ODOT contract 250300 bid tabulation

ATB-SR 7-14.95/18.44 (TWO LANE RESURFACING). Let by Ohio DOT on June 12, 2025, ATB. 2 bids received; low bid $3,775,000 by Karvo Companies Inc, -8.5% against the engineer's estimate of $4,125,000.

Owner
Ohio DOT
Letting
12 JUN 2025
Pay items
46
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Karvo Companies Inc$3,775,000Low-8.0%
2Ronyak Paving Inc$4,055,122+7.0%-2.0%
ODOT contract 250300: bids by rank

Engineer's estimate: $4,125,000.

Bid tabulation

LinePay itemUnitQuantity1. Karvo Companies Inc2. Ronyak Paving Inc
1Wearing course removed (202E23500)SY52$0.50$10.00
2Removal misc.: barrier reflector (202E98100)EACH21$13.00$12.00
3Excavation (203E10000)CY42$15.00$10.00
4Linear grading (209E60200)STA134$50.00$8.00
5Preparing subgrade for shoulder paving (209E72000)STA1,200$15.00$8.00
6Monument assembly adjusted to grade, as per plan (623E39501)EACH12$1,700.00$2,675.00
7Special - as-built construction plans (690E91000)LS1$500.79$2,500.00
8Erosion control (832E30000)EACH3,000$1.00$1.00
9Partial depth pavement repair (441) (251E01000)SY2,750$40.00$40.00
10Partial depth pavement repair (441) (251E01000)SY250$100.00$60.00
11Full depth pavement sawing (252E01500)FT3,375$0.25$1.00
12Pavement repair (253E01000)SY783$65.00$125.00
13Pavement planing, asphalt concrete (T=1.75") (254E01000)SY161,361$1.30$1.25
14Pavement planing, asphalt concrete (T=2.25") (254E01000)SY46,322$2.10$1.50
15Aggregate base (304E20000)CY42$25.00$60.00
16Non-tracking tack coat (407E20000)GAL21,417$2.25$2.00
17Prime coat, as per plan (408E10001)GAL10,664$4.50$2.25
18Aggregate, single chip seal, type A (422E11000)SY162,283$0.45$0.85
19Emulsion, chip seal (422E25000)GAL64,914$4.40$3.00
20Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100)CY8,380$225.00$235.00
21Asphalt concrete intermediate course, type 1, (448) (441E50200)CY1,262$215.00$215.00
22Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY26$225.00$500.00
23Compacted aggregate, as per plan (617E10101)CY741$100.00$175.00
24Rumble stripes, edge line (asphalt concrete) (618E41000)MI3$1,450.00$1,450.00
25Rumble stripes, center line (asphalt concrete) (618E43000)MI3$1,150.00$1,150.00
26Longitudinal joint preparation (874E20000)FT10,772$1.00$1.00
27RPM (621E00100)EACH753$39.50$38.50
28Raised pavement marker removed (621E54000)EACH605$1.00$1.00
29Barrier reflector, type 1 (bidirectional) (626E00102)EACH103$39.00$36.00
30Edge line, 6" (646E10010)MI22.74$2,650.00$2,650.00
31Center line (646E10200)MI11.37$1,385.00$1,385.00
32Stop line (646E10400)FT62$12.25$12.25
33Law enforcement officer with patrol car for assistance (614E11110)HR50$100.00$100.00
34Work zone marking sign (614E12460)EACH12$85.00$85.00
35Asphalt concrete for maintaining traffic (614E13000)CY10$275.00$275.00
36Portable changeable message sign, as per plan (614E18601)SNMT12$900.00$900.00
37Work zone center line, class I (614E21000)MI11.37$975.00$975.00
38Work zone center line, class III, 642 paint (614E21550)MI22.74$950.00$950.00
39Work zone edge line, class III, 6", 642 paint (614E22360)MI68.22$515.00$515.00
40Work zone stop line, class I (614E26000)FT62$3.00$3.00
41Work zone stop line, class III, 642 paint (614E26610)FT124$3.00$3.00
42Premium for contract performance bond and for payment bond (103E05000)LS1$24,375$25,795
43Maintaining traffic (614E11000)LS1$125,000$250,000
44Field office, type B (619E16010)MNTH6$3,000.00$2,000.00
45Construction layout stakes and surveying (623E10000)LS1$5,000.00$8,500.00
46Mobilization (624E10000)LS1$149,000$210,000
ODOT contract 250300: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy