ODOT contract 260255 bid tabulation
CLA-/MOT BH FY27 (BRIDGE REPAIR). Let by Ohio DOT on May 7, 2026, CLA. 3 bids received; low bid $636,706 by Ruhlin Company, -27% against the engineer's estimate of $870,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 35
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ruhlin Company | $636,706 | Low | -27% |
| 2 | Evers Steel Construction LLC | $936,710 | +47% | +8.0% |
| 3 | Vimas Painting Company Inc | $1,162,450 | +83% | +34% |
Engineer's estimate: $870,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ruhlin Company | 2. Evers Steel Construction LLC | 3. Vimas Painting Company Inc |
|---|---|---|---|---|---|---|
| 1 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $100.00 | $70.00 | $140.00 |
| 2 | Portable changeable message sign, as per plan (614E18601) | SNMT | 2 | $925.00 | $2,100.00 | $2,200.00 |
| 3 | Structural steel, misc.:repair of damaged secondar (513E90000) | LB | 332 | $55.00 | $25.00 | $100.00 |
| 4 | Structural steel, misc.:repair of damaged main mat (513E95000) | FT | 1 | $7,002.00 | $200.00 | $15,000 |
| 5 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 278 | $140.00 | $140.00 | $320.00 |
| 6 | Damage assessment, as per plan (849E10001) | LS | 1 | $5,268.03 | $3,500.00 | $5,500.00 |
| 7 | Surface preparation (849E10500) | LS | 1 | $5,000.00 | $3,500.00 | $20,000 |
| 8 | Repairing damaged members by grinding (849E10600) | HR | 3 | $295.00 | $215.00 | $900.00 |
| 9 | Straightening damaged members (849E10700) | LS | 1 | $10,500 | $65,000 | $40,000 |
| 10 | Concrete repair by epoxy injection (512E10600) | FT | 43 | $245.00 | $150.00 | $400.00 |
| 11 | Structural steel, misc.:repair of damaged secondar (513E90000) | LB | 631 | $55.00 | $25.00 | $100.00 |
| 12 | Structural steel, misc.:repair of damaged main mat (513E95000) | FT | 1 | $7,002.00 | $200.00 | $15,000 |
| 13 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 615 | $125.00 | $80.00 | $220.00 |
| 14 | Damage assessment, as per plan (849E10001) | LS | 1 | $5,268.03 | $3,500.00 | $5,500.00 |
| 15 | Surface preparation (849E10500) | LS | 1 | $5,000.00 | $3,500.00 | $40,000 |
| 16 | Repairing damaged members by grinding (849E10600) | HR | 6 | $295.00 | $215.00 | $800.00 |
| 17 | Straightening damaged members (849E10700) | LS | 1 | $40,000 | $158,000 | $85,000 |
| 18 | Structural steel, misc.:repair of damaged main mat (513E90000) | LB | 134 | $228.00 | $100.00 | $340.00 |
| 19 | Structural steel, misc.:repair of damaged secondar (513E90000) | LB | 72 | $135.00 | $25.00 | $220.00 |
| 20 | Structural steel, misc.:repair of damaged main mat (513E95000) | FT | 1 | $22,500 | $200.00 | $15,000 |
| 21 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 70 | $400.00 | $400.00 | $740.00 |
| 22 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $15,000 | $14,000 | $12,500 |
| 23 | Damage assessment, as per plan (849E10001) | LS | 1 | $5,268.03 | $3,500.00 | $5,500.00 |
| 24 | Surface preparation (849E10500) | LS | 1 | $5,000.00 | $3,500.00 | $15,000 |
| 25 | Repairing damaged members by grinding (849E10600) | HR | 1 | $295.00 | $215.00 | $850.00 |
| 26 | Straightening damaged members (849E10700) | LS | 1 | $10,500 | $28,000 | $10,000 |
| 27 | Structural steel, misc.:repair of damaged secondar (513E90000) | LB | 108 | $100.00 | $25.00 | $115.00 |
| 28 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 60 | $400.00 | $500.00 | $850.00 |
| 29 | Damage assessment, as per plan (849E10001) | LS | 1 | $5,268.03 | $3,500.00 | $5,500.00 |
| 30 | Surface preparation (849E10500) | LS | 1 | $5,000.00 | $3,500.00 | $15,000 |
| 31 | Repairing damaged members by grinding (849E10600) | HR | 1 | $295.00 | $215.00 | $820.00 |
| 32 | Straightening damaged members (849E10700) | LS | 1 | $10,500 | $32,000 | $17,000 |
| 33 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,992.58 | $16,000 | $15,000 |
| 34 | Maintaining traffic (614E11000) | LS | 1 | $125,375 | $215,000 | $220,000 |
| 35 | Mobilization (624E10000) | LS | 1 | $31,800 | $165,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.