ODOT contract 250043 bid tabulation
COS-CR 621-00.00 (BIKEWAYS). Let by Ohio DOT on January 30, 2025, COS. 2 bids received; low bid $2,358,781 by Shelly Company, +3.2% against the engineer's estimate of $2,286,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 82
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $2,358,781 | Low | +3.0% |
| 2 | Melway Paving Co Inc | $2,559,741 | +9.0% | +12% |
Engineer's estimate: $2,286,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Melway Paving Co Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $15,000 | $8,715.00 |
| 2 | Pavement removed (202E23000) | SY | 284 | $31.75 | $4.80 |
| 3 | Wearing course removed (202E23500) | SY | 404 | $23.75 | $7.00 |
| 4 | Walk removed (202E30000) | SF | 200 | $3.50 | $3.15 |
| 5 | Curb removed (202E32000) | FT | 55 | $13.00 | $11.50 |
| 6 | Special - pipe cleanout, 24" and under (202E70110) | FT | 50 | $83.00 | $30.15 |
| 7 | Removal misc.: removal and storage of property own (202E98100) | EACH | 9 | $380.00 | $603.00 |
| 8 | Excavation (203E10000) | CY | 4,692 | $46.00 | $39.35 |
| 9 | Embankment (203E20000) | CY | 1,290 | $29.00 | $45.25 |
| 10 | Subgrade compaction (204E10000) | SY | 15,215 | $1.50 | $2.30 |
| 11 | Excavation of subgrade (204E13000) | CY | 500 | $39.00 | $36.25 |
| 12 | Granular material, type B (204E30010) | CY | 500 | $72.00 | $95.15 |
| 13 | Proof rolling (204E45000) | HR | 7 | $240.00 | $100.50 |
| 14 | Geotextile fabric (204E50000) | SY | 500 | $1.30 | $0.70 |
| 15 | Geogrid (204E51000) | SY | 500 | $2.30 | $1.15 |
| 16 | 4" concrete walk, as per plan (608E10001) | SF | 399 | $13.75 | $8.55 |
| 17 | Curb ramp, as per plan (608E52001) | SF | 739 | $24.00 | $20.10 |
| 18 | Monument assembly adjusted to grade (623E39500) | EACH | 3 | $1,000.00 | $1,155.00 |
| 19 | Soil analysis test (659E00100) | EACH | 2 | $125.00 | $125.00 |
| 20 | Topsoil (659E00300) | CY | 1,102 | $60.00 | $44.00 |
| 21 | Seeding and mulching (659E10000) | SY | 9,919 | $0.70 | $0.71 |
| 22 | Repair seeding and mulching (659E14000) | SY | 496 | $0.80 | $0.80 |
| 23 | Commercial fertilizer (659E20000) | TON | 1.34 | $837.36 | $838.00 |
| 24 | Lime (659E31000) | ACRE | 2.05 | $154.79 | $155.00 |
| 25 | Water (659E35000) | MGAL | 54 | $1.00 | $1.00 |
| 26 | Slope erosion protection (670E00500) | SY | 1,181 | $1.29 | $1.30 |
| 27 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,360.00 |
| 28 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $1,500.00 | $3,075.00 |
| 29 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $7,500.00 | $505.00 |
| 30 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 |
| 31 | 12" conduit, type B (611E04400) | FT | 25 | $70.00 | $195.00 |
| 32 | 12" conduit, type B (611E04400) | FT | 25 | $95.00 | $379.00 |
| 33 | 12" conduit, type C (611E04600) | FT | 50 | $65.00 | $129.00 |
| 34 | 12" conduit, type C (611E04600) | FT | 25 | $70.00 | $153.00 |
| 35 | 12" conduit, type C (611E04600) | FT | 25 | $95.00 | $228.00 |
| 36 | 12" conduit, type E (611E05100) | FT | 25 | $70.00 | $126.00 |
| 37 | Catch basin adjusted to grade (611E98630) | EACH | 2 | $955.00 | $317.00 |
| 38 | Inlet, side ditch (611E98700) | EACH | 2 | $2,300.00 | $3,015.00 |
| 39 | Manhole adjusted to grade (611E99654) | EACH | 5 | $965.00 | $453.00 |
| 40 | Manhole reconstructed to grade (611E99660) | EACH | 7 | $2,300.00 | $9,000.00 |
| 41 | Special - miscellaneous metal (611E99820) | LB | 1,000 | $2.00 | $5.00 |
| 42 | Low strength mortar backfill (613E41200) | CY | 25 | $210.00 | $186.00 |
| 43 | Fire hydrant extended and adjusted to grade (638E10300) | EACH | 13 | $3,750.00 | $4,396.00 |
| 44 | Valve box adjusted to grade (638E10800) | EACH | 22 | $350.00 | $317.00 |
| 45 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,988 | $170.25 | $191.00 |
| 46 | Aggregate base, as per plan (304E20001) | CY | 2,321 | $96.75 | $130.00 |
| 47 | Tack coat (407E10000) | GAL | 4,187 | $3.90 | $2.51 |
| 48 | Stabilized crushed aggregate (411E10000) | CY | 491 | $92.00 | $100.00 |
| 49 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 1,672 | $174.00 | $197.00 |
| 50 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 1,166 | $190.00 | $223.00 |
| 51 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 539 | $176.00 | $215.00 |
| 52 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 154 | $158.00 | $72.00 |
| 53 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 932 | $100.00 | $80.00 |
| 54 | Combination curb and gutter, type 2 (609E12000) | FT | 42 | $115.00 | $49.00 |
| 55 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 2.91 | $2,725.00 | $2,581.00 |
| 56 | Delineator, post ground mounted (620E00500) | EACH | 3 | $500.00 | $503.00 |
| 57 | RPM (621E00100) | EACH | 99 | $55.00 | $56.00 |
| 58 | Raised pavement marker removed (621E54000) | EACH | 99 | $32.00 | $10.00 |
| 59 | Ground mounted support, no. 2 post (630E02100) | FT | 308 | $9.00 | $5.00 |
| 60 | Ground mounted support, no. 3 post (630E03100) | FT | 82.80 | $11.00 | $6.00 |
| 61 | Sign, flat sheet (630E80100) | SF | 181.20 | $15.00 | $20.00 |
| 62 | Removal of ground mounted sign and reerection (630E85100) | EACH | 17 | $30.00 | $300.00 |
| 63 | Removal of ground mounted post support and reerection (630E86010) | EACH | 9 | $30.00 | $300.00 |
| 64 | Signing, misc.: solar powered rectangular rapid FL (630E97700) | EACH | 4 | $11,250 | $5,250.00 |
| 65 | Edge line, 4", type 1 (642E00100) | MI | 1.49 | $550.00 | $1,357.00 |
| 66 | Edge line, 6", type 1 (642E00104) | MI | 2.84 | $600.00 | $1,382.00 |
| 67 | Center line, type 1 (642E00300) | MI | 2.91 | $700.00 | $1,558.00 |
| 68 | Channelizing line, 12", type 1 (642E00404) | FT | 7,478 | $0.65 | $0.55 |
| 69 | Stop line, type 1 (642E00500) | FT | 48 | $3.50 | $12.60 |
| 70 | Crosswalk line, 12", type 1 (642E00620) | FT | 88 | $3.00 | $6.05 |
| 71 | Crosswalk line, 24", type 1 (642E00630) | FT | 100 | $3.50 | $7.05 |
| 72 | Word on pavement, 72", type 1 (642E01400) | EACH | 2 | $150.00 | $327.00 |
| 73 | Word on pavement, 96", type 1 (642E01410) | EACH | 6 | $175.00 | $252.00 |
| 74 | Shared lane marking, type 1 (642E19000) | EACH | 12 | $50.00 | $76.00 |
| 75 | Yield line, type 1 (642E20802) | FT | 66 | $20.00 | $26.00 |
| 76 | Traffic compacted surface, type A or B (410E12000) | CY | 50 | $160.00 | $450.00 |
| 77 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $235.00 | $450.00 |
| 78 | Water (616E10000) | MGAL | 24 | $1.00 | $1.00 |
| 79 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,500.00 | $10,000 |
| 80 | Maintaining traffic (614E11000) | LS | 1 | $217,000 | $165,000 |
| 81 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $25,200 |
| 82 | Mobilization (624E10000) | LS | 1 | $50,000 | $73,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.