ODOT contract 260401 bid tabulation
CHP-SR PAVE FY27 (TWO LANE RESURFACING). Let by Ohio DOT on September 17, 2026, CHP. 3 bids received; low bid $6,321,793 by Shelly Company, -9.7% against the engineer's estimate of $7,003,000.
- Owner
- Ohio DOT
- Letting
- 17 SEP 2026
- Pay items
- 30
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $6,321,793 | Low | -10% |
| 2 | A & B Asphalt Corporation | $6,893,800 | +9.0% | -2.0% |
| 3 | Barrett Paving Materials Inc | $7,983,992 | +26% | +14% |
Engineer's estimate: $7,003,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. A & B Asphalt Corporation | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | Monument assembly adjusted to grade (623E39500) | EACH | 1 | $200.00 | $2,669.89 | $1,300.00 |
| 2 | Special - mailbox removed and reset (690E50350) | EACH | 7 | $350.00 | $638.15 | $400.00 |
| 3 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 2,250 | $80.00 | $59.08 | $85.00 |
| 4 | Pavement planing, asphalt concrete, 1 1/2" depth (254E01000) | SY | 451,548 | $1.40 | $1.33 | $3.15 |
| 5 | Patching planed surface, as per plan (254E01601) | SY | 470 | $40.00 | $20.16 | $14.00 |
| 6 | Asphalt concrete base, (449), as per plan, PG 64-2 (301E56001) | CY | 30 | $400.00 | $621.43 | $700.00 |
| 7 | Non-tracking tack coat (407E20000) | GAL | 38,414 | $3.00 | $3.25 | $4.50 |
| 8 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 18,849 | $235.00 | $270.00 | $268.00 |
| 9 | Compacted aggregate (617E10100) | CY | 1,835 | $100.00 | $113.44 | $146.00 |
| 10 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 18.14 | $1,025.00 | $1,025.00 | $1,015.00 |
| 11 | Valve box adjusted to grade (638E10800) | EACH | 1 | $200.00 | $1,905.99 | $1,000.00 |
| 12 | RPM (621E00100) | EACH | 2,025 | $34.25 | $47.06 | $34.25 |
| 13 | Raised pavement marker removed (621E54000) | EACH | 2,025 | $5.00 | $17.53 | $9.75 |
| 14 | Edge line, 6", type 1 (642E00104) | MI | 56.46 | $720.00 | $876.00 | $876.00 |
| 15 | Center line, type 1 (642E00300) | MI | 28.23 | $915.00 | $944.00 | $944.00 |
| 16 | Stop line (644E00500) | FT | 368 | $10.00 | $16.17 | $16.17 |
| 17 | Railroad symbol marking (644E01000) | EACH | 7 | $860.00 | $750.00 | $750.00 |
| 18 | Speed measurement marking (644E40000) | EACH | 5 | $1,065.00 | $350.00 | $1,050.00 |
| 19 | Work zone center line, class I, 642 paint (614E21100) | MI | 56.46 | $870.00 | $2,316.00 | $2,316.00 |
| 20 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 112.92 | $680.00 | $1,158.00 | $1,158.00 |
| 21 | Work zone stop line, class I, 642 paint (614E26200) | FT | 736 | $4.00 | $3.50 | $3.50 |
| 22 | Work zone railroad symbol marking, class I, 642 paint (614E32200) | EACH | 14 | $350.00 | $254.00 | $254.00 |
| 23 | Joint sealer, as per plan (516E31001) | FT | 56 | $35.00 | $35.00 | $35.00 |
| 24 | Joint sealer, as per plan (516E31001) | FT | 160 | $27.00 | $27.00 | $27.00 |
| 25 | Joint sealer, as per plan (516E31001) | FT | 192 | $25.00 | $25.00 | $25.00 |
| 26 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,000.00 | $9,466.84 | $14,000 |
| 27 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $20,681 | $16,855 |
| 28 | Maintaining traffic (614E11000) | LS | 1 | $175,000 | $54,863 | $113,830 |
| 29 | Mobilization (624E10000) | LS | 1 | $200,000 | $76,830 | $200,000 |
| 100 | Work zone marking sign (614E12460) | EACH | 199 | $92.00 | $110.00 | $110.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 17, 2026. Compiled by Mirage Metrics.