ODOT contract 260203 bid tabulation

HUR-AC&Y Trail Phase II (BIKEWAYS). Let by Ohio DOT on April 23, 2026, HUR. 3 bids received; low bid $1,583,058 by Mark Haynes Construction Inc, -11% against the engineer's estimate of $1,783,000.

Owner
Ohio DOT
Letting
23 APR 2026
Pay items
71
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Mark Haynes Construction Inc$1,583,058Low-11%
2Buckeye Excavating & Construction Inc$1,911,054+21%+7.0%
3Marks Construction Inc$2,067,615+31%+16%
ODOT contract 260203: bids by rank

Engineer's estimate: $1,783,000.

Bid tabulation

LinePay itemUnitQuantity1. Mark Haynes Construction Inc2. Buckeye Excavating & Construction Inc3. Marks Construction Inc
1Clearing and grubbing, as per plan (201E11001)LS1$9,600.00$20,000$40,000
2Walk removed (202E30000)SF90$16.00$2.00$10.00
3Curb and gutter removed (202E32500)FT89$14.00$7.00$20.00
4Guardrail removed for reuse (202E38200)FT62.50$4.50$17.00$10.00
5Special - pipe cleanout, 24" and under (202E70110)FT100$4.50$10.00$35.00
6Excavation (203E10000)CY3,705$13.75$30.00$16.00
7Embankment (203E20000)CY2,952$21.75$32.00$12.00
8Roadway, misc.: surface compaction (203E98100)SY28,571$0.60$1.00$2.00
9Roadway, misc.: trailhead kiosk (203E98600)EACH1$3,750.00$23,300$10,000
10Subgrade compaction (204E10000)SY25,450$0.60$1.00$2.00
11Excavation of subgrade (204E13000)CY200$27.00$24.00$20.00
12Granular embankment (204E21000)CY200$56.50$70.00$90.00
13Geotextile fabric (204E50000)SY200$4.00$5.00$4.00
14Ditch cleanout, as per plan (209E10001)FT1,000$16.00$6.00$12.00
15Linear grading, as per plan (209E60501)MI6.96$8,280.00$12,700$10,000
16Guardrail rebuilt, as per plan (606E16001)FT62.50$56.50$45.20$54.24
17Fence, misc.: bikeway rail (607E98000)FT530$64.40$51.50$57.50
184" concrete walk (608E10000)SF2,295$17.00$15.00$8.00
19Curb ramp, as per plan (608E52001)SF4,781$17.00$16.00$17.00
20Water (616E10000)MGAL27$3.00$60.00$50.00
21Special - concrete parking block (690E50500)EACH8$170.00$200.00$300.00
22Soil analysis test (659E00100)EACH2$125.00$150.00$250.00
23Topsoil (659E00300)CY4,559$18.00$50.00$58.00
24Seeding and mulching (659E10000)SY41,068$1.15$1.60$1.50
25Repair seeding and mulching (659E14000)SY2,054$1.15$5.00$1.50
26Commercial fertilizer (659E20000)TON5.54$1,062.50$500.00$1,100.00
27Lime (659E31000)ACRE8.49$43.75$300.00$209.00
28Water (659E35000)MGAL222$1.25$60.00$105.00
29Slope erosion protection (670E00500)SY8,678$2.25$2.50$4.10
30Storm water pollution prevention plan (832E15000)LS1$3,625.00$1,775.00$2,062.50
31Storm water pollution prevention inspections (832E15002)LS1$3,125.00$13,125$8,250.00
32Storm water pollution prevention inspection software (832E15010)LS1$7,000.00$10,375$11,412
33Erosion control (832E30000)EACH25,000$1.00$1.00$1.00
34Concrete masonry (602E20000)CY0.94$1,250.00$5,000.00$3,000.00
358" conduit, type E (611E02500)FT50$68.50$35.00$69.00
3612" conduit, type A (611E04200)FT100$71.00$80.00$75.76
3712" conduit, type E (611E05100)FT100$71.00$50.00$70.00
3815" conduit, type C (611E06100)FT100$70.00$55.00$75.76
39Asphalt concrete base, PG64-22, (449) (301E56000)CY108$250.00$377.00$295.90
40Aggregate base (304E20000)CY6,100$74.00$70.00$88.85
41Tack coat (407E10000)GAL77$3.00$2.00$2.50
42Prime coat (408E10000)GAL254$8.00$3.00$3.35
43Stabilized crushed aggregate, as per plan (411E10001)CY1,947$93.00$78.00$90.00
44Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY23$475.00$513.00$438.90
45Asphalt concrete intermediate course, type 2, (448) (441E50300)CY31$406.25$434.00$356.45
46Combination curb and gutter, type 2, as per plan (609E12001)FT77$67.00$67.00$50.00
47Ground mounted support, no. 3 post (630E03100)FT1,216.50$17.50$17.00$15.40
48Ground mounted support, no. 4 post (630E04100)FT72.70$20.00$21.00$17.60
49Sign post reflector (630E08600)EACH27$68.75$59.00$60.60
50Sign, flat sheet (630E80100)SF712.60$22.50$18.00$19.79
51Removal of ground mounted sign and disposal (630E84900)EACH95$54.50$17.00$27.50
52Removal of ground mounted sign and reerection (630E85100)EACH11$219.50$65.00$104.50
53Removal of ground mounted post support and disposal (630E86002)EACH61$73.80$23.00$33.00
54Signing, misc.: bicycle pedestrian sign (630E97700)EACH3$3,333.75$350.00$2,933.70
55Signing, misc.: solar-powered rectangular rapid FL (630E97700)EACH2$14,375$12,000$12,075
56Signing, misc.: solar-powered rectangular rapid FL (630E97700)EACH2$21,406$13,000$17,981
57Stop line, type 1 (642E00500)FT47$6.25$7.00$5.50
58Crosswalk line, 18", type 1, as per plan (enhanced (642E00627)FT1,095$12.50$17.00$11.00
59Crosswalk line, 18", type 1, as per plan (yielded (642E00627)FT229$12.50$19.00$11.00
60Chevron marking, type 1 (642E00720)FT46$3.75$14.00$3.60
61Parking lot stall marking, type 1 (642E01200)FT189$6.25$1.50$5.50
62Word on pavement, 96", type 1 (642E01410)EACH14$118.75$100.00$104.50
63Bike lane symbol marking, type 1 (642E01602)EACH14$118.75$50.00$104.50
64Handicap symbol marking, type 1 (642E01702)EACH2$193.75$110.00$372.00
65Yield line, type 1 (642E20802)FT48$7.50$7.00$51.00
66Stop line (644E00500)FT72$68.75$9.00$60.50
67Special - bollard (690E50600)EACH44$184.00$72.00$137.50
68Premium for contract performance bond and for payment bond (103E05000)LS1$11,298$16,000$55,000
69Maintaining traffic (614E11000)LS1$15,000$20,000$10,000
70Construction layout stakes and surveying (623E10000)LS1$34,375$28,000$29,700
71Mobilization (624E10000)LS1$25,000$90,000$82,000
ODOT contract 260203: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy