ODOT contract 250092 bid tabulation
LAW-SR 775-19.50 (SLIDE REPAIR). Let by Ohio DOT on February 27, 2025, LAW. 5 bids received; low bid $721,401 by Alan Stone Co Inc, +0.1% against the engineer's estimate of $721,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $721,401 | Low | 0.0% |
| 2 | Allard Excavation LLC | $848,668 | +18% | +18% |
| 3 | Ohio-West Virginia Excavating Co | $852,051 | +18% | +18% |
| 4 | CJ Hughes Construction Company | $998,271 | +38% | +38% |
| 5 | Meridian Communications and Construction Inc | $1,110,160 | +54% | +54% |
Engineer's estimate: $721,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. Allard Excavation LLC | 3. Ohio-West Virginia Excavating Co | 4. CJ Hughes Construction Company | 5. Meridian Communications and Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $12,838 | $17,500 | $15,000 | $12,700 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $460.00 | $216.00 | $2,000.00 | $1,200.00 | $400.00 |
| 3 | Pavement removed (202E23000) | SY | 747 | $15.00 | $28.00 | $11.00 | $20.00 | $18.26 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 44 | $35.00 | $631.00 | $51.00 | $33.00 | $93.18 |
| 5 | Excavation (203E10000) | CY | 59 | $30.00 | $20.00 | $50.00 | $95.00 | $31.35 |
| 6 | Embankment (203E20000) | CY | 287 | $15.00 | $11.00 | $26.00 | $26.00 | $27.00 |
| 7 | Subgrade compaction (204E10000) | SY | 868 | $4.50 | $3.00 | $4.00 | $12.50 | $0.92 |
| 8 | Proof rolling (204E45000) | HR | 1 | $220.00 | $245.00 | $275.00 | $500.00 | $200.00 |
| 9 | Rock channel protection, with grout, type C (601E34400) | CY | 11 | $320.00 | $137.00 | $337.00 | $800.00 | $400.00 |
| 10 | Seeding and mulching (659E10000) | SY | 427 | $5.00 | $3.00 | $9.00 | $11.50 | $17.86 |
| 11 | Repair seeding and mulching (659E14000) | SY | 22 | $1.00 | $0.05 | $9.00 | $18.00 | $22.73 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.06 | $1,600.00 | $680.00 | $1,400.00 | $34,650 | $5,000.00 |
| 13 | Lime (659E31000) | ACRE | 0.09 | $210.00 | $500.00 | $200.00 | $2,500.00 | $4,444.44 |
| 14 | Water (659E35000) | MGAL | 2 | $1.00 | $1.00 | $1.00 | $1.00 | $350.00 |
| 15 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Concrete masonry (602E20000) | CY | 0.30 | $4,700.00 | $6,207.00 | $7,600.00 | $7,700.00 | $3,000.00 |
| 17 | 6" shallow pipe underdrains (605E11100) | FT | 482 | $15.00 | $20.00 | $32.00 | $27.00 | $7.93 |
| 18 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 9 | $6.50 | $20.00 | $5.00 | $60.00 | $13.33 |
| 19 | 6" conduit, type B (611E00900) | FT | 21 | $55.00 | $38.00 | $4.00 | $40.00 | $13.10 |
| 20 | 15" conduit, type A (611E05700) | FT | 36 | $170.00 | $245.00 | $262.00 | $100.00 | $132.92 |
| 21 | Pavement repair (253E02000) | CY | 50 | $300.00 | $615.00 | $711.00 | $200.00 | $120.00 |
| 22 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 93 | $270.00 | $285.00 | $330.00 | $1,080.00 | $288.49 |
| 23 | Aggregate base (304E20000) | CY | 146 | $90.00 | $95.00 | $144.00 | $77.00 | $63.00 |
| 24 | Tack coat (407E10000) | GAL | 297 | $8.50 | $2.50 | $3.00 | $8.00 | $11.00 |
| 25 | Stabilized crushed aggregate (411E10000) | CY | 16 | $170.00 | $112.00 | $176.00 | $135.00 | $68.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 168 | $300.00 | $295.00 | $342.00 | $540.00 | $303.79 |
| 27 | Compacted aggregate (617E10100) | CY | 50 | $100.00 | $76.05 | $138.00 | $93.00 | $69.00 |
| 28 | Water (617E25000) | MGAL | 10 | $1.00 | $1.00 | $1.00 | $1.00 | $210.00 |
| 29 | RPM (621E00100) | EACH | 6 | $520.00 | $500.00 | $550.00 | $730.00 | $630.00 |
| 30 | Raised pavement marker removed (621E54000) | EACH | 6 | $30.00 | $4.00 | $102.00 | $340.00 | $333.33 |
| 31 | Edge line, 6", type 1 (642E00104) | MI | 0.14 | $5,400.00 | $5,250.00 | $6,000.00 | $12,000 | $14,750 |
| 32 | Center line, type 1 (642E00300) | MI | 0.07 | $11,000 | $10,250 | $12,000 | $23,700 | $14,714 |
| 33 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $95.00 | $85.00 | $90.00 | $85.00 | $75.00 |
| 34 | Detour signing (614E12420) | LS | 1 | $3,900.00 | $3,750.00 | $4,300.00 | $5,300.00 | $9,000.00 |
| 35 | Water (616E10000) | MGAL | 50 | $10.00 | $1.00 | $1.00 | $1.00 | $93.60 |
| 36 | Unclassified excavation (503E21300) | LS | 1 | $23,000 | $2,690.00 | $9,000.00 | $22,500 | $5,000.00 |
| 37 | Steel piles, misc.: W24X104 steel beam, furnished, (507E00400) | FT | 1,925 | $100.00 | $145.35 | $138.00 | $149.00 | $310.60 |
| 38 | Concrete, misc.: precast reinforced concrete laggi (511E71200) | SF | 3,968 | $29.15 | $30.00 | $25.25 | $28.00 | $28.56 |
| 39 | Porous backfill with geotextile fabric (518E21200) | CY | 187 | $240.00 | $105.00 | $94.00 | $155.00 | $269.04 |
| 40 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 471 | $90.00 | $105.00 | $120.00 | $164.00 | $63.91 |
| 41 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 600 | $90.00 | $106.00 | $116.00 | $175.00 | $139.99 |
| 42 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,600.00 | $6,630.00 | $15,000 | $7,500.00 | $3,132.48 |
| 43 | Maintaining traffic (614E11000) | LS | 1 | $8,300.00 | $9,204.00 | $9,800.00 | $4,500.00 | $4,000.00 |
| 44 | Field office, type A (619E16000) | MNTH | 3 | $1,000.00 | $1,500.00 | $1,700.00 | $500.00 | $4,000.00 |
| 45 | Construction layout stakes and surveying (623E10000) | LS | 1 | $9,000.00 | $10,030 | $875.00 | $10,000 | $4,000.00 |
| 46 | Mobilization (624E10000) | LS | 1 | $30,000 | $50,000 | $52,500 | $7,000.00 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.