ODOT contract 250548 bid tabulation

CLI-SR 350-00.68 (SPOT PATCHING / PAVEMENT REPAIR). Let by Ohio DOT on December 4, 2025, CLI. 3 bids received; low bid $1,988,672 by Fillmore Construction, -28% against the engineer's estimate of $2,767,000.

Owner
Ohio DOT
Letting
04 DEC 2025
Pay items
28
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Fillmore Construction$1,988,672Low-28%
2John R Jurgensen Company$2,395,263+20%-13%
3Barrett Paving Materials Inc$2,451,500+23%-11%
ODOT contract 250548: bids by rank

Engineer's estimate: $2,767,000.

Bid tabulation

LinePay itemUnitQuantity1. Fillmore Construction2. John R Jurgensen Company3. Barrett Paving Materials Inc
1Preparing subgrade for shoulder paving (209E72050)MI7.02$1,300.00$1,463.27$150.00
2Erosion control (832E30000)EACH1,000$1.00$1.00$1.00
3Pavement repair (253E02000)CY3,000$250.00$280.78$285.00
4Pavement planing, asphalt concrete, 3 inches (254E01000)SY52,629$2.00$3.20$3.75
5Patching planed surface (254E01600)SY2,635$2.00$4.09$6.00
6Non-tracking tack coat (407E20000)GAL7,895$3.50$5.00$3.50
7Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY1,902$208.00$211.08$228.00
8Asphalt concrete intermediate course, type 2, (448) (441E50300)CY2,558$156.00$197.32$205.00
9Compacted aggregate (617E10100)CY212$148.00$140.34$175.00
10Water (617E25000)MGAL5$1.00$7.22$20.00
11Rumble stripes, center line (asphalt concrete) (618E43000)MI2.51$4,000.00$2,725.00$6,000.00
12Longitudinal joint preparation (874E21000)MI2.51$3,000.00$5,990.82$9,000.00
13RPM (621E00100)EACH271$43.00$43.00$50.04
14Raised pavement marker removed (621E54000)EACH271$10.00$12.68$5.00
15Edge line, 6" (644E00104)MI7.20$4,895.00$4,450.00$4,450.00
16Center line (644E00300)MI3.51$5,813.00$5,285.00$5,285.00
17Stop line (644E00500)FT32$16.50$15.00$15.00
18Crosswalk line, 12" (644E00620)FT60$11.00$10.00$10.00
19Work zone center line, class I, 642 paint (614E21100)MI7.02$1,584.00$1,440.00$1,440.00
20Work zone center line, class III, 642 paint (614E21550)MI3.51$1,584.00$1,440.00$1,440.00
21Work zone edge line, class I, 6", 642 paint (614E22110)MI14.40$1,267.00$1,152.00$1,152.00
22Work zone edge line, class III, 6", 642 paint (614E22360)MI7.20$1,267.00$1,152.00$1,152.00
23Work zone stop line, class I, 642 paint (614E26200)FT64$4.10$3.70$3.70
24Work zone stop line, class III, 642 paint (614E26610)FT64$4.10$3.70$3.70
25Premium for contract performance bond and for payment bond (103E05000)LS1$17,500$6,999.15$8,643.56
26Maintaining traffic (614E11000)LS1$50,000$133,404$175,000
27Construction layout stakes and surveying, as per plan (623E10001)LS1$3,500.00$4,919.89$5,000.00
28Mobilization (624E10000)LS1$60,000$112,500$25,000
ODOT contract 250548: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy