ODOT contract 250065 bid tabulation
SUM-SR-SR 8-15.75 (FOUR LANE RESURFACING). Let by Ohio DOT on January 30, 2025, SUM. 4 bids received; low bid $6,724,513 by Shelly Company, +17% against the engineer's estimate of $5,743,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 139
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $6,724,513 | Low | +17% |
| 2 | Shelly & Sands Inc | $6,815,603 | +1.0% | +19% |
| 3 | Karvo Companies Inc | $7,057,000 | +5.0% | +23% |
| 4 | Kokosing Construction Company Inc | $7,217,983 | +7.0% | +26% |
Engineer's estimate: $5,743,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Shelly & Sands Inc | 3. Karvo Companies Inc | 4. Kokosing Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Removal misc.: barrier reflector (202E98100) | EACH | 41 | $7.00 | $7.00 | $5.00 | $7.00 |
| 2 | Excavation (203E10000) | CY | 212 | $65.00 | $75.00 | $12.00 | $60.00 |
| 3 | Linear grading (209E60200) | STA | 110 | $70.00 | $95.00 | $75.00 | $195.00 |
| 4 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 10 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 5 | Special - as-built construction plans (690E91000) | LS | 1 | $10,000 | $3,000.00 | $493.99 | $1,000.00 |
| 6 | Special - vertical clearance (690E98000) | EACH | 2 | $640.00 | $3,000.00 | $640.00 | $2,000.00 |
| 7 | Seeding and mulching (659E10000) | SY | 334 | $11.80 | $13.52 | $1.25 | $11.80 |
| 8 | Commercial fertilizer (659E20000) | TON | 0.04 | $945.00 | $940.00 | $250.00 | $945.00 |
| 9 | Lime (659E31000) | ACRE | 0.07 | $60.00 | $156.00 | $100.00 | $60.00 |
| 10 | Water (659E35000) | MGAL | 1.80 | $1.00 | $1.00 | $1.00 | $1.00 |
| 11 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 10 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 13 | Partial depth pavement repair (441) (251E01000) | SY | 1,800 | $70.00 | $75.00 | $55.00 | $80.00 |
| 14 | Partial depth pavement repair (441) (251E01000) | SY | 200 | $95.00 | $75.00 | $100.00 | $280.00 |
| 15 | Pavement repair (253E01000) | SY | 200 | $110.00 | $350.00 | $95.00 | $300.00 |
| 16 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 196,550 | $1.95 | $3.12 | $3.50 | $1.85 |
| 17 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 163 | $195.00 | $299.00 | $300.00 | $260.00 |
| 18 | Aggregate base (304E20000) | CY | 12 | $85.00 | $100.00 | $90.00 | $80.00 |
| 19 | Non-tracking tack coat (407E20000) | GAL | 17,691 | $3.00 | $3.05 | $2.65 | $2.75 |
| 20 | Prime coat, as per plan (408E10001) | GAL | 3,857 | $5.00 | $3.50 | $5.00 | $4.00 |
| 21 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 49 | $215.00 | $300.00 | $175.00 | $392.00 |
| 22 | Anti-segregation equipment (442E00100) | CY | 4,111 | $13.00 | $19.00 | $18.00 | $1.00 |
| 23 | Asphalt concrete surface course, 12.5 MM, type A (447), PWL 2025, as per plan (442E10331) | CY | 8,191 | $280.00 | $305.00 | $340.00 | $395.00 |
| 24 | Compacted aggregate, as per plan (617E10101) | CY | 282 | $95.00 | $160.00 | $100.00 | $60.00 |
| 25 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 26 | Connection, fused pull apart (625E00450) | EACH | 4 | $200.00 | $200.00 | $200.00 | $125.00 |
| 27 | Connection, unfused permanent (625E00480) | EACH | 3 | $200.00 | $200.00 | $200.00 | $125.00 |
| 28 | Light pole, conventional, AT15B41.7 (625E10490) | EACH | 1 | $3,750.00 | $3,750.00 | $3,750.00 | $4,975.00 |
| 29 | Light pole, conventional, ST15B40 (625E10490) | EACH | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $6,200.00 |
| 30 | Light pole anchor bolts on structure (625E10614) | EACH | 4 | $250.00 | $250.00 | $250.00 | $475.00 |
| 31 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,900.00 |
| 32 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 645 | $3.00 | $3.00 | $3.00 | $4.40 |
| 33 | No. 10 AWG pole and bracket cable (625E23400) | FT | 336 | $2.00 | $2.00 | $2.00 | $2.00 |
| 34 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 400 | $10.00 | $10.00 | $10.00 | $12.00 |
| 35 | Conduit, 2", 725.04 (625E25400) | FT | 8 | $50.00 | $50.00 | $50.00 | $85.00 |
| 36 | Luminaire, conventional, solid state (LED), 115-13 (625E26252) | EACH | 2 | $500.00 | $500.00 | $500.00 | $630.00 |
| 37 | Structure junction box (625E29920) | EACH | 2 | $4,000.00 | $4,000.00 | $4,000.00 | $2,675.00 |
| 38 | Ground rod (625E32000) | EACH | 1 | $250.00 | $250.00 | $250.00 | $300.00 |
| 39 | RPM (621E00100) | EACH | 152 | $39.00 | $36.50 | $36.50 | $39.00 |
| 40 | Raised pavement marker removed (621E54000) | EACH | 427 | $5.00 | $5.00 | $1.00 | $2.00 |
| 41 | Barrier reflector, type 1 (one-way) (626E00102) | EACH | 185 | $25.00 | $25.00 | $25.00 | $25.00 |
| 42 | Barrier reflector, type 2 (one-way) (626E00110) | EACH | 19 | $27.00 | $27.00 | $30.00 | $27.00 |
| 43 | Ground mounted support, no. 2 post (630E02100) | FT | 239 | $8.50 | $8.50 | $8.50 | $8.50 |
| 44 | Sign, flat sheet (630E80100) | SF | 60 | $18.00 | $18.00 | $18.00 | $18.00 |
| 45 | Sign, flat sheet (630E80100) | SF | 18 | $18.00 | $18.00 | $18.00 | $18.00 |
| 46 | Removal of ground mounted sign and disposal (630E84900) | EACH | 24 | $20.00 | $20.00 | $20.00 | $20.00 |
| 47 | Removal of ground mounted post support and disposal (630E86002) | EACH | 24 | $5.00 | $5.00 | $5.00 | $5.00 |
| 48 | Stop line (646E10400) | FT | 45 | $10.00 | $10.00 | $10.00 | $10.00 |
| 49 | Chevron marking (646E10620) | FT | 600 | $10.00 | $10.00 | $10.00 | $10.00 |
| 50 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 10.24 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 51 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 8 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 |
| 52 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 4,800 | $1.75 | $1.75 | $1.75 | $1.75 |
| 53 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 18.82 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 54 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 4,800 | $0.95 | $0.95 | $0.95 | $0.95 |
| 55 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.74 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 |
| 56 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 150 | $100.00 | $90.00 | $100.00 | $105.00 |
| 57 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $3,000.00 | $3,000.00 | $2,000.00 | $3,000.00 |
| 58 | Work zone marking sign (614E12460) | EACH | 6 | $85.00 | $85.00 | $85.00 | $85.00 |
| 59 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $120.00 | $300.00 | $250.00 | $1,400.00 |
| 60 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 36 | $5.00 | $5.00 | $5.00 | $5.00 |
| 61 | Object marker, one way (614E13350) | EACH | 36 | $10.00 | $10.00 | $10.00 | $10.00 |
| 62 | Portable changeable message sign, as per plan (614E18601) | SNMT | 7 | $800.00 | $800.00 | $800.00 | $1,400.00 |
| 63 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 7.49 | $625.00 | $625.00 | $625.00 | $625.00 |
| 64 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 7.49 | $625.00 | $625.00 | $625.00 | $625.00 |
| 65 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 20.88 | $675.00 | $675.00 | $675.00 | $675.00 |
| 66 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 4,200 | $0.65 | $0.65 | $0.65 | $0.65 |
| 67 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,200 | $0.65 | $0.65 | $0.65 | $0.65 |
| 68 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 1,440 | $0.60 | $0.60 | $0.60 | $0.60 |
| 69 | Portable barrier, unanchored (622E41100) | FT | 880 | $18.00 | $18.00 | $18.00 | $18.00 |
| 70 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 12 | $575.00 | $575.00 | $575.00 | $1,500.00 |
| 71 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 72 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 211 | $36.00 | $36.00 | $33.00 | $36.00 |
| 73 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,689 | $11.00 | $11.00 | $11.00 | $11.00 |
| 74 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 211 | $36.00 | $36.00 | $23.00 | $36.00 |
| 75 | Removal of existing pavement marking (512E74500) | FT | 961 | $3.00 | $3.00 | $3.00 | $3.00 |
| 76 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $20,000 | $20,000 | $20,000 | $20,000 |
| 77 | Epoxy coated steel reinforcement (509E10000) | LB | 117 | $10.00 | $10.00 | $10.00 | $10.00 |
| 78 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 25 | $10.00 | $10.00 | $10.00 | $10.00 |
| 79 | Class QC2 concrete, bridge deck (parapet) (511E34448) | CY | 4 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 80 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,787 | $36.00 | $36.00 | $33.00 | $36.00 |
| 81 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 5,114 | $11.00 | $11.00 | $11.00 | $11.00 |
| 82 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 3,000 | $36.00 | $36.00 | $23.00 | $36.00 |
| 83 | Removal of existing pavement marking (512E74500) | FT | 3,003 | $3.00 | $3.00 | $3.00 | $3.00 |
| 84 | Surface preparation of existing structural steel (514E00050) | SF | 49,307 | $13.25 | $15.75 | $13.00 | $15.75 |
| 85 | Field painting of existing structural steel, prime coat (514E00056) | SF | 11,469 | $10.00 | $3.00 | $6.25 | $3.00 |
| 86 | Field painting structural steel, intermediate coat (514E00060) | SF | 11,469 | $9.00 | $2.00 | $5.75 | $2.00 |
| 87 | Field painting structural steel, finish coat (514E00066) | SF | 11,469 | $9.00 | $1.00 | $5.75 | $1.00 |
| 88 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 17 | $100.00 | $150.00 | $10.00 | $150.00 |
| 89 | Final inspection repair (514E10000) | EACH | 7 | $100.00 | $200.00 | $50.00 | $200.00 |
| 90 | Patching concrete structure, as per plan (519E11101) | SF | 25 | $155.00 | $155.00 | $165.00 | $155.00 |
| 91 | Patching concrete bridge deck - type C (519E12304) | SY | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 92 | Special - noise barrier (structure mounted) (damag (606E10920) | SF | 2,430 | $40.00 | $40.00 | $40.00 | $40.00 |
| 93 | Patching concrete structures with trowelable mortar (843E50000) | SF | 1,550 | $155.00 | $155.00 | $165.00 | $155.00 |
| 94 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 95 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 683 | $11.00 | $11.00 | $11.00 | $11.00 |
| 96 | Removal of existing pavement marking (512E74500) | FT | 369 | $3.00 | $3.00 | $3.00 | $3.00 |
| 97 | Patching concrete structure, as per plan (519E11101) | SF | 50 | $155.00 | $155.00 | $165.00 | $155.00 |
| 98 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 99 | Bridge terminal assembly removed for reuse (202E47200) | EACH | 2 | $1,975.00 | $3,960.00 | $1,975.00 | $3,960.00 |
| 100 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 20 | $36.00 | $36.00 | $44.52 | $36.00 |
| 101 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 683 | $11.00 | $11.00 | $11.00 | $11.00 |
| 102 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 238 | $36.00 | $36.00 | $23.00 | $36.00 |
| 103 | Removal of existing pavement marking (512E74500) | FT | 369 | $3.00 | $3.00 | $3.00 | $3.00 |
| 104 | Patching concrete structure, as per plan (519E11101) | SF | 70 | $155.00 | $155.00 | $165.00 | $155.00 |
| 105 | Patching concrete structures with trowelable mortar (843E50000) | SF | 130 | $155.00 | $155.00 | $165.00 | $155.00 |
| 106 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 107 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 525 | $36.00 | $36.00 | $33.00 | $36.00 |
| 108 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 679 | $11.00 | $11.00 | $11.00 | $11.00 |
| 109 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 1,099 | $36.00 | $36.00 | $23.00 | $36.00 |
| 110 | Removal of existing pavement marking (512E74500) | FT | 550 | $3.00 | $3.00 | $3.00 | $3.00 |
| 111 | Surface preparation of existing structural steel (514E00050) | SF | 9,998 | $13.00 | $23.00 | $15.50 | $23.00 |
| 112 | Field painting of existing structural steel, prime coat (514E00056) | SF | 1,573 | $10.00 | $3.00 | $17.80 | $3.00 |
| 113 | Field painting structural steel, intermediate coat (514E00060) | SF | 1,573 | $10.00 | $2.00 | $17.80 | $2.00 |
| 114 | Field painting structural steel, finish coat (514E00066) | SF | 1,573 | $10.00 | $1.00 | $17.80 | $1.00 |
| 115 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 5 | $100.00 | $150.00 | $10.00 | $150.00 |
| 116 | Final inspection repair (514E10000) | EACH | 2 | $100.00 | $200.00 | $50.00 | $200.00 |
| 117 | Special - noise barrier (structure mounted) (damag (606E10920) | SF | 650 | $50.00 | $50.00 | $50.00 | $50.00 |
| 118 | Patching concrete structures with trowelable mortar (843E50000) | SF | 230 | $155.00 | $155.00 | $165.00 | $155.00 |
| 119 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 120 | Removal misc.: channel cleanout (202E98000) | LS | 1 | $15,000 | $15,000 | $15,000 | $15,000 |
| 121 | Rock channel protection, type B without filter (601E34100) | CY | 2 | $500.00 | $500.00 | $500.00 | $500.00 |
| 122 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 123 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 939 | $36.00 | $36.00 | $33.00 | $36.00 |
| 124 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 4,194 | $11.00 | $11.00 | $11.00 | $11.00 |
| 125 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 939 | $36.00 | $36.00 | $23.00 | $36.00 |
| 126 | Removal of existing pavement marking (512E74500) | FT | 2,462 | $3.00 | $3.00 | $3.00 | $3.00 |
| 127 | Patching concrete bridge deck - type C (519E12304) | SY | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 128 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 129 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 967 | $36.00 | $36.00 | $33.00 | $36.00 |
| 130 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 4,066 | $11.00 | $11.00 | $11.00 | $11.00 |
| 131 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 967 | $36.00 | $36.00 | $23.00 | $36.00 |
| 132 | Removal of existing pavement marking (512E74500) | FT | 2,387 | $3.00 | $3.00 | $3.00 | $3.00 |
| 133 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $28,000 | $49,267 | $30,000 |
| 134 | Maintaining traffic (614E11000) | LS | 1 | $833,000 | $431,462 | $325,000 | $209,065 |
| 135 | Field office, type B (619E16010) | MNTH | 6 | $3,000.00 | $3,000.00 | $2,500.00 | $3,000.00 |
| 136 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,000.00 | $10,000 | $4,393.50 | $10,000 |
| 137 | Mobilization (624E10000) | LS | 1 | $200,000 | $200,000 | $400,000 | $360,899 |
| 200 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 8 | $25.00 | $25.00 | $25.00 | $25.00 |
| 201 | RPM, as per plan (621E00101) | EACH | 749 | $38.00 | $29.00 | $29.00 | $38.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way