ODOT contract 258015 bid tabulation

D08-GR FY2026 (GUARDRAIL REBUILDING). Let by Ohio DOT on June 26, 2025, District 8. 1 bid received; low bid $1,494,395 by Lake Erie Construction Company, -2.9% against the engineer's estimate of $1,539,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
71
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lake Erie Construction Company$1,494,395Low-3.0%
ODOT contract 258015: bids by rank

Engineer's estimate: $1,539,000.

Bid tabulation

LinePay itemUnitQuantity1. Lake Erie Construction Company
1Guardrail removed (202E38000)FT2,625$3.20
2Guardrail post removed (202E38700)EACH25$8.00
3Anchor assembly removed, type A, as per plan (202E42001)EACH1$375.00
4Removal misc.:impact attenuator removed with site (202E98100)EACH1$395.00
5Guardrail, type 5 (606E13000)FT250$21.80
6Guardrail, type MGS (606E15050)FT2,000$22.60
7Guardrail, type MGS with long posts (606E15100)FT25$25.60
8Guardrail, barrier design, type 5 (606E15500)FT25$38.40
9Guardrail, barrier design, type MGS (606E15550)FT25$40.80
10Guardrail rebuilt, type MGS (606E16050)FT2,850$22.80
11Guardrail rebuilt, type MGS with long posts (606E16560)FT25$26.40
12Guardrail rebuilt, barrier design, type 5 (606E16600)FT200$39.20
13Guardrail rebuilt, barrier design, type MGS (606E16660)FT25$40.40
14Guardrail post (606E17900)EACH25$75.00
15Anchor assembly, type B (606E26000)EACH1$2,520.00
16Anchor assembly, MGS type B (606E26050)EACH1$2,580.00
17Anchor assembly, MGS type E (MASH 2016) (606E26150)EACH39$3,220.00
18Anchor assembly, type T (606E26500)EACH1$1,125.00
19Anchor assembly, MGS type T (606E26550)EACH4$1,475.00
20Anchor assembly rebuilt, type B, as per plan (606E27841)EACH8$2,320.00
21Anchor assembly rebuilt, MGS type B, as per plan (606E27847)EACH1$2,395.00
22Anchor assembly rebuilt, type E, as per plan (606E27851)EACH60$2,230.00
23Anchor assembly rebuilt, MGS type E, as per plan (606E27861)EACH70$2,475.00
24Anchor assembly rebuilt, type T, as per plan (606E27901)EACH12$950.00
25Anchor assembly rebuilt, MGS type T, as per plan (606E27911)EACH4$1,330.00
26Bridge terminal assembly, type 1 (606E35000)EACH2$1,425.00
27MGS bridge terminal assembly, type 1 (606E35002)EACH1$2,730.00
28Bridge terminal assembly rebuilt, type 1, as per plan (606E35011)EACH3$1,640.00
29MGS bridge terminal assembly rebuilt, type 1, as per plan (606E35013)EACH1$2,320.00
30Bridge terminal assembly rebuilt, type 2, as per plan (606E35111)EACH3$585.00
31MGS bridge terminal assembly rebuilt, type 2, as per plan (606E35113)EACH1$545.00
32Special - cable barrier, anchor repair (606E54950)EACH4$1,320.00
33Special - cable barrier, readjust cable tension (R (606E54950)EACH6$375.00
34Special - cable barrier, tensioning (606E55200)EACH6$395.00
35Special - cable barrier, anchor reconstructed (606E55210)EACH2$2,360.00
36Impact attenuator, type 1 (unidirectional) (606E60002)EACH1$9,125.00
37Impact attenuator, type 1 (bidirectional) (606E60012)EACH6$9,150.00
38Impact attenuator, type 2 (unidirectional)70 MPH, (606E60022)EACH1$32,550
39Impact attenuator, type 2 (bidirectional)70 MPH, 3 (606E60028)EACH1$34,850
40Impact attenuator, type 3 (bidirectional), 60 MPH, (606E60050)EACH1$49,150
41Impact attenuator rebuilt, type 1 (unidirectional), as per plan (606E60061)EACH1$3,320.00
42Impact attenuator rebuilt, type 1 (bidirectional), as per plan (606E60071)EACH2$3,480.00
43Impact attenuator, misc.:belt nose assembly (quard (606E61000)EACH4$2,940.00
44Impact attenuator, misc.:cartridge, type 1 (quadgu (606E61000)EACH20$1,080.00
45Impact attenuator, misc.:cartridge, type 2 (quardg (606E61000)EACH15$1,140.00
46Impact attenuator, misc.:cylinder QE1 (quadguard E (606E61000)EACH2$3,260.00
47Impact attenuator, misc.:cylinder QE2 (quadguard E (606E61000)EACH2$3,495.00
48Impact attenuator, misc.:diaphram assembly (24"-36 (606E61000)EACH5$2,575.00
49Impact attenuator, misc.:diaphram assembly (69"-90 (606E61000)EACH2$3,380.00
50Impact attenuator, misc.:fender panel assembly (QU (606E61000)EACH15$1,535.00
51Impact attenuator, misc.:plastic nose piece (tracc (606E61000)EACH2$595.00
52Guardrail, misc.: guardrail, misc, : type 5 rebuil (606E98000)FT750$23.80
53Guardrail, misc.:type 5 rebuilt using wood post (606E98000)FT7,000$21.20
54Guardrail, misc.:urgent repair (606E98100)EACH35$640.00
55Combination curb and gutter, type 4, as per plan (609E23001)FT54$195.00
56Curb, type 4-C (609E24510)FT25$45.00
57Barrier reflector, type 2, bidirectional (626E00110)EACH100$12.50
58Law enforcement officer with patrol car for assistance (614E11110)HR50$52.00
59Maintenance of traffic, one lane closure on A two lane highway (614E13600)EACH120$125.00
60Maintenance of traffic, one lane closure on A four lane undivided highway (614E13700)EACH10$255.00
61Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800)EACH40$295.00
62Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800)EACH15$300.00
63Maintenance of traffic for shoulder closure (614E13900)EACH325$180.00
64Maintenance of traffic for shoulder closure (614E13900)EACH80$185.00
65Railing (deep beam rail with steel tubular backup and type 1 steel posts), as per plan (517E72205)FT25$132.00
66Railing (deep beam rail with steel tubular backup and type 2 steel posts), as per plan (517E72307)FT25$145.00
67Premium for contract performance bond and for payment bond (103E05000)LS1$12,850
68Mobilization (624E15000)EACH425$375.00
100Special -misc.: concrete barrier end section (690E98000)EACH2$5,820.00
101Special -misc.: class QC1, concrete barrier repair (690E98700)CY20$1,340.00
102Special -misc.: class QC2, superstructure barrier (690E98700)CY10$1,565.00
ODOT contract 258015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy