ODOT contract 250528 bid tabulation

KNO-US 62/SR 205-14.32/00.00 (TWO LANE RESURFACING). Let by Ohio DOT on November 13, 2025, KNO. 3 bids received; low bid $3,944,227 by Kokosing Construction Company Inc, -4.4% against the engineer's estimate of $4,127,000.

Owner
Ohio DOT
Letting
13 NOV 2025
Pay items
54
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kokosing Construction Company Inc$3,944,227Low-4.0%
2Shelly Company$4,544,509+15%+10%
3Shelly & Sands Inc$4,821,987+22%+17%
ODOT contract 250528: bids by rank

Engineer's estimate: $4,127,000.

Bid tabulation

LinePay itemUnitQuantity1. Kokosing Construction Company Inc2. Shelly Company3. Shelly & Sands Inc
1Pavement removed, as per plan (202E23001)SY29$60.00$120.00$60.00
2Wearing course removed (202E23500)SY7,226$4.00$10.00$12.00
3Walk removed (202E30000)SF996$6.50$10.00$6.50
4Curb removed (202E32000)FT60$14.00$15.00$14.00
5Excavation (203E10000)CY77$50.00$130.00$150.00
6Preparing subgrade for shoulder paving, as per plan (209E72051)MI15.80$1,400.00$1,375.00$5,500.00
74" concrete walk (608E10000)SF50$24.00$18.00$24.00
88" concrete walk (608E15000)SF256$27.00$22.00$27.00
9Curb ramp (608E52000)SF946$24.00$18.00$24.00
10Detectable warning (608E53020)SF64$25.00$50.00$25.00
11Curb, type 6 (609E26000)FT60$31.00$40.00$31.00
12Catch basin adjusted to grade, as per plan (611E98631)EACH15$1,075.00$1,100.00$1,075.00
13Catch basin reconstructed to grade, as per plan (611E98635)EACH1$1,475.00$1,500.00$1,475.00
14Manhole adjusted to grade (611E99654)EACH18$1,100.00$1,100.00$1,100.00
15Valve box adjusted to grade (638E10800)EACH14$600.00$400.00$600.00
16Pavement repair (253E02000)CY3,100$210.00$315.25$275.00
17Pavement planing, asphalt concrete, 1.50" (254E01000)SY118,500$0.75$2.50$2.50
18Pavement planing, asphalt concrete, 3.00" (254E01000)SY20,772$2.00$5.00$4.00
19Asphalt concrete base, PG64-22, (449) (301E56000)CY64$210.00$285.00$250.00
20Non-tracking tack coat (407E20000)GAL12,713$2.90$4.10$3.25
21Prime coat, as per plan (408E10001)GAL7,365$5.15$5.50$4.50
22Asphalt concrete intermediate course, type 1, (448) (441E50200)CY867$215.00$252.00$225.00
23Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY190$525.00$530.00$750.00
24Stone matrix asphalt concrete, 12.5 MM, PG70-22M, (446), as per plan (443E10001)CY5,760$345.00$308.00$290.00
252" deep joint sealer, as per plan (516E31011)FT312$28.62$32.50$32.50
26Compacted aggregate, as per plan (617E10101)CY1,015$30.00$99.00$70.00
27Rumble stripes, center line (asphalt concrete) (618E43000)MI2.99$2,300.00$2,300.00$3,000.00
28Longitudinal joint preparation (874E21000)MI2.99$2,900.00$8,000.00$2,200.00
29RPM (621E00100)EACH513$36.75$42.00$36.75
30Raised pavement marker removed (621E54000)EACH513$2.00$5.00$15.00
31Edge line, 6" (644E00104)MI16.02$3,510.00$3,510.00$3,510.00
32Center line (644E00300)MI8.47$3,672.00$3,672.00$3,672.00
33Channelizing line, 8" (644E00400)FT110$3.30$3.30$3.30
34Stop line (644E00500)FT683$10.00$10.00$10.00
35Crosswalk line, 12" (644E00620)FT2,057$4.00$4.00$4.00
36School symbol marking, 96" (644E01110)EACH2$830.00$830.00$830.00
37Parking lot stall marking (644E01200)FT2,140$2.25$2.25$2.25
38Lane arrow (644E01300)EACH1$125.00$125.00$125.00
39Word on pavement, 96" (644E01410)EACH1$165.00$165.00$165.00
40Yield line (644E20800)FT30$14.50$14.50$14.50
41Edge line, 6" (646E10010)MI0.20$21,980$21,980$21,980
42Center line (646E10200)MI0.12$36,000$36,000$36,000
43Handicap symbol marking, type B125 (647E20212)EACH2$250.00$250.00$250.00
44Work zone marking sign (614E12460)EACH51$60.00$90.00$100.00
45Asphalt concrete for maintaining traffic (614E13000)CY12$250.00$250.00$750.00
46Work zone center line, class I, 642 paint (614E21100)MI0.83$1,500.00$2,975.00$1,500.00
47Work zone center line, class III, 642 paint (614E21550)MI8.57$900.00$1,075.00$900.00
48Work zone channelizing line, class III, 8", 642 paint (614E23680)FT110$0.90$8.00$0.90
49Work zone stop line, class I, 642 paint (614E26200)FT50$3.00$12.00$3.00
50Work zone stop line, class III, 642 paint (614E26610)FT64$2.50$10.00$2.50
51Premium for contract performance bond and for payment bond (103E05000)LS1$16,000$12,500$20,000
52Maintaining traffic (614E11000)LS1$233,509$310,000$466,000
53Construction layout stakes and surveying (623E10000)LS1$1,300.00$5,000.00$15,500
54Mobilization (624E10000)LS1$197,000$138,500$450,000
ODOT contract 250528: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy