ODOT contract 260169 bid tabulation
ATH-Nelsonville Mobility Corridor (SIDEWALK). Let by Ohio DOT on April 9, 2026, ATH. 4 bids received; low bid $655,947 by MC Kee Paving & Sealing LLC, -2.5% against the engineer's estimate of $673,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | MC Kee Paving & Sealing LLC | $655,947 | Low | -3.0% |
| 2 | Axis Civil Construction LLC | $693,827 | +6.0% | +3.0% |
| 3 | Shelly & Sands Inc | $805,983 | +23% | +20% |
| 4 | Sunesis Construction Co | $845,650 | +29% | +26% |
Engineer's estimate: $673,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. MC Kee Paving & Sealing LLC | 2. Axis Civil Construction LLC | 3. Shelly & Sands Inc | 4. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $3,500.00 | $2,705.00 | $3,776.92 |
| 2 | Pavement removed (202E23000) | SY | 665 | $20.00 | $19.00 | $44.00 | $29.80 |
| 3 | Walk removed (202E30000) | SF | 32,139 | $3.25 | $2.20 | $2.15 | $2.68 |
| 4 | Curb removed (202E32000) | FT | 729 | $22.00 | $12.00 | $26.75 | $12.28 |
| 5 | Excavation (203E10000) | CY | 25 | $45.00 | $90.00 | $85.00 | $89.31 |
| 6 | Embankment (203E20000) | CY | 25 | $45.00 | $90.00 | $57.00 | $88.78 |
| 7 | 4" concrete walk (608E10000) | SF | 27,582 | $7.75 | $7.80 | $6.90 | $9.95 |
| 8 | Curb ramp (608E52000) | SF | 3,640 | $24.00 | $24.00 | $25.50 | $24.08 |
| 9 | Detectable warning (608E53020) | SF | 457 | $30.00 | $35.00 | $53.25 | $60.00 |
| 10 | Combination curb and gutter, type 2 (609E12000) | FT | 82 | $65.00 | $60.00 | $133.50 | $79.99 |
| 11 | Curb, type 6, as per plan (609E26001) | FT | 645 | $45.00 | $60.00 | $132.00 | $126.10 |
| 12 | Special - gas valve box adjusted to grade (611E99700) | EACH | 7 | $350.00 | $500.00 | $440.50 | $105.77 |
| 13 | Valve box adjusted to grade (638E10800) | EACH | 56 | $300.00 | $500.00 | $436.00 | $68.89 |
| 14 | Soil analysis test (659E00100) | EACH | 2 | $220.00 | $150.00 | $162.50 | $135.00 |
| 15 | Topsoil (659E00300) | CY | 65 | $65.00 | $65.00 | $285.00 | $515.01 |
| 16 | Seeding and mulching (659E10000) | SY | 1,940 | $2.25 | $2.00 | $3.00 | $7.04 |
| 17 | Repair seeding and mulching (659E14000) | SY | 150 | $2.25 | $2.00 | $2.25 | $0.80 |
| 18 | Inter-seeding (659E15000) | SY | 150 | $2.25 | $2.00 | $2.00 | $0.80 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.20 | $1,500.00 | $1,250.00 | $1,353.00 | $939.00 |
| 20 | Lime (659E31000) | ACRE | 0.50 | $155.00 | $150.00 | $162.50 | $157.88 |
| 21 | Water (659E35000) | MGAL | 15 | $1.00 | $1.00 | $108.25 | $1.00 |
| 22 | Erosion control (832E30000) | EACH | 17,460 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | 4" conduit, type B (611E00100) | FT | 50 | $15.00 | $22.00 | $31.50 | $22.87 |
| 24 | 4" conduit, type C (611E00200) | FT | 50 | $15.00 | $22.00 | $28.50 | $22.87 |
| 25 | 4" conduit, type E (611E00400) | FT | 50 | $15.00 | $22.00 | $28.50 | $29.93 |
| 26 | 4" conduit, type F (611E00406) | FT | 50 | $15.00 | $22.00 | $28.50 | $29.93 |
| 27 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 303 | $85.00 | $150.00 | $165.75 | $109.14 |
| 28 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 347 | $85.00 | $160.00 | $132.75 | $110.98 |
| 29 | Ground mounted support, no. 3 post (630E03100) | FT | 79 | $18.00 | $21.85 | $23.75 | $18.00 |
| 30 | Street name sign support, no. 3 post (630E08520) | FT | 98 | $20.00 | $21.85 | $16.25 | $18.00 |
| 31 | Sign post reflector (630E08600) | EACH | 7 | $50.00 | $62.91 | $68.00 | $65.00 |
| 32 | Sign, flat sheet (630E80100) | SF | 80 | $28.00 | $23.67 | $38.00 | $20.00 |
| 33 | Removal of ground mounted sign and disposal (630E84900) | EACH | 14 | $25.00 | $16.56 | $18.00 | $25.00 |
| 34 | Removal of ground mounted sign and reerection (630E85100) | EACH | 12 | $75.00 | $66.73 | $72.25 | $55.00 |
| 35 | Removal of ground mounted post support and disposal (630E86002) | EACH | 24 | $25.00 | $22.08 | $24.00 | $30.00 |
| 36 | Stop line, type 1 (642E00500) | FT | 219 | $13.00 | $5.00 | $5.50 | $8.72 |
| 37 | Crosswalk line, 12", type 1 (642E00620) | FT | 2,030 | $6.50 | $3.00 | $3.25 | $5.45 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,800.00 | $7,500.00 | $4,351.00 | $5,342.31 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $8,500.00 | $15,000 | $31,434 | $13,916 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $8,500.00 | $8,154.00 | $7,000.00 |
| 41 | Mobilization (624E10000) | LS | 1 | $15,000 | $22,000 | $43,510 | $52,068 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.