ODOT contract 250042 bid tabulation
BUT-/HAM BP FY2025 (BRIDGE REPAIR). Let by Ohio DOT on January 30, 2025, BUT. 4 bids received; low bid $917,633 by 360 Construction Company Inc, +11% against the engineer's estimate of $830,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 51
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | 360 Construction Company Inc | $917,633 | Low | +11% |
| 2 | KMX Painting Inc | $994,554 | +8.0% | +20% |
| 3 | Apbn Inc | $1,214,177 | +32% | +46% |
| 4 | Elite Contractors Inc | $1,239,333 | +35% | +49% |
Engineer's estimate: $830,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 360 Construction Company Inc | 2. KMX Painting Inc | 3. Apbn Inc | 4. Elite Contractors Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $2,000.00 | $4,000.00 | $1,000.00 | $10,000 |
| 2 | Seeding and mulching (659E10000) | SY | 1,215 | $4.20 | $5.00 | $3.75 | $4.20 |
| 3 | Repair seeding and mulching (659E14000) | SY | 61 | $1.40 | $2.00 | $1.00 | $1.40 |
| 4 | Commercial fertilizer (659E20000) | TON | 0.16 | $765.00 | $900.00 | $1,500.00 | $765.00 |
| 5 | Lime (659E31000) | ACRE | 0.25 | $50.00 | $200.00 | $200.00 | $50.00 |
| 6 | Water (659E35000) | MGAL | 6.70 | $1.00 | $10.00 | $1.00 | $1.00 |
| 7 | Mowing (659E40000) | MSF | 2.70 | $1,000.00 | $200.00 | $1.00 | $850.00 |
| 8 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | RPM (621E00100) | EACH | 8 | $292.05 | $400.00 | $292.05 | $292.05 |
| 10 | Raised pavement marker removed (621E54000) | EACH | 8 | $75.00 | $100.00 | $100.00 | $500.00 |
| 11 | Edge line, 6" (644E00104) | MI | 0.05 | $31,510 | $35,000 | $31,510 | $31,510 |
| 12 | Center line (644E00300) | MI | 0.05 | $40,030 | $42,000 | $40,030 | $40,030 |
| 13 | Edge line, 6" (646E10010) | MI | 0.05 | $38,840 | $57,000 | $38,840 | $38,840 |
| 14 | Center line (646E10200) | MI | 0.05 | $51,855 | $52,000 | $51,855 | $51,855 |
| 15 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,200.00 | $2,500.00 | $2,200.00 | $2,200.00 |
| 16 | Work zone raised pavement marker (614E12800) | EACH | 200 | $15.00 | $20.00 | $15.00 | $15.00 |
| 17 | Barrier reflector, type 1 (BI-directional) (614E13310) | EACH | 5 | $14.00 | $50.00 | $14.00 | $14.00 |
| 18 | Object marker, two way (614E13360) | EACH | 5 | $18.00 | $50.00 | $18.00 | $18.00 |
| 19 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.42 | $3,160.00 | $8,000.00 | $3,160.00 | $3,160.00 |
| 20 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.46 | $2,415.00 | $9,000.00 | $2,415.00 | $2,415.00 |
| 21 | Roads for maintaining traffic (615E10000) | LS | 1 | $4,000.00 | $10,000 | $24,450 | $20,000 |
| 22 | Pavement for maintaining traffic, class B (615E25000) | SY | 125 | $25.00 | $300.00 | $285.00 | $285.00 |
| 23 | Portable barrier, unanchored (622E41100) | FT | 230 | $19.00 | $40.00 | $19.00 | $19.00 |
| 24 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $2,715.00 | $7,000.00 | $2,400.00 | $2,715.00 |
| 25 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 250 | $44.64 | $45.00 | $50.00 | $44.64 |
| 26 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 238 | $26.86 | $30.00 | $50.00 | $26.86 |
| 27 | Surface preparation of existing structural steel (514E00050) | SF | 7,742 | $31.00 | $23.00 | $15.00 | $22.00 |
| 28 | Field painting of existing structural steel, prime coat (514E00056) | SF | 7,742 | $2.00 | $5.00 | $10.00 | $5.00 |
| 29 | Field painting structural steel, intermediate coat (514E00060) | SF | 7,742 | $2.00 | $5.00 | $5.00 | $5.00 |
| 30 | Field painting structural steel, finish coat (514E00066) | SF | 7,742 | $2.00 | $5.00 | $5.00 | $5.00 |
| 31 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 14 | $125.00 | $250.00 | $100.00 | $100.00 |
| 32 | Final inspection repair (514E10000) | EACH | 4 | $200.00 | $350.00 | $100.00 | $200.00 |
| 33 | Joint sealer (516E31000) | FT | 146 | $23.40 | $25.00 | $16.00 | $23.40 |
| 34 | Deep beam bridge retrofit railing, as per plan (517E75601) | FT | 375 | $127.80 | $140.00 | $137.00 | $127.80 |
| 35 | Patching concrete bridge deck - type B (519E12300) | SY | 29 | $726.00 | $750.00 | $4,500.00 | $726.00 |
| 36 | Structure grounding system (625E33000) | EACH | 2 | $14,000 | $5,000.00 | $4,250.00 | $8,500.00 |
| 37 | Patching concrete structures with trowelable mortar (843E50000) | SF | 8 | $381.00 | $500.00 | $2,000.00 | $381.00 |
| 38 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $1,334.10 | $4,000.00 | $1,500.00 | $1,334.10 |
| 39 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 650 | $32.22 | $34.00 | $50.00 | $32.22 |
| 40 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 650 | $26.87 | $28.00 | $50.00 | $26.87 |
| 41 | Surface preparation of existing structural steel (514E00050) | SF | 9,370 | $27.00 | $20.00 | $15.00 | $22.00 |
| 42 | Field painting of existing structural steel, prime coat (514E00056) | SF | 9,370 | $2.00 | $5.00 | $10.00 | $5.00 |
| 43 | Field painting structural steel, intermediate coat (514E00060) | SF | 9,370 | $2.00 | $5.00 | $5.00 | $5.00 |
| 44 | Field painting structural steel, finish coat (514E00066) | SF | 9,370 | $2.00 | $4.00 | $5.00 | $5.00 |
| 45 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 17 | $125.00 | $250.00 | $100.00 | $100.00 |
| 46 | Final inspection repair (514E10000) | EACH | 6 | $200.00 | $350.00 | $100.00 | $200.00 |
| 47 | Joint sealer (516E31000) | FT | 98 | $26.22 | $30.00 | $16.00 | $26.22 |
| 48 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $15,000 | $15,000 | $50,000 |
| 49 | Maintaining traffic (614E11000) | LS | 1 | $60,000 | $46,000 | $75,970 | $100,000 |
| 50 | Construction layout stakes and surveying (623E10000) | LS | 1 | $500.00 | $5,000.00 | $1,000.00 | $2,000.00 |
| 51 | Mobilization (624E10000) | LS | 1 | $20,000 | $40,000 | $122,000 | $190,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.