ODOT contract 260263 bid tabulation
COS-SR 16-01.40 (CULVERT REPLACEMENT). Let by Ohio DOT on May 21, 2026, COS. 2 bids received; low bid $4,481,615 by Daniel R Schmoldt Enterprises Inc, +12% against the engineer's estimate of $4,000,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Daniel R Schmoldt Enterprises Inc | $4,481,615 | Low | +12% |
| 2 | Turn-Key Tunneling Inc | $4,913,390 | +10% | +23% |
Engineer's estimate: $4,000,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Daniel R Schmoldt Enterprises Inc | 2. Turn-Key Tunneling Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $112,000 | $71,200 |
| 2 | Pavement removed (202E23000) | SY | 745 | $23.00 | $42.00 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 74 | $26.00 | $89.00 |
| 4 | Guardrail removed (202E38000) | FT | 108 | $8.00 | $6.00 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 1 | $500.00 | $1,200.00 |
| 6 | Excavation (203E10000) | CY | 603 | $45.00 | $30.00 |
| 7 | Embankment (203E20000) | CY | 985 | $45.00 | $90.00 |
| 8 | Subgrade compaction (204E10000) | SY | 726 | $5.00 | $2.40 |
| 9 | Excavation of subgrade (204E13000) | CY | 50 | $40.00 | $30.00 |
| 10 | Granular material, type B (204E30010) | CY | 50 | $50.00 | $185.00 |
| 11 | Proof rolling (204E45000) | HR | 1 | $200.00 | $120.00 |
| 12 | Geotextile fabric (204E50000) | SY | 75 | $10.00 | $12.00 |
| 13 | Guardrail, type MGS (606E15050) | FT | 137.50 | $45.00 | $120.00 |
| 14 | Anchor assembly, type T (606E26500) | EACH | 2 | $3,600.00 | $2,400.00 |
| 15 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,800.00 | $6,000.00 |
| 16 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,800.00 | $6,000.00 |
| 17 | Rock channel protection, type A with filter (601E32000) | CY | 251 | $135.00 | $300.00 |
| 18 | Rock channel protection, type B with filter (601E32100) | CY | 29 | $180.00 | $300.00 |
| 19 | Seeding and mulching, class 2 (659E00510) | SY | 1,690 | $2.50 | $12.00 |
| 20 | Seeding and mulching, class 3B (659E00530) | SY | 828 | $3.75 | $24.00 |
| 21 | Repair seeding and mulching (659E14000) | SY | 126 | $1.00 | $0.25 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.35 | $0.51 | $2,400.00 |
| 23 | Lime (659E31000) | ACRE | 0.52 | $0.75 | $2,100.00 |
| 24 | Water (659E35000) | MGAL | 14 | $20.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 45,000 | $1.00 | $1.00 |
| 26 | 12" conduit, type D (611E04900) | FT | 23 | $145.00 | $300.00 |
| 27 | 72" conduit, type A, as per plan, 748.06 (611E26001) | FT | 180 | $1,100.00 | $6,830.00 |
| 28 | Conduit, misc.: geotechnical instrumentation and M (611E97300) | LS | 1 | $60,400 | $76,700 |
| 29 | Conduit, misc.: pilot tube guided auger boring, 72 (611E97400) | FT | 702 | $4,125.00 | $2,870.00 |
| 30 | Full depth pavement sawing (252E01500) | FT | 147 | $2.25 | $60.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 78 | $316.00 | $510.00 |
| 32 | Aggregate base (304E20000) | CY | 135 | $50.00 | $240.00 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 90 | $4.00 | $12.00 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 24 | $475.00 | $660.00 |
| 35 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 33 | $380.00 | $660.00 |
| 36 | Compacted aggregate (617E10100) | CY | 14 | $60.00 | $330.00 |
| 37 | Barrier reflector, type 2, (BI-directional) (626E00110) | EACH | 3 | $20.00 | $60.00 |
| 38 | Ground mounted support, no. 2 post (630E02100) | FT | 51 | $30.00 | $120.00 |
| 39 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 21 | $34.00 | $180.00 |
| 40 | Sign post reflector (630E08600) | EACH | 1 | $55.00 | $61.00 |
| 41 | Sign, flat sheet (630E80100) | SF | 4 | $40.00 | $120.00 |
| 42 | Removal of ground mounted sign and reerection (630E85100) | EACH | 5 | $75.00 | $60.00 |
| 43 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $25.00 | $1.00 |
| 44 | Stop line (644E00500) | FT | 30 | $35.00 | $2,400.00 |
| 45 | Detour signing (614E12420) | LS | 1 | $5,000.00 | $18,000 |
| 46 | Water (616E10000) | MGAL | 3 | $10.00 | $1.00 |
| 47 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $357,200 | $72,000 |
| 48 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $13,500 | $72,000 |
| 49 | Galvanized steel reinforcement (509E26000) | LB | 22,217 | $3.75 | $8.00 |
| 50 | Class QC1 concrete, footing (511E46510) | CY | 97 | $1,680.00 | $1,650.00 |
| 51 | Class QC1 concrete, headwall (511E46610) | CY | 54 | $1,680.00 | $1,920.00 |
| 52 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 129 | $36.00 | $120.00 |
| 53 | Porous backfill with geotextile fabric, as per plan (518E21201) | CY | 45 | $130.00 | $330.00 |
| 54 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,500.00 | $13,000 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $109,308 | $72,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $1,400.00 | $60,000 |
| 57 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $15,000 | $30,000 |
| 58 | Mobilization (624E10000) | LS | 1 | $85,000 | $134,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.