ODOT contract 260369 bid tabulation
RIC-/WAY-IR 71/SR 226-19.61/05.26 (CULVERT REPLACEMENT). Let by Ohio DOT on August 13, 2026, RIC. 3 bids received; low bid $695,376 by Proshot Concrete Inc, +38% against the engineer's estimate of $504,000.
- Owner
- Ohio DOT
- Letting
- 13 AUG 2026
- Pay items
- 37
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Proshot Concrete Inc | $695,376 | Low | +38% |
| 2 | Madex Construction Co | $997,722 | +43% | +98% |
| 3 | Stanley Miller Construction Company | $1,435,942 | +106% | +185% |
Engineer's estimate: $504,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Proshot Concrete Inc | 2. Madex Construction Co | 3. Stanley Miller Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $28,947 | $75,000 |
| 2 | Guardrail removed for reuse, as per plan (202E38201) | FT | 150 | $60.00 | $13.68 | $75.00 |
| 3 | Special - pipe cleanout over 48" (202E70130) | FT | 355 | $72.00 | $244.17 | $750.00 |
| 4 | Excavation (203E10000) | CY | 62 | $185.00 | $63.68 | $425.00 |
| 5 | Embankment (203E20000) | CY | 5 | $250.00 | $98.42 | $1,000.00 |
| 6 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $15,000 | $8,684.21 | $15,000 |
| 7 | Riprap, type D (601E11000) | SY | 26 | $1,925.00 | $752.63 | $2,400.00 |
| 8 | Rock channel protection, type B with filter (601E32100) | CY | 31 | $807.00 | $439.41 | $600.00 |
| 9 | Soil analysis test (659E00100) | EACH | 4 | $70.00 | $89.47 | $150.00 |
| 10 | Topsoil (659E00300) | CY | 1,117 | $10.00 | $19.53 | $40.00 |
| 11 | Seeding and mulching (659E10000) | SY | 10,054 | $2.90 | $0.97 | $6.00 |
| 12 | Repair seeding and mulching (659E14000) | SY | 504 | $2.00 | $0.97 | $2.00 |
| 13 | Inter-seeding (659E15000) | SY | 504 | $0.20 | $0.47 | $0.50 |
| 14 | Commercial fertilizer (659E20000) | TON | 1.42 | $890.00 | $1,183.18 | $800.00 |
| 15 | Lime (659E31000) | ACRE | 2.09 | $24.00 | $636.84 | $150.00 |
| 16 | Water (659E35000) | MGAL | 57 | $1.00 | $4.53 | $1.00 |
| 17 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 |
| 18 | Conduit, misc.:video log (611E97400) | FT | 355 | $10.00 | $58.95 | $50.00 |
| 19 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $300.00 | $115.79 | $225.00 |
| 20 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $2,670.00 | $2,278.95 | $4,000.00 |
| 21 | Detour signing (614E12420) | LS | 1 | $9,172.00 | $12,684 | $10,000 |
| 22 | Barrier reflector, type 1(one way) (614E13310) | EACH | 20 | $15.00 | $12.37 | $50.00 |
| 23 | Object marker, one way (614E13350) | EACH | 20 | $24.00 | $19.16 | $50.00 |
| 24 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,515.00 | $1,305.26 | $3,000.00 |
| 25 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.20 | $9,000.00 | $8,684.20 | $10,000 |
| 26 | Portable barrier, unanchored (622E41100) | FT | 960 | $53.00 | $32.11 | $63.00 |
| 27 | Removal of pavement marking (642E30000) | FT | 1,060 | $1.80 | $1.54 | $2.00 |
| 28 | Edge line, 6" (644E00104) | MI | 0.20 | $12,000 | $10,579 | $15,000 |
| 29 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $32,105 | $50,000 |
| 30 | Conduit renewal using spray applied structural liner, round conduit (833E10000) | FT | 266 | $832.00 | $1,237.89 | $981.00 |
| 33 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $37,895 | $25,000 |
| 34 | Conduit renewal using spray applied structural liner, round conduit (833E10000) | FT | 89 | $884.00 | $1,643.16 | $1,325.00 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,175 | $42,756 | $15,000 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $27,890 | $60,676 | $45,000 |
| 39 | Field office, type B (619E16010) | MNTH | 3 | $2,000.00 | $736.84 | $500.00 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $19,759 | $25,000 |
| 41 | Mobilization (624E10000) | LS | 1 | $25,000 | $35,922 | $175,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.