ODOT contract 250301 bid tabulation
BEL-IR 70-07.64 (SPOT PATCHING / PAVEMENT REPAIR). Let by Ohio DOT on June 12, 2025, BEL. 4 bids received; low bid $1,159,640 by Shelly & Sands Inc, -24% against the engineer's estimate of $1,518,000.
- Owner
- Ohio DOT
- Letting
- 12 JUN 2025
- Pay items
- 19
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,159,640 | Low | -24% |
| 2 | NLS Paving, Inc | $1,476,650 | +27% | -3.0% |
| 3 | Karvo Companies Inc | $1,518,000 | +31% | 0.0% |
| 4 | Perk Company Inc | $1,994,950 | +72% | +31% |
Engineer's estimate: $1,518,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. NLS Paving, Inc | 3. Karvo Companies Inc | 4. Perk Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 2 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 2,000 | $430.00 | $525.00 | $425.00 | $630.50 |
| 3 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 48 | $670.00 | $1,200.00 | $500.00 | $1,000.00 |
| 4 | Full depth pavement sawing (255E20000) | FT | 7,624 | $5.00 | $7.50 | $3.00 | $6.65 |
| 5 | RPM (621E00100) | EACH | 40 | $75.00 | $75.00 | $210.00 | $245.00 |
| 6 | Raised pavement marker removed (621E54000) | EACH | 40 | $35.50 | $30.00 | $1.00 | $100.00 |
| 7 | Edge line, 6" (646E10010) | MI | 0.80 | $9,000.00 | $15,690 | $15,690 | $15,060 |
| 8 | Lane line, 6" (646E10110) | MI | 0.40 | $7,000.00 | $9,950.00 | $9,950.00 | $5,565.00 |
| 9 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 300 | $118.00 | $100.00 | $100.00 | $125.00 |
| 10 | Work zone increased penalties sign (614E12484) | EACH | 16 | $95.00 | $95.00 | $175.00 | $245.00 |
| 11 | Replacement sign (614E12500) | EACH | 4 | $150.00 | $150.00 | $150.00 | $240.00 |
| 12 | Replacement drum (614E12600) | EACH | 25 | $80.00 | $80.00 | $50.00 | $55.00 |
| 13 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.40 | $4,250.00 | $4,250.00 | $5,000.00 | $1,190.00 |
| 14 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.80 | $2,400.00 | $2,400.00 | $2,500.00 | $3,415.00 |
| 15 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 24 | $725.00 | $725.00 | $750.00 | $897.00 |
| 16 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,900.00 | $7,498.00 | $29,000 | $22,000 |
| 17 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $63,500 | $140,000 | $270,000 | $305,685 |
| 18 | Field office, type B (619E16010) | MNTH | 5 | $5,000.00 | $2,500.00 | $3,000.00 | $1,600.00 |
| 19 | Mobilization (624E10000) | LS | 1 | $58,000 | $75,000 | $224,506 | $202,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 12, 2025. Compiled by Mirage Metrics.