Adjustment of meter boxes or valve boxes, NCDOT 2845000000-N

Low bidders on NCDOT contracts carried a median of $1,000.00 per EACH for this item, over the 24 months to 20 OCT 2026, across 85 low bids. Half of all 283 bids fell between $800.00 and $1,500.00.

Owner
North Carolina DOT
Item
2845000000-N
Unit
EACH
Data through
20 OCT 2026

NCDOT prints this item as “ADJ METER OR VALVE BOXES”.

$1,000.00Low bidder's median, per EACH
$1,000.00Median of all bids, per EACH
85Contracts in the window

By year of letting

Adjustment of meter boxes or valve boxes, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20136565$495.00222$500.00
20144545$549.00149$527.00
20155858$500.00173$500.00
20164545$650.00132$650.00
20172929$700.0088$737.50
20186161$800.00170$772.50
20192020$660.0056$679.19
20201717$550.0057$750.00
20215252$815.00180$815.00
20223434$942.50102$950.00
20233131$950.00103$1,000.00
20244544$1,025.00161$1,050.00
20254343$1,021.22134$1,061.00
20263232$908.05113$900.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Wake11$900.0053$900.00
Forsyth3$1,021.2215$1,123.00
Mecklenburg4$2,410.0015$1,800.00
Alamance4$1,225.0013$1,450.00
Buncombe3$1,000.0010$1,175.00
Richmond3$1,385.007$1,250.00
Adjustment of meter boxes or valve boxes, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 521$1,200.00
5 to 1321$900.00
14 to 2621$900.00
28 to 35722$1,035.61
Adjustment of meter boxes or valve boxes, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Adjustment of meter boxes or valve boxes, NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C205247Rowan66$1,150.00$1,136.502NJR Group IncNCDOT
24 SEP 2026C205140New Hanover15$574.02$574.021Balfour Beatty Infrastructure IncNCDOT
15 SEP 2026C205206Onslow5$1,100.00$1,100.003Barnhill Contracting CompanyNCDOT
15 SEP 2026C205233Wake11$650.00$650.004Blythe Construction IncNCDOT
15 SEP 2026C205234Rockingham12$750.00$750.003Apac - Atlantic, Inc. Thompson Arthur DivisionNCDOT
18 AUG 2026C205202Guilford8$900.00$1,034.565Triangle Grading & Paving IncNCDOT
16 JUN 2026C205182Carteret4$650.00$575.002Barnhill Contracting CompanyNCDOT
16 JUN 2026C205213New Hanover30$1,050.00$1,050.003Barnhill Contracting CompanyNCDOT
16 JUN 2026C205212Pender5$1,000.00$725.004S T Wooten CorporationNCDOT
16 JUN 2026C205211Buncombe92$700.00$1,200.005Apac Atlantic Inc Asheville DivisionNCDOT
19 MAY 2026C205199Brunswick5$750.00$925.004Highland Paving Co LLCNCDOT
19 MAY 2026C205197Randolph8$1,531.44$900.005Vecellio & Grogan Inc DBA Sharpe BrothersNCDOT
19 MAY 2026C204733Yadkin6$916.09$1,128.844Blythe Construction IncNCDOT
19 MAY 2026C205200Rutherford17$1,500.00$1,251.244Tarheel Paving & Asphalt Company Inc DBA Tarheel Paving & AsNCDOT
19 MAY 2026C205198Burke18$900.00$1,450.002Maymead, Inc.NCDOT
Latest NCDOT contracts carrying Adjustment of meter boxes or valve boxes

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.