ODOT contract 260370 bid tabulation
SEN-US 224-00.00 Resurfacing (TWO LANE RESURFACING). Let by Ohio DOT on August 13, 2026, SEN. 5 bids received; low bid $3,705,852 by M & B Asphalt Co Inc, -18% against the engineer's estimate of $4,494,000.
- Owner
- Ohio DOT
- Letting
- 13 AUG 2026
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M & B Asphalt Co Inc | $3,705,852 | Low | -18% |
| 2 | Gerken Paving Inc | $4,106,707 | +11% | -9.0% |
| 3 | Kokosing Construction Company Inc | $4,148,578 | +12% | -8.0% |
| 4 | Shelly Company | $4,315,081 | +16% | -4.0% |
| 5 | Erie Blacktop Inc | $4,585,967 | +24% | +2.0% |
Engineer's estimate: $4,494,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M & B Asphalt Co Inc | 2. Gerken Paving Inc | 3. Kokosing Construction Company Inc | 4. Shelly Company | 5. Erie Blacktop Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Pavement removed, as per plan (202E23001) | SY | 123 | $75.00 | $71.50 | $95.00 | $78.00 | $150.00 |
| 2 | Anchor assembly removed, type E (202E42010) | EACH | 31 | $185.00 | $185.00 | $185.00 | $185.00 | $194.25 |
| 3 | Embankment (203E20000) | CY | 81 | $95.00 | $95.00 | $95.00 | $95.00 | $99.75 |
| 4 | Reshaping under guardrail (209E15050) | MI | 1 | $3,450.00 | $3,450.00 | $3,450.00 | $3,450.00 | $3,622.50 |
| 5 | Linear grading (209E60500) | MI | 23 | $1,000.00 | $1,900.00 | $2,100.00 | $1,100.00 | $2,250.00 |
| 6 | Preparing subgrade for shoulder paving (209E72050) | MI | 22 | $350.00 | $275.00 | $250.00 | $1,100.00 | $2,250.00 |
| 7 | Anchor assembly, MGS type E (606E26150) | EACH | 31 | $3,280.00 | $3,280.00 | $3,280.00 | $3,280.00 | $3,444.00 |
| 8 | Monument assembly adjusted to grade (623E39500) | EACH | 1 | $1,200.00 | $975.00 | $4,000.00 | $1,200.00 | $975.00 |
| 9 | Crushed aggregate slope protection (601E20010) | CY | 27 | $150.00 | $145.00 | $145.00 | $145.00 | $152.25 |
| 10 | Seeding and mulching (659E10000) | SY | 677 | $3.00 | $3.55 | $6.50 | $2.20 | $6.85 |
| 11 | Commercial fertilizer (659E20000) | TON | 0.10 | $850.00 | $850.00 | $950.00 | $850.00 | $997.50 |
| 12 | Water (659E35000) | MGAL | 4 | $0.10 | $4.00 | $1.00 | $0.10 | $1.05 |
| 13 | Erosion control (832E30000) | EACH | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Pavement repair (253E02000) | CY | 4,429 | $188.00 | $220.00 | $220.00 | $221.00 | $225.00 |
| 15 | Pavement planing, asphalt concrete, 1 1/2" (254E01000) | SY | 201,689 | $1.05 | $1.61 | $1.40 | $2.03 | $1.25 |
| 16 | Asphalt concrete base, (449), as per plan, PG64-22 (301E56001) | CY | 55 | $360.00 | $350.00 | $220.00 | $347.00 | $425.00 |
| 17 | Tack coat (407E10000) | GAL | 11,096 | $2.70 | $2.50 | $3.00 | $2.00 | $2.55 |
| 18 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 8,464 | $224.00 | $215.00 | $220.00 | $239.50 | $268.00 |
| 19 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 557 | $30.00 | $28.44 | $28.44 | $42.00 | $29.85 |
| 20 | Compacted aggregate (617E10100) | CY | 1,983 | $68.00 | $73.00 | $40.00 | $59.00 | $72.00 |
| 21 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 21 | $1,150.00 | $650.00 | $650.00 | $650.00 | $1,000.00 |
