ODOT contract 260093 bid tabulation

PER-SR 669-00.00 (CHIP SEAL). Let by Ohio DOT on February 19, 2026, PER. 2 bids received; low bid $820,747 by Shelly Company, -16% against the engineer's estimate of $977,000.

Owner
Ohio DOT
Letting
19 FEB 2026
Pay items
21
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly Company$820,747Low-16%
2Henry W Bergman Inc$931,611+14%-5.0%
ODOT contract 260093: bids by rank

Engineer's estimate: $977,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly Company2. Henry W Bergman Inc
1Linear grading (209E60500)MI18.99$1,225.00$400.00
2Pavement repair (253E02000)CY350$355.00$550.00
3Prime coat, as per plan (408E10001)GAL8,915$4.50$5.00
4Aggregate, single chip seal, type A (422E11000)SY110,015$1.11$0.70
5Emulsion, chip seal (422E25000)GAL40,706$3.05$5.45
6Compacted aggregate, as per plan (617E10101)CY1,239$85.00$102.00
7Fog seal (886E11000)GAL16,503$3.05$3.50
8RPM (621E00100)EACH926$34.00$38.00
9Raised pavement marker removed (621E54000)EACH926$16.50$26.00
10Edge line, 6", type 1 (642E00104)MI19.08$695.00$770.00
11Center line, type 1 (642E00300)MI9.11$910.00$1,000.00
12Stop line, type 1 (642E00500)FT64$5.00$6.00
13Removal of pavement marking (642E30000)FT64$9.50$5.00
14Removal of pavement marking (642E30030)MI28.19$1,280.00$1,000.00
15Work zone marking sign (614E12460)EACH32$86.00$100.00
16Work zone center line, class III, 642 paint (614E21550)MI27.33$760.67$800.00
17Work zone stop line, class III, 642 paint (614E26610)FT192$4.33$10.00
18Premium for contract performance bond and for payment bond (103E05000)LS1$4,000.00$10,000
19Maintaining traffic (614E11000)LS1$75,000$20,000
20Construction layout stakes and surveying (623E10000)LS1$2,500.00$5,000.00
21Mobilization (624E10000)LS1$20,000$30,000
ODOT contract 260093: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy