ODOT contract 260333 bid tabulation
TRU-SR 46-00.50 (Sidewalks) (SIDEWALK). Let by Ohio DOT on July 16, 2026, TRU. 4 bids received; low bid $383,648 by Foust Construction Inc, -4.1% against the engineer's estimate of $400,000.
- Owner
- Ohio DOT
- Letting
- 16 JUL 2026
- Pay items
- 51
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foust Construction Inc | $383,648 | Low | -4.0% |
| 2 | Daniel A Terreri & Sons Inc | $388,800 | +1.0% | -3.0% |
| 3 | Madex Construction Co | $546,675 | +42% | +37% |
| 4 | Ruhlin Company | $659,981 | +72% | +65% |
Engineer's estimate: $400,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Foust Construction Inc | 2. Daniel A Terreri & Sons Inc | 3. Madex Construction Co | 4. Ruhlin Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $15,000 | $6,000.00 | $11,579 | $5,700.00 |
| 2 | Pavement removed (202E23000) | SY | 27 | $50.00 | $35.00 | $52.11 | $141.00 |
| 3 | Wearing course removed (202E23500) | SY | 5 | $250.00 | $200.00 | $115.79 | $750.00 |
| 4 | Walk removed (202E30000) | SF | 13,437 | $2.00 | $1.00 | $2.89 | $5.00 |
| 5 | Curb removed (202E32000) | FT | 39 | $40.00 | $20.00 | $45.16 | $49.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 10 | $50.00 | $30.00 | $282.12 | $118.00 |
| 7 | Gutter removed, as per plan (202E32601) | FT | 25 | $50.00 | $30.00 | $57.89 | $54.50 |
| 8 | Excavation (203E10000) | CY | 192 | $30.00 | $25.00 | $38.21 | $55.00 |
| 9 | Embankment (203E20000) | CY | 47 | $40.00 | $30.00 | $46.32 | $255.00 |
| 10 | 4" concrete walk (608E10000) | SF | 9,820 | $9.00 | $9.00 | $12.16 | $11.50 |
| 11 | Curb ramp (608E52000) | SF | 483 | $25.50 | $48.00 | $39.37 | $35.00 |
| 12 | Curb ramp, as per plan (608E52001) | SF | 261 | $28.50 | $50.00 | $40.53 | $35.00 |
| 13 | Special - as-built construction plans (690E91000) | LS | 1 | $1,000.00 | $500.00 | $5,789.47 | $1,700.00 |
| 14 | Topsoil (659E00300) | CY | 193 | $65.00 | $75.00 | $81.05 | $105.00 |
| 15 | Seeding and mulching (659E10000) | SY | 1,738 | $4.00 | $3.00 | $5.79 | $3.11 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.23 | $500.00 | $1,000.00 | $2,315.78 | $800.00 |
| 17 | Lime (659E31000) | ACRE | 0.36 | $500.00 | $1,000.00 | $1,157.89 | $0.50 |
| 18 | Water (659E35000) | MGAL | 10 | $2.00 | $10.00 | $70.53 | $0.20 |
| 19 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,000.00 | $1,000.00 | $2,663.16 | $750.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1 | $2,000.00 | $1,000.00 | $1,157.89 | $3,261.00 |
| 22 | Non-tracking tack coat (407E20000) | GAL | 1 | $3.05 | $200.00 | $57.89 | $8.75 |
| 23 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 11 | $1,550.00 | $500.00 | $1,126.32 | $2,960.00 |
| 24 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 139 | $100.00 | $90.00 | $150.53 | $225.00 |
| 25 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 727 | $95.00 | $100.00 | $173.68 | $150.00 |
| 26 | Curb, type 6 (609E26000) | FT | 34 | $40.00 | $60.00 | $98.42 | $150.00 |
| 27 | Compacted aggregate (617E10100) | CY | 1 | $95.00 | $300.00 | $227.37 | $800.00 |
| 28 | Valve box adjusted to grade (638E10800) | EACH | 1 | $150.00 | $500.00 | $1,505.26 | $700.00 |
| 29 | Ground mounted support, no. 3 post (630E03100) | FT | 13 | $83.25 | $84.00 | $98.42 | $83.25 |
| 30 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 5 | $84.46 | $85.00 | $100.74 | $84.46 |
| 31 | Sign post reflector (630E08600) | EACH | 1 | $121.36 | $122.00 | $144.74 | $121.36 |
| 32 | Sign, flat sheet (630E80100) | SF | 6.30 | $84.75 | $85.00 | $99.58 | $84.75 |
| 33 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $16.68 | $17.00 | $19.68 | $16.68 |
| 34 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $129.29 | $130.00 | $156.32 | $129.29 |
| 35 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $22.24 | $23.00 | $28.95 | $22.24 |
| 36 | Removal of pole mounted sign and disposal (630E87500) | EACH | 4 | $16.68 | $17.00 | $20.84 | $16.68 |
| 37 | Removal of pole mounted sign and reerection, as per plan (630E87521) | EACH | 2 | $132.57 | $133.00 | $158.63 | $132.57 |
| 38 | Signing, misc.:removal of reflector (630E97700) | EACH | 2 | $12.57 | $13.00 | $17.37 | $914.25 |
| 39 | Signing, misc.:solar powered rectangular rapid fla (630E97700) | EACH | 2 | $9,372.04 | $9,400.00 | $10,884 | $9,372.04 |
| 40 | Stop line (646E10400) | FT | 24 | $32.10 | $33.00 | $40.53 | $32.10 |
| 41 | Crosswalk line, 24" (646E10520) | FT | 150 | $28.35 | $29.00 | $33.58 | $28.35 |
| 42 | Removal of pavement marking (646E50100) | FT | 70 | $47.95 | $50.00 | $57.89 | $47.95 |
| 43 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $90.00 | $80.00 | $115.79 | $85.00 |
| 44 | Water (616E10000) | MGAL | 0.30 | $1.00 | $500.00 | $70.53 | $86.00 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,000.00 | $6,100.00 | $10,137 | $3,099.85 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $11,948 | $18,000 | $28,947 | $98,000 |
| 47 | Field office, type B (619E16010) | MNTH | 6 | $3,000.00 | $400.00 | $857.89 | $3,200.00 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,855 | $14,500 | $10,421 | $10,000 |
| 49 | Mobilization (624E10000) | LS | 1 | $10,020 | $38,665 | $26,633 | $30,000 |
| 100 | Special - gas valve box adjusted to grade (611E99700) | EACH | 3 | $150.00 | $200.00 | $557.78 | $800.00 |
| 101 | Pull box removed (625E31510) | EACH | 1 | $1,000.00 | $500.00 | $1,158.00 | $850.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.