ODOT contract 250195 bid tabulation
MOT-CS-Denlinger Rd RSF-01.51 (TWO LANE RESURFACING). Let by Ohio DOT on April 10, 2025, MOT. 2 bids received; low bid $838,353 by John R Jurgensen Company, -14% against the engineer's estimate of $978,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 29
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $838,353 | Low | -14% |
| 2 | Barrett Paving Materials Inc | $903,609 | +8.0% | -8.0% |
Engineer's estimate: $978,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Barrett Paving Materials Inc |
|---|---|---|---|---|---|
| 1 | Manhole adjusted to grade (611E99654) | EACH | 22 | $1,019.17 | $1,150.00 |
| 2 | Pavement repair, as per plan (253E02001) | CY | 400 | $374.57 | $450.00 |
| 3 | Pavement planing, asphalt concrete, 2" (254E01000) | SY | 34,000 | $2.60 | $2.65 |
| 4 | Non-tracking tack coat (407E20000) | GAL | 2,890 | $5.00 | $3.50 |
| 5 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 1,889 | $204.28 | $220.00 |
| 6 | Compacted aggregate, as per plan (617E10101) | CY | 120 | $177.19 | $200.00 |
| 7 | Valve box adjusted to grade (638E10800) | EACH | 21 | $720.00 | $650.00 |
| 8 | Edge line, 4" (644E00100) | MI | 0.79 | $2,500.00 | $2,500.00 |
| 9 | Lane line, 4" (644E00200) | MI | 0.10 | $1,300.00 | $1,300.00 |
| 10 | Center line (644E00300) | MI | 2.16 | $4,033.00 | $4,035.00 |
| 11 | Channelizing line, 8" (644E00400) | FT | 1,229 | $1.16 | $1.20 |
| 12 | Stop line (644E00500) | FT | 217 | $7.00 | $7.00 |
| 13 | Crosswalk line, 12" (644E00620) | FT | 677 | $3.50 | $3.50 |
| 14 | Lane arrow (644E01300) | EACH | 13 | $85.00 | $85.00 |
| 15 | Two way left turn arrow (644E01370) | EACH | 13 | $165.00 | $165.00 |
| 16 | Word on pavement, 72" (644E01400) | EACH | 2 | $95.00 | $95.00 |
| 17 | Detector loop (632E26500) | EACH | 18 | $1,350.00 | $1,350.00 |
| 18 | Loop detector tie in (632E27200) | EACH | 18 | $100.00 | $100.00 |
| 19 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 96 | $107.14 | $90.00 |
| 20 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 0.20 | $450.00 | $450.00 |
| 21 | Work zone center line, class III, 642 paint (614E21550) | MI | 4.32 | $1,033.00 | $1,035.00 |
| 22 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 1.58 | $680.00 | $680.00 |
| 23 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 2,458 | $0.45 | $0.45 |
| 24 | Work zone stop line, class III, 642 paint (614E26610) | FT | 434 | $3.00 | $3.00 |
| 25 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 78 | $27.00 | $27.00 |
| 26 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,045.88 | $10,350 |
| 27 | Maintaining traffic (614E11000) | LS | 1 | $23,182 | $42,000 |
| 28 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,660.36 | $8,000.00 |
| 29 | Mobilization (624E10000) | LS | 1 | $40,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.