ODOT contract 250208 bid tabulation
TRU-N River Rd Parking Lot (PARKING AREAS). Let by Ohio DOT on April 10, 2025, TRU. 3 bids received; low bid $204,204 by Shook Company LLC, +19% against the engineer's estimate of $171,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 28
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shook Company LLC | $204,204 | Low | +19% |
| 2 | Barbicas Construction Company Inc | $219,299 | +7.0% | +28% |
| 3 | Shelly Company | $322,392 | +58% | +89% |
Engineer's estimate: $171,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shook Company LLC | 2. Barbicas Construction Company Inc | 3. Shelly Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $4,000.00 | $6,000.00 |
| 2 | Excavation (203E10000) | CY | 584 | $35.00 | $49.00 | $35.00 |
| 3 | Embankment (203E20000) | CY | 9 | $50.00 | $49.00 | $35.00 |
| 4 | Roadway, misc.:#2 crushed limestone base/stormwate (203E98000) | CY | 385 | $80.00 | $100.00 | $100.00 |
| 5 | Roadway, misc.:#57 crushed limestone choker course (203E98000) | CY | 65 | $100.00 | $200.00 | $110.00 |
| 6 | Geotextile fabric (204E50000) | SY | 1,228 | $7.00 | $3.00 | $2.75 |
| 7 | Special - concrete parking block (690E50500) | EACH | 18 | $200.00 | $80.00 | $250.00 |
| 8 | Topsoil (659E00300) | CY | 27 | $100.00 | $100.00 | $150.00 |
| 9 | Seeding and mulching (659E10000) | SY | 243 | $2.00 | $10.00 | $20.00 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.03 | $1,000.00 | $1,000.00 | $800.00 |
| 11 | Lime (659E31000) | ACRE | 0.05 | $1,000.00 | $150.00 | $150.00 |
| 12 | Water (659E35000) | MGAL | 1 | $1.00 | $5.00 | $1.00 |
| 13 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 14 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 284 | $30.00 | $16.00 | $39.00 |
| 15 | 6" conduit, type F for underdrain outlets, as per plan (611E00511) | FT | 75 | $100.00 | $22.00 | $45.00 |
| 16 | Asphalt concrete, misc.:porous asphalt pavement BA (441E90000) | CY | 97 | $420.00 | $415.00 | $800.00 |
| 17 | Asphalt concrete, misc.:porous asphalt pavement SU (441E90000) | CY | 41 | $825.00 | $455.00 | $2,000.00 |
| 18 | Conduit, 1-1/2", 725.051 (625E25304) | FT | 125 | $40.00 | $15.00 | $18.00 |
| 19 | Ground mounted support, no. 3 post (630E03100) | FT | 26 | $30.00 | $16.00 | $16.00 |
| 20 | Sign, flat sheet (630E80100) | SF | 7 | $100.00 | $50.00 | $50.00 |
| 21 | Transverse/diagonal line, type 1 (642E00700) | FT | 150 | $10.00 | $4.00 | $4.00 |
| 22 | Parking lot stall marking, type 1 (642E01200) | FT | 435 | $6.00 | $4.00 | $4.00 |
| 23 | Handicap symbol marking, type A125 (647E20202) | EACH | 1 | $50.00 | $250.00 | $250.00 |
| 24 | Water (616E10000) | MGAL | 1 | $1.00 | $10.00 | $10.00 |
| 25 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,000.00 | $2,000.00 | $2,500.00 |
| 26 | Maintaining traffic (614E11000) | LS | 1 | $5,000.00 | $4,300.00 | $35,000 |
| 27 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,325.00 | $1,800.00 | $5,000.00 |
| 28 | Mobilization (624E10000) | LS | 1 | $13,000 | $45,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way