ODOT contract 250422 bid tabulation
D02-LG FY2026 (LIGHTING). Let by Ohio DOT on September 11, 2025, District 2. 3 bids received; low bid $946,225 by J Ranck Electric Inc, +4.9% against the engineer's estimate of $902,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 62
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J Ranck Electric Inc | $946,225 | Low | +5.0% |
| 2 | U S Utility Contractor Company | $1,014,893 | +7.0% | +13% |
| 3 | Miller Cable Company | $1,609,885 | +70% | +78% |
Engineer's estimate: $902,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J Ranck Electric Inc | 2. U S Utility Contractor Company | 3. Miller Cable Company |
|---|---|---|---|---|---|---|
| 1 | Control center removed (202E75700) | LS | 1 | $1,500.00 | $1,155.00 | $1,200.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 3 | Connection, fused pull apart (625E00450) | EACH | 20 | $200.00 | $145.50 | $180.00 |
| 4 | Connection, unfused pull apart (625E00460) | EACH | 20 | $100.00 | $139.75 | $180.00 |
| 5 | Connection, unfused permanent (625E00480) | EACH | 20 | $100.00 | $145.50 | $180.00 |
| 6 | Transformer base, type at-A (625E02500) | EACH | 8 | $900.00 | $967.25 | $1,200.00 |
| 7 | Transformer base, type at-C (625E02600) | EACH | 8 | $1,000.00 | $1,381.25 | $1,600.00 |
| 8 | Light pole, misc.: lightpole (725.21), 30' height (625E10500) | EACH | 2 | $3,500.00 | $6,267.80 | $6,500.00 |
| 9 | Light pole, misc.: lightpole (725.21), 33'-6" heig (625E10500) | EACH | 5 | $3,500.00 | $6,561.05 | $7,500.00 |
| 10 | Light pole, misc.: lightpole (725.21), 50' height (625E10500) | EACH | 1 | $6,000.00 | $4,649.75 | $6,000.00 |
| 11 | Light pole, misc.: lightpole (725.21), VGCS, 20'-5 (625E10500) | EACH | 2 | $9,500.00 | $4,805.00 | $10,000 |
| 12 | Light pole (installation only), as per plan (625E10503) | EACH | 5 | $2,000.00 | $895.00 | $1,600.00 |
| 13 | Light pole (installation only), as per plan (625E10503) | EACH | 1 | $2,000.00 | $895.00 | $1,500.00 |
| 14 | Erecting reusable downed light pole (625E10504) | EACH | 15 | $700.00 | $952.50 | $2,500.00 |
| 15 | Erecting reusable downed light pole (625E10504) | EACH | 5 | $700.00 | $952.50 | $2,000.00 |
| 16 | Light pole foundation, as per plan (625E14501) | EACH | 5 | $2,500.00 | $2,135.00 | $4,500.00 |
| 17 | Bracket arm, misc.:bracket arm (625E18600) | EACH | 10 | $1,500.00 | $3,024.70 | $3,000.00 |
| 18 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 3,300 | $5.00 | $5.68 | $5.00 |
| 19 | No. 4 AWG 2400 volt distribution cable, as per plan (625E23201) | FT | 500 | $5.00 | $5.68 | $6.00 |
| 20 | No. 10 AWG pole and bracket cable, as per plan (625E23401) | FT | 1,000 | $1.50 | $2.83 | $3.00 |
| 21 | Conduit, 1-1/2", 725.04 (625E25300) | FT | 25 | $30.00 | $16.15 | $20.00 |
| 22 | Conduit, 2", 725.04 (625E25400) | FT | 20 | $40.00 | $18.45 | $22.00 |
| 23 | Conduit, 2", 725.05 (625E25402) | FT | 20 | $10.00 | $7.29 | $16.00 |
| 24 | Conduit, 3", 725.04 (625E25500) | FT | 20 | $70.00 | $25.05 | $35.00 |
| 25 | Conduit, 3", 725.05 (625E25502) | FT | 20 | $10.00 | $8.04 | $20.00 |
| 26 | Conduit, 3", 725.051 (625E25504) | FT | 415 | $30.00 | $8.15 | $20.00 |
| 27 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 50 | $125.00 | $64.70 | $70.00 |
| 28 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 50 | $575.00 | $744.50 | $750.00 |
| 29 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 10 | $1,500.00 | $2,077.05 | $3,000.00 |
| 30 | Luminaire, low mast, solid state (LED), as per plan (625E26273) | EACH | 20 | $1,000.00 | $1,524.20 | $2,000.00 |
| 31 | Luminaire, underpass, solid state (LED), as per plan (625E27503) | EACH | 30 | $400.00 | $1,217.50 | $900.00 |
| 32 | Luminaire, installation only, as per plan (625E27561) | EACH | 10 | $325.00 | $447.50 | $300.00 |
| 33 | Luminaire, misc.:LED navigational light fixture (625E27600) | EACH | 6 | $500.00 | $2,160.00 | $25,000 |
| 34 | Glare shield, as per plan (625E28001) | EACH | 2 | $325.00 | $187.50 | $250.00 |
| 35 | Pull box removed and replaced (625E31506) | EACH | 9 | $2,000.00 | $1,470.00 | $1,850.00 |
| 36 | Ground rod, as per plan (625E32001) | EACH | 2 | $500.00 | $403.75 | $500.00 |
| 37 | Circuit breaker, tower lighting (625E33100) | EACH | 5 | $275.00 | $807.50 | $1,500.00 |
| 38 | Control center cabinet, complete (625E34450) | EACH | 1 | $6,000.00 | $5,900.00 | $12,000 |
| 39 | Control center cabinet, complete (625E34450) | EACH | 1 | $6,000.00 | $4,490.00 | $10,000 |
| 40 | Control center cabinet, complete (625E34450) | EACH | 2 | $6,000.00 | $5,325.00 | $13,000 |
| 41 | Troubleshooting underground and above ground circuitry problem (625E50100) | EACH | 75 | $600.00 | $1,311.50 | $1,500.00 |
| 42 | Repair integral luminaire lowering mechanism of tower lighting fixture, as per plan (625E50401) | EACH | 1 | $4,000.00 | $3,462.50 | $6,850.00 |
| 43 | Secondary surge protector, as per plan (625E50451) | EACH | 1 | $625.00 | $375.00 | $1,500.00 |
| 44 | Lighting contactor, 100 amp (625E70000) | EACH | 2 | $850.00 | $921.25 | $1,200.00 |
| 45 | Lighting contactor, 60 amp (625E70000) | EACH | 2 | $700.00 | $921.25 | $1,000.00 |
| 46 | Light pole removed, as per plan (625E75401) | EACH | 1 | $800.00 | $606.25 | $900.00 |
| 47 | Lighting, misc.: foundation and pole base inspecti (625E98000) | EACH | 250 | $425.00 | $447.50 | $250.00 |
| 48 | Lighting, misc.:annual operation and inspection of (625E98000) | EACH | 250 | $525.00 | $548.75 | $500.00 |
| 49 | Lighting, misc.:circuit locating (625E98000) | EACH | 100 | $500.00 | $577.50 | $500.00 |
| 50 | Lighting, misc.:photocell, 30 amp (625E98000) | EACH | 1 | $400.00 | $317.50 | $250.00 |
| 51 | Lighting, misc.:photocell, 60 amp (625E98000) | EACH | 2 | $450.00 | $317.50 | $250.00 |
| 52 | Pedestal foundation, as per plan (632E64021) | EACH | 2 | $4,000.00 | $1,326.25 | $1,900.00 |
| 53 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 160 | $60.00 | $80.50 | $85.00 |
| 54 | Maintaining traffic, misc.:double lane closure (614E18000) | EACH | 9 | $1,000.00 | $4,762.50 | $5,875.00 |
| 55 | Maintaining traffic, misc.:ramp closure (614E18000) | EACH | 9 | $1,000.00 | $1,615.00 | $4,500.00 |
| 56 | Maintaining traffic, misc.:roundabout closure (614E18000) | EACH | 5 | $1,000.00 | $2,135.00 | $4,250.00 |
| 57 | Maintaining traffic, misc.:shoulder closure (614E18000) | EACH | 45 | $1,450.00 | $1,270.00 | $2,500.00 |
| 58 | Maintaining traffic, misc.:single lane closure (614E18000) | EACH | 18 | $1,750.00 | $2,765.00 | $5,250.00 |
| 59 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $50,775 | $15,275 | $5,750.00 |
| 60 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $100,000 | $5,775.00 | $6,500.00 |
| 61 | Mobilization, as per plan (624E15001) | EACH | 10 | $1,500.00 | $1,820.00 | $25,000 |
| 62 | Mobilization, as per plan (624E15001) | EACH | 1 | $2,500.00 | $1,820.00 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.