ODOT contract 250416 bid tabulation

SCI-US 52-00.00 (CHIP SEAL). Let by Ohio DOT on September 11, 2025, SCI. 2 bids received; low bid $698,102 by Shelly Company, +0.4% against the engineer's estimate of $695,000.

Owner
Ohio DOT
Letting
11 SEP 2025
Pay items
19
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly Company$698,102Low0.0%
2Runway Incorporated$719,431+3.0%+4.0%
ODOT contract 250416: bids by rank

Engineer's estimate: $695,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly Company2. Runway Incorporated
1Partial depth pavement repair (asphalt concrete base), as per plan (251E01041)SY500$77.00$132.87
2Aggregate, single chip seal, type A (422E11000)SY143,287$1.06$0.65
3Emulsion, chip seal (422E25000)GAL53,016$3.05$3.84
4Compacted aggregate (617E10100)CY204$130.00$175.10
5Fog seal (886E11000)GAL21,494$3.15$2.97
6RPM (621E00100)EACH618$32.75$37.80
7Raised pavement marker removed (621E54000)EACH618$16.00$17.43
8Edge line, 6", type 1 (642E00104)MI20.06$760.00$875.50
9Center line, type 1 (642E00300)MI10.03$1,065.00$1,127.85
10Removal of pavement marking (644E30030)MI30.09$1,142.00$1,133.00
11Edge line, 6" (646E10010)MI0.08$23,530$30,900
12Center line (646E10200)MI0.04$32,550$30,900
13Work zone marking sign (614E12460)EACH47$90.00$92.70
14Work zone center line, class III, 642 paint (614E21550)MI30.09$817.00$849.75
15Work zone edge line, class III, 6", 642 paint (614E22360)MI60.18$538.00$715.85
16Premium for contract performance bond and for payment bond (103E05000)LS1$3,000.00$15,000
17Maintaining traffic (614E11000)LS1$67,000$43,398
18Construction layout stakes and surveying (623E10000)LS1$2,000.00$10,710
19Mobilization (624E10000)LS1$25,000$13,800
ODOT contract 250416: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy