ODOT contract 250140 bid tabulation
COL-ODNR GUILFORD LAKE STATE PAR (PARKING AREAS). Let by Ohio DOT on February 27, 2025, COL. 4 bids received; low bid $985,581 by Shelly Company, -25% against the engineer's estimate of $1,311,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 26
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $985,581 | Low | -25% |
| 2 | Barbicas Construction Company Inc | $1,103,834 | +12% | -16% |
| 3 | Brennstuhl Construction Inc | $1,221,463 | +24% | -7.0% |
| 4 | NLS Paving, Inc | $1,393,950 | +41% | +6.0% |
Engineer's estimate: $1,311,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Barbicas Construction Company Inc | 3. Brennstuhl Construction Inc | 4. NLS Paving, Inc |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 7,029 | $7.00 | $9.50 | $11.47 | $10.00 |
| 2 | Special - parking block removed and reset (202E53010) | EACH | 487 | $60.00 | $30.00 | $58.73 | $115.00 |
| 3 | Removal misc.: speed bumps removed and reset (202E98100) | EACH | 2 | $1,175.00 | $1,000.00 | $204.09 | $325.00 |
| 4 | Excavation (203E10000) | CY | 1,171 | $40.00 | $50.00 | $46.41 | $51.50 |
| 5 | Subgrade compaction (204E10000) | SY | 7,029 | $1.00 | $1.00 | $0.70 | $2.00 |
| 6 | Special - concrete parking block (690E50500) | EACH | 26 | $350.00 | $125.00 | $213.59 | $200.00 |
| 7 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 8 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 20,817 | $2.25 | $3.00 | $3.28 | $3.25 |
| 9 | Pavement planing, asphalt concrete (2.5") (254E01000) | SY | 4,179 | $7.50 | $4.00 | $7.83 | $7.50 |
| 10 | Pavement planing, asphalt concrete (3.0") (254E01000) | SY | 1,281 | $6.00 | $2.00 | $11.43 | $8.00 |
| 11 | Aggregate base (304E20000) | CY | 1,171 | $62.00 | $125.00 | $100.04 | $125.00 |
| 12 | Non-tracking tack coat (407E20000) | GAL | 3,305 | $3.00 | $3.20 | $5.94 | $3.50 |
| 13 | Prime coat, as per plan (408E10001) | GAL | 3,654 | $4.75 | $4.50 | $7.70 | $4.50 |
| 14 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 1,379 | $225.00 | $250.00 | $254.36 | $300.00 |
| 15 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 116 | $280.00 | $250.00 | $278.58 | $300.00 |
| 16 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 941 | $165.00 | $220.00 | $238.33 | $260.00 |
| 17 | Compacted aggregate, as per plan (617E10101) | CY | 318 | $120.00 | $125.00 | $191.18 | $160.00 |
| 18 | Shoulder preparation (617E20000) | SY | 9,135 | $1.00 | $0.50 | $4.38 | $3.00 |
| 19 | Parking lot stall marking, type 1 (642E01200) | FT | 8,622 | $1.30 | $1.30 | $1.43 | $1.50 |
| 20 | Lane arrow, type 1 (642E01300) | EACH | 15 | $50.00 | $50.00 | $55.00 | $55.00 |
| 21 | Handicap symbol marking, type 1 (642E01702) | EACH | 12 | $50.00 | $50.00 | $55.00 | $55.00 |
| 22 | Pavement marking, misc.: camping lot number (642E50010) | EACH | 35 | $35.00 | $10.00 | $11.00 | $20.00 |
| 23 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $7,500.00 | $15,000 | $7,496.25 |
| 24 | Maintaining traffic (614E11000) | LS | 1 | $64,000 | $11,000 | $12,151 | $35,000 |
| 25 | Field office, type B (619E16010) | MNTH | 5 | $1,400.00 | $1,000.00 | $110.00 | $2,750.00 |
| 26 | Mobilization (624E10000) | LS | 1 | $20,000 | $34,000 | $15,400 | $60,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.