ODOT contract 260200 bid tabulation
HAM-Madeira SRTS 2023 (SIDEWALK). Let by Ohio DOT on April 23, 2026, HAM. 2 bids received; low bid $393,935 by Prus Construction Company, +5.3% against the engineer's estimate of $374,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 52
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Prus Construction Company | $393,935 | Low | +5.0% |
| 2 | Sunesis Construction Co | $423,923 | +8.0% | +13% |
Engineer's estimate: $374,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Prus Construction Company | 2. Sunesis Construction Co |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $7,500.00 | $12,899 |
| 2 | Pavement removed (202E23000) | SY | 298 | $37.75 | $38.39 |
| 3 | Walk removed (202E30000) | SF | 372 | $5.75 | $3.55 |
| 4 | Curb removed (202E32000) | FT | 467 | $18.25 | $44.64 |
| 5 | Removal misc.:ground mounted address post, remove (202E98100) | EACH | 2 | $430.00 | $100.43 |
| 6 | Excavation (203E10000) | CY | 334 | $53.00 | $128.16 |
| 7 | Embankment (203E20000) | CY | 23 | $61.00 | $127.41 |
| 8 | Subgrade compaction (204E10000) | SY | 1,142 | $3.00 | $3.93 |
| 9 | Proof rolling (204E45000) | HR | 3 | $145.00 | $451.10 |
| 10 | 5" concrete walk (608E12000) | SF | 8,077 | $11.50 | $10.52 |
| 11 | Curb ramp (608E52000) | SF | 500 | $27.50 | $42.53 |
| 12 | Curb ramp, as per plan (608E52001) | SF | 273 | $20.75 | $24.78 |
| 13 | Topsoil (659E00300) | CY | 90 | $115.00 | $104.30 |
| 14 | Seeding and mulching (659E10000) | SY | 805 | $5.50 | $5.06 |
| 15 | Repair seeding and mulching (659E14000) | SY | 41 | $1.10 | $2.50 |
| 16 | Inter-seeding (659E15000) | SY | 41 | $0.01 | $2.50 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.11 | $1,650.00 | $1,400.00 |
| 18 | Lime (659E31000) | ACRE | 0.17 | $220.00 | $55.00 |
| 19 | Water (659E35000) | MGAL | 4.50 | $1.10 | $2.00 |
| 20 | Erosion control (832E30000) | EACH | 7,700 | $1.00 | $1.00 |
| 21 | Conduit, misc.:pipe removed and replaced (611E97400) | FT | 168 | $72.50 | $51.74 |
| 22 | Manhole adjusted to grade (611E99654) | EACH | 4 | $767.00 | $476.63 |
| 23 | Pavement repair, as per plan (253E02001) | CY | 48 | $515.00 | $839.62 |
| 24 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 4 | $545.00 | $750.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 2 | $10.00 | $500.00 |
| 26 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 1 | $785.00 | $100.00 |
| 27 | Asphalt concrete intermediate course, type 1, (449), (driveways) (441E70600) | CY | 1 | $775.00 | $100.00 |
| 28 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 278 | $122.00 | $102.47 |
| 29 | Combination curb and gutter, type 2 (609E12000) | FT | 31 | $70.00 | $81.88 |
| 30 | Curb, type 3-B (609E22000) | FT | 311 | $62.50 | $59.92 |
| 31 | Curb, type 6 (609E26000) | FT | 66 | $58.00 | $52.19 |
| 32 | Valve box adjusted to grade (638E10800) | EACH | 15 | $630.00 | $33.47 |
| 33 | Special - gas valve box adjusted to grade (611E99700) | EACH | 5 | $670.00 | $40.17 |
| 34 | Ground mounted support, no. 3 post (630E03100) | FT | 168 | $17.00 | $15.50 |
| 35 | Sign post reflector (630E08600) | EACH | 2 | $60.50 | $55.00 |
| 36 | Sign, flat sheet (630E80100) | SF | 16.60 | $17.50 | $16.00 |
| 37 | Removal of ground mounted sign and reerection (630E85100) | EACH | 16 | $22.00 | $45.00 |
| 38 | Removal of ground mounted post support and disposal (630E86002) | EACH | 12 | $27.50 | $25.00 |
| 39 | Removal of pole mounted sign and disposal (630E87500) | EACH | 4 | $22.00 | $20.00 |
| 40 | Removal of pavement marking (642E30000) | FT | 73 | $31.00 | $30.55 |
| 41 | Stop line (644E00500) | FT | 11 | $11.00 | $22.85 |
| 42 | Crosswalk line, 12" (644E00620) | FT | 62 | $6.00 | $11.40 |
| 43 | Crosswalk line, 24" (644E00630) | FT | 154 | $11.00 | $18.30 |
| 44 | Pavement marking, misc.:crosswalk pattern (644E50200) | SF | 256 | $40.00 | $19.45 |
| 45 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 2 | $935.00 | $850.25 |
| 46 | Accessible pedestrian pushbutton (632E20750) | EACH | 2 | $2,035.00 | $1,850.00 |
| 47 | Water (616E10000) | MGAL | 0.34 | $1,010.00 | $17.12 |
| 48 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,060.00 | $3,007.57 |
| 49 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $40,250 | $10,434 |
| 50 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,850.00 | $12,000 |
| 51 | Mobilization (624E10000) | LS | 1 | $10,000 | $31,280 |
| 100 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $132.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.