Vecellio & Grogan Inc DBA Sharpe Brothers: NCDOT bid record
Vecellio & Grogan Inc DBA Sharpe Brothers submitted 39 bids on North Carolina DOT contracts in the data, from 19 SEP 2017 to 15 SEP 2026, and was the low bidder on 12 of them (31%). When it was not low, its total sat a median +8.0% above the low bid.
- Owner
- North Carolina DOT
- Low bid volume
- $83,548,537
- Latest bid
- 15 SEP 2026
- Data through
- 20 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2017 | 2 | 1 | 50% |
| 2018 | 4 | 0 | 0% |
| 2019 | 3 | 0 | 0% |
| 2022 | 7 | 3 | 43% |
| 2023 | 3 | 2 | 67% |
| 2024 | 9 | 3 | 33% |
| 2025 | 6 | 1 | 17% |
| 2026 | 5 | 2 | 40% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Randolph | 12 | 3 | 25% |
| Guilford | 6 | 2 | 33% |
| Forsyth | 6 | 0 | 0% |
| Davidson | 2 | 1 | 50% |
| Alamance | 2 | 1 | 50% |
| Rockingham | 2 | 1 | 50% |
| Buncombe, Henderson | 2 | 0 | 0% |
| Guilford, Rockingham | 1 | 1 | 100% |
| Alamance, Guilford | 1 | 1 | 100% |
| Davidson, Randolph | 1 | 0 | 0% |
| Chatham, Lee | 1 | 0 | 0% |
| Chatham, Randolph | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Asphalt conc surface course, type S9.5B | 1519000000-E | TON | 32 | 18 (56%) | $55.41 | $63.50 |
| Shoulder reconstruction | 1245000000-E | SMI | 25 | 13 (52%) | $2,301.04 | $2,670.00 |
| Ast, mat coat, #*** stone - (#67) | 1775500000-E | SY | 13 | 11 (85%) | $0.57 | $1.20 |
| Pipe removal | 0995000000-E | LF | 12 | 8 (67%) | $9.13 | $20.00 |
| Incidental stone base | 1220000000-E | TON | 23 | 7 (30%) | $40.38 | $40.00 |
| Patching existing pavement | 1704000000-E | TON | 25 | 6 (24%) | $153.64 | $125.00 |
| Undercut excavation | 0036000000-E | CY | 11 | 6 (55%) | $8.42 | $15.00 |
| Frame with cover, STD 840.54 | 2396000000-N | EACH | 11 | 6 (55%) | $363.42 | $670.00 |
| Class A concrete (bridge) | 8182000000-E | CY | 9 | 6 (67%) | $725.00 | $1,100.00 |
| Frame with two grates, STD 840.16 | 2364000000-N | EACH | 9 | 6 (67%) | $472.37 | $817.50 |
| Asphalt surface treatment, mat coat, #78M stone | 1775000000-E | SY | 6 | 6 (100%) | $0.42 | $1.00 |
| Asphalt conc surface course, type S9.5C | 1523000000-E | TON | 21 | 5 (24%) | $59.57 | $64.72 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Apac - Atlantic, Inc. Thompson Arthur Division | 27 | 14 of 27 |
| Blythe Construction Inc | 22 | 4 of 22 |
| FSC II LLC DBA Fred Smith Company | 12 | 2 of 12 |
| Truerock Construction LLC | 10 | 5 of 10 |
| J. T. Russell & Sons, Inc. | 7 | 2 of 7 |
| Branch Civil Inc | 6 | 5 of 6 |
| Boggs Contracting Inc | 6 | 1 of 6 |
| Triangle Grading & Paving Inc | 4 | 3 of 4 |
| NJR Group Inc | 4 | 2 of 4 |
| W C English Incorporated | 4 | 2 of 4 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 SEP 2026 | C205234 | Rockingham | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-704, 1 SECTION OF NC-14, 1 SECTION OF US-158, AND 6 SECTIONS OF SECONDARY | 2 of 3 | $7,615,873 | +8.0% |
| 15 SEP 2026 | C204990 | Randolph | GRADING, DRAINAGE, PAVING, SIGNALS, AND CULVERT. SR-1712 (PINEVIEW ST) FROM W OF SYLVAN DR TO US-220 BUSINESS | 7 of 9 | $9,361,775 | +12% |
| 16 JUN 2026 | C205157 | Randolph | GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURES. NC-42/SR-2194 (DUBLIN SQUARE RD) FROM SR-2237 (E SALISBURY ST) TO N OF US-64/NC-49 (DIXI | 8 of 11 | $14,850,511 | +20% |
| 19 MAY 2026 | C205197 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 11 SECTIONS OF SECONDARY ROADS, AND 1 SECTION OF NC-49 | 1 of 5 | $5,769,452 | Low, 0.0% under the second |
| 21 APR 2026 | C205193 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-134, 1 SECTION OF NC-159, 1 SECTION OF NC-109, AND 12 SECTIONS OF SECONDA | 1 of 5 | $5,736,346 | Low, 3.0% under the second |
| 21 OCT 2025 | C205143 | Davidson | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 16 SECTIONS OF SECONDARY ROADS | 2 of 3 | $7,014,239 | +11% |
| 21 OCT 2025 | C205142 | Forsyth | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-158, 1 SECTION OF NC-66, AND 15 SECTIONS OF SECONDARY ROADS | 2 of 2 | $10,578,938 | +21% |
| 15 JUL 2025 | C205114 | Rockingham | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 40 SECTIONS OF SECONDARY ROADS | 1 of 1 | $6,850,869 | Low |
| 20 MAY 2025 | C205102 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-64, 2 SECTIONS OF NC-22, AND 1 SECTION OF NC-42 | 5 of 5 | $4,638,430 | +16% |
| 20 MAY 2025 | C205087 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 13 SECTIONS OF SECONDARY ROADS | 2 of 3 | $4,061,769 | +11% |
| 20 MAY 2025 | C205089 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 10 SECTIONS OF SECONDARY ROADS | 2 of 5 | $3,768,471 | +2.0% |
| 17 DEC 2024 | C205003 | Alamance | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 15 SECTIONS OF SECONDARY ROADS | 2 of 5 | $4,657,351 | +5.0% |
| 15 OCT 2024 | C204986 | Davidson | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-109, AND 7 SECTIONS OF SECONDARY ROADS | 1 of 4 | $7,057,484 | Low, 2.0% under the second |
| 15 OCT 2024 | C204985 | Forsyth | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF OF US-158, AND 5 SECTIONS OF SECONDARY ROADS | 2 of 2 | $7,368,260 | +8.0% |
| 28 MAY 2024 | C204959 | Alamance, Guilford | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 29 SECTIONS OF SECONDARY ROADS | 1 of 4 | $5,067,692 | Low, 0.0% under the second |
| 28 MAY 2024 | C204908 | Guilford | GRADING, DRAINAGE, AND PAVING. RAILWAY-HIGHWAY CROSSING CLOSURE AT PINE STREET AND NORFOLK SOUTHERN CROSSING 722 957-L | 3 of 3 | $5,632,425 | +15% |
| 19 MAR 2024 | C204928 | Guilford, Rockingham | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-62 AND 39 SECTIONS OF SECONDARY ROADS | 1 of 3 | $5,794,919 | Low, 4.0% under the second |
| 19 MAR 2024 | C204916 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 8 SECTIONS OF SECONDARY ROADS | 3 of 5 | $3,216,051 | +3.0% |
| 20 FEB 2024 | C204915 | Randolph | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION EACH OF NC-42, NC-42 SOUTH, NC-22, AND 13 SECTIONS OF SECONDARY ROADS | 3 of 5 | $4,678,925 | +8.0% |
| 20 FEB 2024 | C204492 | Randolph | RESURFACING AND SHOULDER RECONSTRUCTION. 6 SECTIONS OF SECONDARY ROADS | 2 of 5 | $2,292,558 | +6.0% |
| 18 APR 2023 | C204736 | Guilford | Pavement rehabilitation. I-40 FROM BUFFALO CREEK BRIDGE EAST OF US-220 TO EAST OF SR-3037/SR-4240 (GATE CITY BLVD) IN GREENSBORO. | 1 of 3 | $11,499,384 | Low, 9.0% under the second |
| 21 FEB 2023 | C204849 | Randolph | Milling, resurfacing, and shoulder reconstruction. 1 SECTION OF NC-49 AND 19 SECTIONS OF SECONDARY ROADS. | 1 of 4 | $4,856,004 | Low, 5.0% under the second |
| 21 FEB 2023 | C204858 | Randolph | Milling, resurfacing, and shoulder reconstruction. 10 SECTIONS OF SECONDARY ROADS. | 2 of 4 | $3,413,377 | +1.0% |
| 20 DEC 2022 | C204809 | Chatham, Randolph | Milling, resurfacing, and shoulder reconstruction. 2 SECTIONS OF US-421. | 2 of 5 | $6,264,180 | 0.0% |
| 20 DEC 2022 | C204808 | Chatham | Shoulder reconstruction, milling, and resurfacing. 4 SECTIONS OF SECONDARY ROADS. | 1 of 4 | $2,157,118 | Low, 1.0% under the second |
How this record was read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.