ODOT contract 254000 bid tabulation
ASD-/WAY-US 42/SR 301-01.90/05.54 (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, ASD. 2 bids received; low bid $353,092 by Great Lakes Demolition Company, -13% against the engineer's estimate of $405,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Demolition Company | $353,092 | Low | -13% |
| 2 | Crawford Construction Company Inc | $368,200 | +4.0% | -9.0% |
Engineer's estimate: $405,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Demolition Company | 2. Crawford Construction Company Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $14,000 | $8,700.00 |
| 2 | Pavement removed (202E23000) | SY | 218 | $25.00 | $23.40 |
| 3 | Guardrail removed for reuse, as per plan (202E38201) | FT | 162.50 | $43.00 | $65.00 |
| 4 | Removal misc.: fence post (202E98100) | EACH | 4 | $50.00 | $60.00 |
| 5 | Excavation (203E10000) | CY | 215 | $20.00 | $34.30 |
| 6 | Embankment (203E20000) | CY | 384 | $25.00 | $25.00 |
| 7 | Subgrade compaction (204E10000) | SY | 255 | $3.00 | $2.00 |
| 8 | Monument assembly adjusted to grade (623E39500) | EACH | 1 | $1,650.00 | $1,710.00 |
| 9 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,000.00 | $1,543.00 |
| 10 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $1,543.00 |
| 11 | Riprap, type D (601E11000) | SY | 22 | $125.00 | $209.00 |
| 12 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 55 | $60.00 | $92.00 |
| 13 | Rock channel protection, type A with filter (601E32000) | CY | 28 | $160.00 | $156.00 |
| 14 | Rock channel protection, type B with filter (601E32100) | CY | 15 | $140.00 | $213.00 |
| 15 | Soil analysis test (659E00100) | EACH | 4 | $250.00 | $50.00 |
| 16 | Topsoil (659E00300) | CY | 182 | $50.00 | $15.00 |
| 17 | Seeding and mulching (659E10000) | SY | 1,639 | $3.00 | $4.30 |
| 18 | Repair seeding and mulching (659E14000) | SY | 82 | $1.00 | $1.00 |
| 19 | Inter-seeding (659E15000) | SY | 82 | $1.00 | $1.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.24 | $800.00 | $400.00 |
| 21 | Lime (659E31000) | ACRE | 0.34 | $80.00 | $136.00 |
| 22 | Water (659E35000) | MGAL | 9.07 | $1.00 | $5.00 |
| 23 | Slope erosion protection mat, type C (670E00530) | SY | 563 | $5.00 | $7.30 |
| 24 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 |
| 25 | Pipe removed, over 24" diameter (202E35200) | FT | 135 | $35.00 | $80.00 |
| 26 | Special - fill and plug existing conduit (202E70000) | FT | 54 | $25.00 | $64.00 |
| 27 | Aggregate drains (605E31100) | FT | 52 | $20.00 | $19.00 |
| 28 | 36" conduit, type A (611E16200) | FT | 112 | $240.00 | $324.00 |
| 29 | Conduit, bored or jacked 42" (611E96600) | FT | 88 | $725.00 | $1,040.00 |
| 30 | Pavement planing, asphalt concrete, (3.0") (254E01000) | SY | 138 | $20.00 | $46.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 61 | $350.00 | $484.00 |
| 32 | Aggregate base (304E20000) | CY | 64 | $75.00 | $131.00 |
| 33 | Tack coat (407E10000) | GAL | 63 | $4.00 | $3.91 |
| 34 | Prime coat, as per plan (408E10001) | GAL | 25 | $6.00 | $8.00 |
| 35 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 32 | $520.00 | $908.00 |
| 36 | Raised pavement marker removed (621E54000) | EACH | 1 | $80.00 | $180.00 |
| 37 | Edge line, 6", type 1 (642E00104) | MI | 0.05 | $20,260 | $25,900 |
| 38 | Center line, type 1 (642E00300) | MI | 0.03 | $27,015 | $35,590 |
| 39 | Detour signing (614E12420) | LS | 1 | $8,500.00 | $5,220.00 |
| 40 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $12,500 | $4,000.00 |
| 41 | Concrete masonry (602E20000) | CY | 1.84 | $2,200.00 | $3,000.00 |
| 42 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $8,500.00 | $4,000.00 |
| 43 | Concrete masonry (602E20000) | CY | 1.52 | $2,360.00 | $4,500.00 |
| 44 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,500.00 | $4,625.00 |
| 45 | Maintaining traffic (614E11000) | LS | 1 | $8,500.00 | $5,230.00 |
| 46 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,500.00 | $4,768.00 |
| 47 | Mobilization (624E10000) | LS | 1 | $65,000 | $24,100 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.