ODOT contract 250418 bid tabulation
STA-US 62-36.42/38.60 (TWO LANE RESURFACING). Let by Ohio DOT on September 11, 2025, STA. 3 bids received; low bid $1,618,571 by Karvo Companies Inc, +12% against the engineer's estimate of $1,449,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Karvo Companies Inc | $1,618,571 | Low | +12% |
| 2 | Shelly Company | $1,689,502 | +4.0% | +17% |
| 3 | Barbicas Construction Company Inc | $1,820,533 | +12% | +26% |
Engineer's estimate: $1,449,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Karvo Companies Inc | 2. Shelly Company | 3. Barbicas Construction Company Inc |
|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 433 | $8.75 | $8.00 | $10.00 |
| 2 | Curb and gutter removed (202E32500) | FT | 132 | $20.00 | $43.00 | $10.00 |
| 3 | Removal misc.: top of curb removed (202E98200) | FT | 15 | $20.00 | $80.00 | $30.00 |
| 4 | Excavation (203E10000) | CY | 84 | $25.00 | $20.00 | $20.00 |
| 5 | 4" concrete walk (608E10000) | SF | 153 | $18.75 | $13.00 | $20.00 |
| 6 | Curb ramp (608E52000) | SF | 280 | $18.75 | $27.00 | $20.00 |
| 7 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 1 | $1,500.00 | $3,000.00 | $1,200.00 |
| 8 | Special - as-built construction plans (690E91000) | LS | 1 | $650.00 | $10,000 | $150.00 |
| 9 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 10 | Partial depth pavement repair (441) (251E01000) | SY | 1,000 | $61.00 | $80.00 | $80.00 |
| 11 | Partial depth pavement repair (441) (251E01000) | SY | 200 | $115.00 | $175.00 | $125.00 |
| 12 | Full depth pavement sawing (252E01500) | FT | 1,000 | $5.00 | $4.50 | $4.00 |
| 13 | Pavement repair (253E01000) | SY | 500 | $118.00 | $175.00 | $290.00 |
| 14 | Pavement planing, asphalt concrete(T=2") (254E01000) | SY | 59,313 | $2.60 | $2.50 | $3.00 |
| 15 | Aggregate base (304E20000) | CY | 84 | $55.00 | $70.00 | $100.00 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 8,898 | $2.50 | $3.00 | $3.00 |
| 17 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 1,648 | $253.00 | $260.00 | $240.00 |
| 18 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 1,648 | $198.00 | $205.00 | $240.00 |
| 19 | Combination curb and gutter, type 2 (609E12000) | FT | 78 | $65.00 | $70.00 | $50.00 |
| 20 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 1 | $1,100.00 | $3,000.00 | $1,200.00 |
| 21 | Lane line, 6" (646E10110) | MI | 3.52 | $1,800.00 | $1,380.00 | $3,250.00 |
| 22 | Center line (646E10200) | MI | 2.82 | $3,330.00 | $3,250.00 | $4,500.00 |
| 23 | Channelizing line, 12" (646E10310) | FT | 1,498 | $1.75 | $1.50 | $1.50 |
| 24 | Stop line (646E10400) | FT | 332 | $12.00 | $9.25 | $10.00 |
| 25 | Crosswalk line, 12" (646E10510) | FT | 2,293 | $5.10 | $4.35 | $8.00 |
| 26 | Transverse/diagonal line (646E10600) | FT | 206 | $8.00 | $7.60 | $10.00 |
| 27 | Island marking (646E10800) | SF | 62 | $7.00 | $3.90 | $15.00 |
| 28 | Lane arrow (646E20300) | EACH | 37 | $162.00 | $115.00 | $150.00 |
| 29 | Two way left turn arrow (646E20370) | EACH | 6 | $188.00 | $180.00 | $150.00 |
| 31 | Stop line radar detection, as per plan (809E69101) | EACH | 17 | $8,800.00 | $8,800.00 | $7,700.00 |
| 32 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $125.00 | $120.00 | $80.00 |
| 33 | Work zone marking sign (614E12460) | EACH | 4 | $106.15 | $65.00 | $65.00 |
| 34 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $265.00 | $150.00 | $250.00 |
| 35 | Portable changeable message sign (614E18600) | SNMT | 4 | $1,100.00 | $900.00 | $1,500.00 |
| 36 | Work zone lane line, class I, 6" (614E20010) | MI | 7.04 | $575.00 | $500.00 | $500.00 |
| 37 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 3.52 | $565.00 | $500.00 | $500.00 |
| 38 | Work zone center line, class I (614E21000) | MI | 5.64 | $1,050.00 | $900.00 | $900.00 |
| 39 | Work zone center line, class III, 642 paint (614E21550) | MI | 2.82 | $999.00 | $900.00 | $900.00 |
| 40 | Work zone channelizing line, class I, 12" (614E23010) | FT | 2,996 | $0.68 | $0.50 | $0.50 |
| 41 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 1,498 | $0.58 | $0.50 | $0.50 |
| 42 | Work zone stop line, class I (614E26000) | FT | 664 | $2.50 | $3.00 | $3.00 |
| 43 | Work zone stop line, class III, 642 paint (614E26610) | FT | 332 | $2.50 | $3.00 | $3.00 |
| 44 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,500 | $10,000 | $30,000 |
| 45 | Maintaining traffic (614E11000) | LS | 1 | $126,000 | $165,750 | $175,000 |
| 46 | Field office, type B (619E16010) | MNTH | 12 | $3,500.00 | $3,500.00 | $1,000.00 |
| 47 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $10,000 | $300.00 |
| 48 | Mobilization (624E10000) | LS | 1 | $102,000 | $40,000 | $96,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.