NCDOT contract C205197 bid tabulation
MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 11 SECTIONS OF SECONDARY ROADS, AND 1 SECTION OF NC-49. Let by North Carolina DOT on May 19, 2026, Randolph. 5 bids received; low bid $5,769,452 by Vecellio & Grogan Inc DBA Sharpe Brothers.
- Owner
- North Carolina DOT
- Letting
- 19 MAY 2026
- Pay items
- 34
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vecellio & Grogan Inc DBA Sharpe Brothers | $5,769,452 | Low |
| 2 | Apac - Atlantic, Inc. Thompson Arthur Division | $5,786,032 | 0.0% |
| 3 | NJR Group Inc | $5,829,348 | +1.0% |
| 4 | Truerock Construction LLC | $5,957,058 | +3.0% |
| 5 | Blythe Construction Inc | $6,129,956 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vecellio & Grogan Inc DBA Sharpe Brothers | 2. Apac - Atlantic, Inc. Thompson Arthur Division | 3. NJR Group Inc | 4. Truerock Construction LLC | 5. Blythe Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $171,530 | $162,000 | $275,000 | $298,000 | $155,000 |
| 0002 | Incidental stone base (1220000000-E) | TON | 115 | $32.69 | $90.00 | $35.00 | $105.00 | $85.00 |
| 0003 | Shoulder reconstruction (1245000000-E) | SMI | 44.75 | $2,090.33 | $3,320.00 | $2,400.00 | $3,250.00 | $2,800.00 |
| 0004 | Aggregate shoulder borrow (1260000000-E) | TON | 7,360 | $29.20 | $23.00 | $22.00 | $20.00 | $40.00 |
| 0005 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 92,594 | $1.89 | $1.81 | $1.73 | $1.75 | $1.55 |
| 0006 | Incidental milling (1330000000-E) | SY | 15,270 | $9.00 | $7.71 | $5.75 | $6.75 | $6.90 |
| 0007 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 34,884 | $46.33 | $52.00 | $47.56 | $51.00 | $59.00 |
| 0008 | Asphalt binder for plant mix (1575000000-E) | TON | 2,395 | $749.30 | $710.00 | $730.00 | $650.00 | $725.00 |
| 0009 | Patching existing pavement (1704000000-E) | TON | 2,638 | $127.72 | $125.00 | $105.00 | $140.00 | $120.00 |
| 0010 | Ast, mat coat, #*** stone - (#67) (1775500000-E) | SY | 314,583.20 | $0.63 | $0.83 | $0.64 | $0.80 | $0.70 |
| 0011 | Emulsion for asphalt surface treatment (1838000000-E) | GAL | 125,833 | $2.91 | $2.62 | $2.95 | $2.75 | $2.10 |
| 0012 | Vacuum truck (1838500000-N) | WK | 17 | $0.01 | $0.01 | $1.00 | $1.00 | $1.00 |
| 0013 | Blotting sand (2143000000-E) | TON | 90 | $0.01 | $0.01 | $1.00 | $1.00 | $1.00 |
| 0014 | Adjustment of manholes (2830000000-N) | EACH | 12 | $1,537.92 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 0015 | Adjustment of meter boxes or valve boxes (2845000000-N) | EACH | 8 | $1,531.44 | $900.00 | $900.00 | $900.00 | $900.00 |
| 0016 | Work zone advance/general warning signing (4413000000-E) | SF | 3,030 | $5.45 | $5.40 | $5.05 | $8.00 | $5.05 |
| 0017 | Temporary traffic control (4457000000-N) | LS | 1 | $156,017 | $100,000 | $245,000 | $246,385 | $170,000 |
| 0018 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 575,895 | $0.54 | $0.53 | $0.65 | $0.65 | $0.65 |
| 0019 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 165 | $1.08 | $1.00 | $3.00 | $3.00 | $3.00 |
| 0020 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 60 | $2.16 | $2.00 | $4.00 | $4.00 | $4.00 |
| 0021 | Thermoplastic pavement marking lines (16", 90 mils) (4704000000-E) | LF | 548 | $7.56 | $7.00 | $10.00 | $10.00 | $10.00 |
| 0022 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 1,047 | $9.72 | $9.00 | $10.00 | $10.00 | $10.00 |
| 0023 | Thermoplastic pavement marking character (90 mils) (4720000000-E) | EACH | 14 | $108.00 | $100.00 | $80.00 | $80.00 | $80.00 |
| 0024 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 49 | $162.00 | $150.00 | $95.00 | $95.00 | $95.00 |
| 0025 | 4" cold appl plstic lines type ** - (II) (4770000000-E) | LF | 2,100 | $6.48 | $6.00 | $2.50 | $2.50 | $2.50 |
| 0026 | Paint pavement marking lines (4") (4810000000-E) | LF | 575,895 | $0.09 | $0.08 | $0.07 | $0.07 | $0.07 |
| 0027 | Paint pavement marking lines (8") (4820000000-E) | LF | 165 | $0.54 | $0.50 | $0.60 | $0.60 | $0.60 |
| 0028 | Paint pavement marking lines (16") (4830000000-E) | LF | 500 | $2.16 | $2.00 | $3.00 | $3.00 | $3.00 |
| 0029 | Paint pavement marking lines (24") (4835000000-E) | LF | 505 | $3.24 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0030 | Paint pavement marking character (4840000000-N) | EACH | 10 | $32.40 | $30.00 | $35.00 | $35.00 | $35.00 |
| 0031 | Paint pavement marking symbol (4845000000-N) | EACH | 12 | $54.00 | $50.00 | $35.00 | $35.00 | $35.00 |
| 0032 | Removal of pavement marking lines (8") (4860000000-E) | LF | 150 | $1.08 | $1.00 | $5.00 | $5.00 | $5.00 |
| 0033 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 349 | $54.00 | $50.00 | $48.00 | $48.00 | $48.00 |
| 0034 | Inductive loop sawcut (7444000000-E) | LF | 2,250 | $15.43 | $14.00 | $14.00 | $14.00 | $14.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of May 19, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.