ODOT contract 260136 bid tabulation
STA-SR 93/VAR-19.26/VAR (FOUR LANE RESURFACING). Let by Ohio DOT on March 12, 2026, STA. 5 bids received; low bid $2,799,942 by Shelly Company, -9.2% against the engineer's estimate of $3,084,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $2,799,942 | Low | -9.0% |
| 2 | Kenmore Construction Co Inc | $2,855,819 | +2.0% | -7.0% |
| 3 | Karvo Companies Inc | $2,978,080 | +6.0% | -3.0% |
| 4 | Northstar Asphalt Inc | $3,075,010 | +10% | 0.0% |
| 5 | Superior Paving & Materials Inc | $3,222,408 | +15% | +4.0% |
Engineer's estimate: $3,084,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Kenmore Construction Co Inc | 3. Karvo Companies Inc | 4. Northstar Asphalt Inc | 5. Superior Paving & Materials Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (203E10000) | CY | 10 | $30.00 | $35.00 | $15.00 | $40.00 | $115.00 |
| 2 | Linear grading (209E60200) | STA | 194 | $50.00 | $70.00 | $50.00 | $60.00 | $7.00 |
| 3 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 10 | $1,200.00 | $1,800.00 | $1,800.00 | $2,000.00 | $1,900.00 |
| 4 | Special - as-built construction plans (690E91000) | LS | 1 | $7,500.00 | $3,000.00 | $1,000.00 | $8,000.00 | $2,500.00 |
| 5 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 6 | Catch basin adjusted to grade (611E98630) | EACH | 20 | $1,100.00 | $440.00 | $1,500.00 | $2,000.00 | $1,300.00 |
| 7 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 35 | $1,500.00 | $2,200.00 | $1,800.00 | $1,800.00 | $1,700.00 |
| 8 | Special - miscellaneous metal (611E99820) | LB | 800 | $5.00 | $4.00 | $4.00 | $4.00 | $2.00 |
| 9 | Partial depth pavement repair (441) (251E01000) | SY | 100 | $90.00 | $30.00 | $100.00 | $60.00 | $32.00 |
| 10 | Partial depth pavement repair (441) (251E01000) | SY | 900 | $80.00 | $35.00 | $45.00 | $60.00 | $36.00 |
| 12 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 79,151 | $1.65 | $1.85 | $1.50 | $2.00 | $1.90 |
| 13 | Pavement planing, asphalt concrete (T=2.25") (254E01000) | SY | 43,265 | $2.15 | $2.30 | $2.50 | $3.00 | $2.40 |
| 14 | Patching planed surface (254E01600) | SY | 1,250 | $1.00 | $5.00 | $0.25 | $10.00 | $2.50 |
| 15 | Aggregate base (304E20000) | CY | 10 | $60.00 | $60.00 | $25.00 | $80.00 | $65.00 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 14,076 | $3.00 | $5.00 | $2.30 | $3.80 | $3.00 |
| 17 | Prime coat (408E10000) | GAL | 4,352 | $5.00 | $5.00 | $5.00 | $5.00 | $4.00 |
| 18 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 736 | $210.00 | $252.00 | $245.00 | $230.00 | $280.00 |
| 19 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 4,802 | $200.00 | $187.00 | $215.00 | $200.00 | $230.00 |
| 20 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 1,203 | $170.00 | $194.00 | $200.00 | $180.00 | $200.00 |
| 21 | Compacted aggregate, as per plan (617E10101) | CY | 303 | $90.00 | $75.00 | $125.00 | $80.00 | $55.00 |
| 22 | Pavement planing, asphalt concrete, class A (T=1") (897E01010) | SY | 28,468 | $1.75 | $2.25 | $1.15 | $2.00 | $1.70 |
| 23 | Valve box adjusted to grade (638E10800) | EACH | 15 | $700.00 | $400.00 | $1,500.00 | $1,000.00 | $95.00 |
| 24 | RPM (621E00100) | EACH | 387 | $45.00 | $45.00 | $51.50 | $53.00 | $52.00 |
| 25 | Ground mounted support, no. 2 post (630E02100) | FT | 133 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 26 | Sign, flat sheet (630E80100) | SF | 8 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 27 | Sign, flat sheet (630E80100) | SF | 10 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 28 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 29 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 30 | Edge line, 6" (646E10010) | MI | 9.27 | $2,850.00 | $2,850.00 | $2,850.00 | $3,000.00 | $2,850.00 |
| 31 | Lane line, 6" (646E10110) | MI | 1.52 | $1,650.00 | $1,650.00 | $1,650.00 | $1,800.00 | $1,650.00 |
| 32 | Center line (646E10200) | MI | 6.53 | $3,250.00 | $3,250.00 | $3,250.00 | $3,300.00 | $3,250.00 |
| 33 | Channelizing line, 12" (646E10310) | FT | 1,174 | $1.50 | $1.50 | $1.50 | $2.00 | $1.50 |
| 34 | Stop line (646E10400) | FT | 444 | $12.50 | $12.50 | $12.50 | $15.00 | $12.50 |
| 35 | Crosswalk line, 24" (646E10520) | FT | 927 | $12.50 | $12.50 | $12.50 | $15.00 | $12.50 |
| 36 | Railroad symbol marking (646E20000) | EACH | 2 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 37 | Lane arrow (646E20300) | EACH | 33 | $165.00 | $165.00 | $165.00 | $200.00 | $165.00 |
