ODOT contract 260100 bid tabulation
VAN-Fox Road Walk Connections (SIDEWALK). Let by Ohio DOT on February 19, 2026, VAN. 3 bids received; low bid $343,076 by Oglesby Construction Inc, -29% against the engineer's estimate of $485,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Oglesby Construction Inc | $343,076 | Low | -29% |
| 2 | D L Smith Concrete LLC | $511,763 | +49% | +6.0% |
| 3 | Smith Paving & Excavating Inc | $529,278 | +54% | +9.0% |
Engineer's estimate: $485,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Oglesby Construction Inc | 2. D L Smith Concrete LLC | 3. Smith Paving & Excavating Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $500.00 | $4,000.00 | $5,000.00 |
| 2 | Walk removed (202E30000) | SF | 456 | $3.00 | $5.00 | $15.00 |
| 3 | Curb removed (202E32000) | FT | 243 | $8.00 | $15.00 | $24.00 |
| 4 | Fence removed (202E75000) | FT | 14 | $40.00 | $8.50 | $8.50 |
| 5 | Excavation (203E10000) | CY | 349 | $50.00 | $53.00 | $24.00 |
| 6 | Embankment (203E20000) | CY | 209 | $30.00 | $53.00 | $30.00 |
| 7 | Subgrade compaction (204E10000) | SY | 3,698 | $1.00 | $1.00 | $1.00 |
| 8 | Proof rolling (204E45000) | HR | 4 | $200.00 | $75.00 | $90.00 |
| 9 | Fence removed and rebuilt (607E35000) | FT | 83 | $100.00 | $62.00 | $62.00 |
| 10 | Gate, type 47 (607E40500) | EACH | 2 | $600.00 | $1,780.00 | $1,780.00 |
| 11 | 4" concrete walk (608E10000) | SF | 24,771 | $5.25 | $9.00 | $8.10 |
| 12 | Curb ramp (608E52000) | SF | 1,708 | $16.00 | $9.00 | $8.10 |
| 13 | Walkway, misc.: ADA domes (608E98000) | SF | 36 | $40.00 | $125.00 | $35.00 |
| 14 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 463 | $37.00 | $48.00 | $64.00 |
| 15 | Topsoil (659E00300) | CY | 290 | $45.00 | $70.00 | $68.00 |
| 16 | Seeding and mulching (659E10000) | SY | 2,622 | $2.00 | $3.75 | $2.00 |
| 17 | Repair seeding and mulching (659E14000) | SY | 131 | $1.00 | $0.90 | $3.00 |
| 18 | Inter-seeding (659E15000) | SY | 131 | $1.50 | $0.10 | $3.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.35 | $175.00 | $350.00 | $1,500.00 |
| 20 | Water (659E35000) | MGAL | 14 | $1.00 | $1.00 | $10.00 |
| 21 | Storm water pollution prevention plan (832E15000) | LS | 1 | $1,325.00 | $1,800.00 | $2,550.00 |
| 22 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $9,000.00 | $7,500.00 | $1,000.00 |
| 23 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $5,545.00 | $6,000.00 | $3,850.00 |
| 24 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 25 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,000.00 | $2,350.00 | $1,800.00 |
| 26 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 2 | $2,000.00 | $3,350.00 | $2,300.00 |
| 27 | Aggregate base (304E20000) | CY | 373 | $48.00 | $68.00 | $88.00 |
| 28 | Aggregate base (304E20000) | CY | 58 | $48.00 | $68.00 | $85.00 |
| 29 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 315 | $73.50 | $118.00 | $105.00 |
| 30 | Water (616E10000) | MGAL | 2 | $1.00 | $1.00 | $10.00 |
| 31 | Valve box adjusted to grade (638E10800) | EACH | 2 | $300.00 | $685.00 | $260.00 |
| 32 | Manhole adjusted to grade (611E99654) | EACH | 8 | $750.00 | $1,200.00 | $580.00 |
| 33 | Pull box, misc.: adjusted to grade (625E31600) | EACH | 3 | $600.00 | $1,050.00 | $925.00 |
| 34 | Ground mounted support, no. 3 post (630E03100) | FT | 23 | $40.00 | $45.00 | $45.00 |
| 35 | Sign, flat sheet (630E80100) | SF | 5 | $50.00 | $65.00 | $65.00 |
| 36 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $300.00 | $60.00 | $60.00 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $300.00 | $20.00 | $20.00 |
| 38 | Stop line (644E00500) | FT | 12 | $10.00 | $11.00 | $11.00 |
| 39 | Crosswalk line, 24" (644E00630) | FT | 734 | $10.00 | $11.00 | $11.00 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $3,000.00 | $10,000 | $45,000 |
| 41 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,000.00 | $7,000.00 | $5,000.00 |
| 42 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,700.00 | $3,500.00 | $4,500.00 |
| 43 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,500.00 | $2,500.00 | $2,000.00 |
| 44 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,500.00 | $2,500.00 | $2,000.00 |
| 45 | Mobilization (624E10000) | LS | 1 | $2,000.00 | $13,000 | $40,000 |
| 46 | Special - preconstruction video (900E17000) | LS | 1 | $1,000.00 | $850.00 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.