $115.00 |
| 0026 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 770 | $124.00 | $108.00 | $108.00 | $110.00 | $113.00 | $108.00 |
| 0027 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 635 | $124.00 | $105.00 | $105.00 | $107.00 | $110.00 | $105.00 |
| 0028 | Asphalt binder for plant mix (1575000000-E) | TON | 153 | $500.00 | $500.00 | $500.00 | $510.00 | $525.00 | $500.00 |
| 0029 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 215 | $200.00 | $240.00 | $538.29 | $375.00 | $375.00 | $395.00 |
| 0030 | Subdrain excavation (2022000000-E) | CY | 44.80 | $0.01 | $8.50 | $10.45 | $25.00 | $9.11 | $95.00 |
| 0031 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $0.01 | $3.00 | $3.41 | $2.10 | $3.21 | $12.90 |
| 0032 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $0.01 | $84.00 | $95.00 | $75.00 | $90.00 | $209.40 |
| 0033 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $0.01 | $3.00 | $12.00 | $20.00 | $3.21 | $53.72 |
| 0034 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $0.01 | $220.00 | $648.00 | $250.00 | $235.00 | $3,342.00 |
| 0035 | 6" outlet pipe (2077000000-E) | LF | 6 | $0.01 | $4.50 | $440.00 | $22.00 | $4.75 | $130.00 |
| 0036 | Masonry drainage structures (2286000000-N) | EACH | 4 | $6,100.00 | $3,650.00 | $4,766.05 | $3,700.00 | $3,910.00 | $11,147 |
| 0037 | Steel frame with two grates, STD 840.37 (2407000000-N) | EACH | 4 | $3,600.00 | $3,275.00 | $4,191.47 | $2,800.00 | $3,500.00 | $4,157.90 |
| 0038 | Shoulder berm gutter (2556000000-E) | LF | 65 | $283.00 | $72.00 | $125.00 | $37.00 | $49.50 | $50.25 |
| 0039 | Steel beam guardrail (3030000000-E) | LF | 125 | $24.50 | $24.50 | $25.01 | $26.00 | $25.75 | $24.50 |
| 0040 | Steel beam guardrail, shop curved (3045000000-E) | LF | 50 | $25.00 | $25.00 | $25.52 | $26.00 | $26.25 | $25.00 |
| 0041 | Steel beam guardrail terminal sections (3105000000-N) | EACH | 4 | $95.00 | $95.00 | $96.99 | $100.00 | $99.75 | $95.00 |
| 0042 | Additional guardrail posts (3150000000-N) | EACH | 5 | $11.00 | $11.00 | $11.23 | $12.00 | $11.55 | $11.00 |
| 0043 | Guardrail end units, type at-1 (3195000000-N) | EACH | 1 | $950.00 | $950.00 | $969.86 | $953.00 | $997.50 | $950.00 |
| 0044 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $2,250.00 | $2,250.00 | $2,297.04 | $2,400.00 | $2,362.50 | $2,250.00 |
| 0045 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 3 | $3,250.00 | $3,250.00 | $3,317.94 | $3,300.00 | $3,412.50 | $3,250.00 |
| 0046 | Remove existing guardrail (3360000000-E) | LF | 60 | $1.00 | $0.63 | $1.02 | $1.10 | $1.05 | $1.00 |
| 0047 | Rip rap, class B (3649000000-E) | TON | 245 | $73.65 | $77.25 | $109.00 | $62.00 | $83.00 | $113.00 |
| 0048 | Geotextile for drainage (3656000000-E) | SY | 1,655 | $3.75 | $3.10 | $4.13 | $3.10 | $3.35 | $6.82 |
| 0049 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 84 | $20.00 | $20.00 | $20.00 | $14.00 | $21.00 | $13.00 |
| 0050 | Supports, wood (4082000000-E) | LF | 197 | $20.00 | $20.00 | $20.00 | $13.00 | $21.00 | $12.00 |
| 0051 | Sign erection, type E (4102000000-N) | EACH | 28 | $100.00 | $100.00 | $100.00 | $76.00 | $105.00 | $75.00 |
| 0052 | Disposal of sign system, wood (4158000000-N) | EACH | 13 | $5.00 | $5.00 | $5.00 | $16.00 | $5.25 | $15.00 |
| 0053 | Work zone signs (stationary) (4400000000-E) | SF | 48 | $25.00 | $10.65 | $22.00 | $9.00 | $26.25 | $8.00 |
| 0054 | Work zone signs (portable) (4405000000-E) | SF | 128 | $9.75 | $8.55 | $36.57 | $15.00 | $22.00 | $14.00 |
| 0055 | Work zone signs (barricade mounted) (4410000000-E) | SF | 60 | $9.00 | $8.95 | $8.25 | $8.00 | $9.45 | $7.00 |
| 0056 | Drums (4430000000-N) | EACH | 50 | $47.00 | $46.00 | $81.73 | $44.00 | $79.00 | $43.00 |
| 0057 | Barricades (type III) (4445000000-E) | LF | 67 | $25.00 | $25.00 | $48.42 | $28.00 | $26.25 | $27.00 |
| 0058 | Flagger (4455000000-N) | DAY | 16 | $425.00 | $545.00 | $649.31 | $320.00 | $750.00 | $375.00 |
| 0059 | Skinny drum (4516000000-N) | EACH | 50 | $35.00 | $34.00 | $63.16 | $35.00 | $60.00 | $34.00 |
| 0060 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 5,246 | $2.75 | $2.75 | $2.75 | $3.00 | $2.90 | $2.75 |
| 0061 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 26 | $13.00 | $13.00 | $13.00 | $14.00 | $13.65 | $13.00 |
| 0062 | 4" cold appl plstic lines type ** - (I) (4770000000-E) | LF | 3,960 | $3.75 | $3.75 | $3.75 | $4.00 | $4.00 | $3.75 |
| 0063 | Paint pavement marking lines (4") (4810000000-E) | LF | 9,300 | $0.60 | $0.60 | $0.60 | $0.70 | $0.65 | $0.60 |
| 0064 | 8" water line (5325800000-E) | LF | 750 | $212.00 | $115.00 | $134.60 | $112.00 | $216.00 | $212.00 |
| 0065 | DI H2O pipe fittings (5329000000-E) | LB | 2,325 | $15.00 | $16.00 | $16.72 | $7.00 | $11.37 | $15.00 |
| 0066 | 8" valve (5546000000-E) | EACH | 4 | $6,475.00 | $4,230.00 | $4,524.23 | $2,900.00 | $5,200.00 | $6,475.00 |
| 0067 | Reconnect water meter (5649000000-N) | EACH | 5 | $2,120.00 | $2,370.00 | $2,698.83 | $1,400.00 | $2,400.00 | $2,120.00 |
| 0068 | Water service line (<2") (5686500000-E) | LF | 158 | $32.00 | $65.00 | $8.35 | $60.00 | $105.00 | $32.00 |
| 0069 | Abandon 8" utility pipe (5801000000-E) | LF | 654 | $10.00 | $28.00 | $10.85 | $10.00 | $31.00 | $10.00 |
| 0070 | Remove water meter (5815000000-N) | EACH | 1 | $1,000.00 | $2,000.00 | $458.35 | $710.00 | $625.00 | $1,000.00 |
| 0071 | 12" encasement pipe (5835600000-E) | LF | 87 | $300.00 | $167.00 | $148.01 | $130.00 | $300.00 | $300.00 |
| 0072 | Temporary silt fence (6000000000-E) | LF | 2,800 | $3.89 | $3.00 | $3.00 | $5.00 | $6.85 | $3.00 |
| 0073 | Stone for erosion control, class A (6006000000-E) | TON | 65 | $52.25 | $50.00 | $69.00 | $61.00 | $77.00 | $110.00 |
| 0074 | Stone for erosion control, class B (6009000000-E) | TON | 250 | $52.25 | $75.00 | $63.00 | $61.00 | $80.00 | $110.00 |
| 0075 | Sediment control stone (6012000000-E) | TON | 400 | $45.25 | $40.00 | $49.00 | $46.00 | $73.00 | $95.00 |
| 0076 | Temporary mulching (6015000000-E) | ACRE | 4.50 | $1,087.50 | $2,000.00 | $1,900.00 | $2,050.00 | $2,315.00 | $2,000.00 |
| 0077 | Seed for temporary seeding (6018000000-E) | LB | 400 | $6.33 | $1.00 | $3.00 | $1.10 | $6.40 | $1.00 |
| 0078 | Fertilizer for temporary seeding (6021000000-E) | TON | 2 | $1,725.00 | $300.00 | $1,400.00 | $310.00 | $1,420.00 | $300.00 |
| 0079 | Temporary slope drains (6024000000-E) | LF | 200 | $10.70 | $5.00 | $22.07 | $22.00 | $11.75 | $75.00 |
| 0080 | Safety fence (6029000000-E) | LF | 1,350 | $3.65 | $2.25 | $3.50 | $2.50 | $4.65 | $2.25 |
| 0081 | Silt excavation (6030000000-E) | CY | 350 | $0.01 | $5.00 | $33.84 | $14.00 | $10.50 | $100.00 |
| 0082 | Matting for erosion control (6036000000-E) | SY | 1,250 | $2.15 | $2.00 | $1.80 | $2.10 | $2.57 | $2.00 |
| 0083 | Coir fiber mat (6037000000-E) | SY | 625 | $6.95 | $5.50 | $6.50 | $6.00 | $6.00 | $5.50 |
| 0084 | 1/4" hardware cloth (6042000000-E) | LF | 350 | $7.25 | $6.00 | $5.50 | $7.92 | $14.18 | $6.00 |
| 0085 | Floating turbidity curtain (6048000000-E) | SY | 2,850 | $8.56 | $1.00 | $10.73 | $26.24 | $35.00 | $66.00 |
| 0086 | Special stilling basins (6070000000-N) | EACH | 14 | $0.01 | $100.00 | $469.37 | $1,028.80 | $700.00 | $3,133.34 |
| 0087 | Flocculant (6071002000-E) | LB | 60 | $25.00 | $8.00 | $5.00 | $10.56 | $16.25 | $8.00 |
| 0088 | Coir fiber wattle (6071012000-E) | LF | 350 | $12.95 | $13.50 | $10.00 | $17.82 | $13.55 | $13.50 |
| 0089 | Coir fiber wattle barrier (6071014000-E) | LF | 300 | $12.95 | $13.50 | $32.00 | $17.82 | $22.00 | $13.50 |
| 0090 | Coir fiber baffle (6071030000-E) | LF | 30 | $8.00 | $7.00 | $24.00 | $9.24 | $7.00 | $7.00 |
| 0091 | Seeding and mulching (6084000000-E) | ACRE | 6 | $2,875.00 | $3,200.00 | $2,800.00 | $4,223.45 | $3,925.00 | $3,200.00 |
| 0092 | Mowing (6087000000-E) | ACRE | 6 | $525.00 | $175.00 | $350.00 | $230.97 | $257.00 | $175.00 |
| 0093 | Seed for repair seeding (6090000000-E) | LB | 50 | $1.00 | $5.00 | $4.50 | $6.60 | $7.00 | $5.00 |
| 0094 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1.00 | $500.00 | $1,400.00 | $659.92 | $1,420.00 | $500.00 |
| 0095 | Seed for supplemental seeding (6096000000-E) | LB | 150 | $1.00 | $5.00 | $4.50 | $6.60 | $7.50 | $5.00 |
| 0096 | Fertilizer topdressing (6108000000-E) | TON | 4 | $1,564.50 | $500.00 | $1,200.00 | $659.92 | $1,419.00 | $500.00 |
| 0097 | Specialized hand mowing (6114500000-N) | MHR | 10 | $95.00 | $55.00 | $175.00 | $72.59 | $112.50 | $55.00 |
| 0098 | Response for erosion control (6117000000-N) | EACH | 13 | $150.00 | $500.00 | $500.00 | $659.92 | $245.00 | $500.00 |
| 0099 | Concrete washout structure (6117500000-N) | EACH | 2 | $321.00 | $5,000.00 | $1,296.51 | $1,065.65 | $2,500.00 | $589.00 |
| 0100 | Reforestation (6123000000-E) | ACRE | 0.10 | $10,000 | $8,400.00 | $25,000 | $11,087 | $5,350.00 | $8,400.00 |
| 0101 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 2 | $321.00 | $5,000.00 | $1,296.51 | $1,331.78 | $578.00 | $1,500.00 |
| 0102 | CM&R temp access *********** - (22+57.00 -L-) (8017000000-N) | LS | 1 | $2,395,000 | $3,400,000 | $3,045,129 | $5,839,619 | $3,000,000 | $4,347,000 |
| 0103 | Remv exist STR ****** BRG (402) - (22+57.00 -L-) (8035000000-N) | LS | 1 | $475,000 | $450,000 | $465,325 | $532,559 | $150,000 | $400,000 |
| 0104 | Asbestos assessment (8065000000-N) | LS | 1 | $3,000.00 | $2,000.00 | $2,690.00 | $851.30 | $2,100.00 | $2,000.00 |
| 0105 | Uncl STR excav sta ***** - (22+57.00 -L-) (8121000000-N) | LS | 1 | $5,000.00 | $15,000 | $8,982.51 | $7,029.50 | $15,000 | $35,000 |
| 0106 | Reinforced concrete deck slab (8147000000-E) | SF | 30,985 | $51.00 | $58.00 | $68.62 | $58.05 | $100.00 | $67.45 |
| 0107 | Grooving bridge floors (8161000000-E) | SF | 26,662 | $0.67 | $0.37 | $0.64 | $0.39 | $1.00 | $0.40 |
| 0108 | Class AA concrete (bridge) (8175000000-E) | CY | 309.50 | $1,700.00 | $960.00 | $2,054.41 | $1,949.46 | $4,050.00 | $2,500.00 |
| 0109 | BRG appr slab *********** - (22+57.00 -L-) (8210000000-N) | LS | 1 | $75,000 | $50,000 | $66,520 | $47,459 | $75,000 | $40,000 |
| 0110 | Epoxy coated reinforcing steel (bridge) (8224000000-E) | LB | 38,947 | $1.14 | $2.00 | $2.37 | $1.89 | $4.00 | $2.15 |
| 0111 | Fib **" prestr conc girdr - (63") (8278000000-E) | LF | 3,829.33 | $380.00 | $452.00 | $553.80 | $426.02 | $625.00 | $495.68 |
| 0112 | Pile DRV equip setup * prestr conc piles - (30") (8328000000-E) | EACH | 42 | $8,800.00 | $2,075.00 | $10,305 | $7,142.86 | $25,000 | $21,637 |
| 0113 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 14 | $5,300.00 | $1,750.00 | $4,095.72 | $5,208.58 | $3,500.00 | $4,750.00 |
| 0114 | 30" prestressed concrete piles (8353000000-E) | LF | 2,340 | $185.11 | $200.00 | $321.36 | $397.64 | $400.00 | $440.42 |
| 0115 | HP 12 X 53 steel piles (8364000000-E) | LF | 1,365 | $0.01 | $50.00 | $68.86 | $83.18 | $75.00 | $150.00 |
| 0116 | Steel pile points (8391000000-N) | EACH | 14 | $160.50 | $500.00 | $241.48 | $192.00 | $250.00 | $200.00 |
| 0117 | Pile redrives (8393000000-N) | EACH | 28 | $1.00 | $50.00 | $4,305.16 | $1,222.22 | $2,000.00 | $6,500.00 |
| 0118 | Dynamic pile testing (8394000000-N) | EACH | 6 | $2,500.00 | $10,000 | $6,153.10 | $2,889.39 | $3,000.00 | $13,350 |
| 0119 | Vertical concrete barrier rail (8505000000-E) | LF | 1,921.56 | $150.00 | $140.00 | $135.82 | $153.78 | $150.00 | $137.28 |
| 0120 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 185 | $87.16 | $110.00 | $129.57 | $81.38 | $130.00 | $189.62 |
| 0121 | Geotextile for drainage (8622000000-E) | SY | 205 | $3.75 | $1.00 | $4.21 | $6.51 | $5.00 | $21.69 |
| 0122 | Elastomeric bearings (8657000000-N) | LS | 1 | $20,069 | $25,000 | $65,968 | $126,303 | $235,000 | $148,660 |
| 0123 | Foam joint seals (8692000000-N) | LS | 1 | $60,000 | $40,000 | $43,961 | $54,019 | $50,000 | $25,940 |
| 0124 | Generic structure item (TON) - bridge deck asphalt patching (8874000000-E) | TON | 30 | $600.00 | $395.00 | $395.00 | $691.29 | $415.00 | $395.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of October 21, 2025. Compiled by Mirage Metrics.