| 38 | Detector loop (632E26500) | EACH | 2 | $1,500.00 | $1,800.00 | $1,500.00 | $1,800.00 | $1,500.00 |
| 39 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 150 | $100.00 | $110.00 | $125.00 | $80.00 | $100.00 |
| 40 | Work zone marking sign (614E12460) | EACH | 25 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $125.00 | $180.00 | $500.00 | $400.00 | $160.00 |
| 42 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $850.00 | $850.00 | $850.00 | $850.00 | $850.00 |
| 43 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 1.92 | $650.00 | $650.00 | $650.00 | $700.00 | $650.00 |
| 44 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 1.52 | $650.00 | $650.00 | $650.00 | $700.00 | $650.00 |
| 45 | Work zone center line, class I, 642 paint (614E21100) | MI | 7.69 | $1,250.00 | $1,250.00 | $1,250.00 | $1,300.00 | $1,250.00 |
| 46 | Work zone center line, class III, 642 paint (614E21550) | MI | 6.53 | $1,250.00 | $1,250.00 | $1,250.00 | $1,300.00 | $1,250.00 |
| 47 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 9.27 | $725.00 | $725.00 | $725.00 | $800.00 | $725.00 |
| 48 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 1,844 | $0.75 | $0.75 | $0.75 | $1.00 | $0.75 |
| 49 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 1,174 | $0.75 | $0.75 | $0.75 | $1.00 | $0.75 |
| 50 | Work zone stop line, class I, 642 paint (614E26200) | FT | 729 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 51 | Work zone stop line, class III, 642 paint (614E26610) | FT | 444 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 52 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $2,580.00 | $15,000 | $2,580.00 | $17,600 | $17,600 |
| 53 | Wearing course removed (202E23500) | SY | 4,684 | $6.00 | $3.00 | $3.50 | $8.00 | $3.36 |
| 54 | Tack coat, 702.13 (407E13900) | GAL | 375 | $6.00 | $5.00 | $2.30 | $4.00 | $2.50 |
| 55 | Non-tracking tack coat (407E20000) | GAL | 281 | $3.00 | $5.00 | $2.30 | $4.00 | $3.00 |
| 56 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 195 | $230.00 | $200.00 | $215.00 | $200.00 | $210.00 |
| 57 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 47 | $58.15 | $50.00 | $60.00 | $60.00 | $60.00 |
| 58 | Elastomeric strip seal without steel extrusions (516E01300) | FT | 52 | $274.25 | $350.00 | $275.00 | $325.00 | $325.00 |
| 59 | Special - patching concrete structure, concrete CU (519E11720) | FT | 418 | $80.25 | $250.00 | $81.00 | $90.00 | $90.00 |
| 60 | Patching concrete bridge deck - type C (519E12304) | SY | 94 | $851.25 | $675.00 | $852.00 | $700.00 | $700.00 |
| 61 | Bridge deck waterproofing asphalt concrete (856E10000) | CY | 260 | $450.00 | $780.00 | $550.00 | $1,300.00 | $1,550.00 |
| 62 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $1,335.00 | $3,000.00 | $1,335.00 | $10,600 | $10,600 |
| 63 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,556 | $10.80 | $12.00 | $11.00 | $16.00 | $16.00 |
| 64 | Removal of existing pavement marking (512E74500) | FT | 1,351 | $4.00 | $4.00 | $4.00 | $2.00 | $2.78 |
| 65 | Removal of existing pavement marking (512E74510) | SF | 14 | $50.00 | $50.00 | $50.00 | $20.00 | $107.14 |
| 66 | Removal of existing pavement marking (512E74520) | EACH | 4 | $150.00 | $150.00 | $150.00 | $100.00 | $750.00 |
| 67 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,096.00 | $3,000.00 | $3,100.00 | $10,600 | $10,600 |
| 68 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $1,032.00 | $3,000.00 | $1,035.00 | $10,600 | $10,600 |
| 69 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $3,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $2,500.00 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $10,000 | $21,300 | $8,000.00 | $15,000 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $229,100 | $125,000 | $183,600 | $120,000 | $175,000 |
| 72 | Field office, type B (619E16010) | MNTH | 6 | $2,500.00 | $3,200.00 | $3,000.00 | $2,500.00 | $2,800.00 |
| 73 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,500.00 | $3,000.00 | $9,000.00 | $10,000 | $2,900.00 |
| 74 | Mobilization (624E10000) | LS | 1 | $100,000 | $100,000 | $162,380 | $70,000 | $65,000 |
| 100 | Pavement repair (253E01000) | SY | 75 | $200.00 | $105.00 | $200.00 | $150.00 | $180.00 |
| 101 | Pavement repair (253E01000) | SY | 75 | $200.00 | $92.00 | $200.00 | $150.00 | $180.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.