| 22 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 12 | $1,500.00 | $1,150.00 | $1,150.00 | $1,150.00 | $1,525.00 |
| 23 | Longitudinal joint preparation (874E20000) | FT | 54,433 | $0.30 | $2.60 | $0.30 | $2.38 | $1.50 |
| 24 | RPM (621E00100) | EACH | 687 | $42.00 | $42.50 | $39.00 | $42.50 | $44.00 |
| 25 | Raised pavement marker removed (621E54000) | EACH | 684 | $6.00 | $5.50 | $2.00 | $5.50 | $6.50 |
| 26 | Barrier reflector, type 5, 50FT spacing, BI-direct (626E00116) | EACH | 31 | $100.00 | $15.00 | $15.00 | $15.00 | $15.75 |
| 27 | Edge line, 6", type 1 (642E00104) | MI | 21 | $800.00 | $800.00 | $800.00 | $1,100.00 | $840.00 |
| 28 | Center line, type 1 (642E00300) | MI | 11 | $800.00 | $800.00 | $990.00 | $800.00 | $840.00 |
| 29 | Channelizing line, 12" (644E00404) | FT | 81 | $4.00 | $4.00 | $1.50 | $4.00 | $4.20 |
| 30 | Stop line (644E00500) | FT | 66 | $8.00 | $8.00 | $10.00 | $8.00 | $8.40 |
| 31 | Transverse/diagonal line (644E00700) | FT | 89 | $8.00 | $8.00 | $10.00 | $8.00 | $8.40 |
| 32 | Railroad symbol marking (644E01000) | EACH | 2 | $700.00 | $700.00 | $400.00 | $700.00 | $735.00 |
| 33 | Lane arrow (644E01300) | EACH | 2 | $125.00 | $125.00 | $150.00 | $125.00 | $132.00 |
| 34 | Speed measurement marking, as per plan (644E40001) | EACH | 10 | $250.00 | $150.00 | $150.00 | $150.00 | $158.00 |
| 35 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $90.00 | $110.00 | $130.00 | $105.00 | $105.00 |
| 36 | Work zone marking sign (614E12460) | EACH | 22 | $175.00 | $125.00 | $100.00 | $100.00 | $105.00 |
| 37 | Replacement sign (614E12500) | EACH | 5 | $80.00 | $125.00 | $200.00 | $200.00 | $210.00 |
| 38 | Work zone center line, class I (614E21000) | MI | 11 | $800.00 | $800.00 | $1,250.00 | $800.00 | $840.00 |
| 39 | Work zone edge line, class I, 6" (614E22010) | MI | 21 | $800.00 | $800.00 | $1,125.00 | $800.00 | $840.00 |
| 40 | Work zone channelizing line, class I, 12" (614E23010) | FT | 80 | $2.00 | $2.00 | $0.50 | $2.00 | $2.10 |
| 41 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 80 | $2.00 | $2.00 | $0.50 | $2.00 | $2.10 |
| 42 | Work zone stop line, class I (614E26000) | FT | 66 | $4.00 | $4.00 | $5.00 | $4.00 | $4.20 |
| 43 | Work zone railroad symbol marking, class I (614E32000) | EACH | 2 | $300.00 | $300.00 | $300.00 | $300.00 | $315.00 |
| 44 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,000.00 | $5,500.00 | $4,000.00 | $2,500.00 | $4,750.00 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $24,000 | $17,000 | $20,000 | $11,000 | $15,675 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $88,000 | $166,406 | $296,212 | $140,000 | $85,000 |
| 47 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $1,250.00 | $3,750.00 | $1,500.00 | $1,250.00 | $2,865.00 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,500.00 | $14,720 | $4,000.00 | $14,000 | $15,475 |
| 49 | Mobilization (624E10000) | LS | 1 | $100,000 | $80,000 | $200,000 | $90,000 | $225,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.