ODOT contract 260436 bid tabulation

SCI-SR 125-00.00 (CHIP SEAL). Let by Ohio DOT on October 1, 2026, SCI. 5 bids received; low bid $503,222 by Runway Incorporated, -12% against the engineer's estimate of $571,000.

Owner
Ohio DOT
Letting
01 OCT 2026
Pay items
24
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Runway Incorporated$503,222Low-12%
2SC Construction & Materials LLC$535,844+6.0%-6.0%
3Henry W Bergman Inc$547,766+9.0%-4.0%
4Shelly Company$561,782+12%-2.0%
5Strawser Construction Inc$756,455+50%+32%
ODOT contract 260436: bids by rank

Engineer's estimate: $571,000.

Bid tabulation

LinePay itemUnitQuantity1. Runway Incorporated2. SC Construction & Materials LLC3. Henry W Bergman Inc4. Shelly Company5. Strawser Construction Inc
1Partial depth pavement repair (asphalt concrete base), as per plan (251E01041)SY1,000$80.34$79.25$72.00$62.50$80.00
2Aggregate, single chip seal, type A (422E11000)SY99,174$0.93$0.65$0.40$1.20$1.75
3Emulsion, chip seal (422E25000)GAL36,694$3.43$3.65$5.00$3.45$3.70
4Fog seal (886E11000)GAL14,840$3.21$3.30$3.50$3.50$6.75
5RPM (621E00100)EACH633$30.33$29.00$38.00$28.39$30.00
6Raised pavement marker removed (621E54000)EACH633$14.38$35.00$25.00$16.50$25.00
7Edge line, 6", type 1 (642E00104)MI12.44$844.60$820.00$900.00$820.00$875.00
8Center line, type 1 (642E00300)MI6.28$1,133.00$1,310.00$1,200.00$1,310.00$1,200.00
9Channelizing line, 12", type 1 (642E00404)FT420$1.24$1.15$2.00$1.15$1.30
10Stop line, type 1 (642E00500)FT93$9.27$6.00$10.00$6.00$10.00
11Transverse/diagonal line, type 1 (642E00700)FT75$9.27$6.00$10.00$6.00$9.50
12Lane arrow, type 1 (642E01300)EACH8$61.80$85.00$66.00$85.00$65.00
13Removal of pavement marking (644E30000)FT588$3.09$3.00$3.30$3.00$3.25
14Removal of pavement marking (644E30020)EACH8$51.50$110.00$55.00$110.00$55.00
15Removal of pavement marking (644E30030)MI18.61$1,081.50$1,385.00$1,100.00$1,385.00$1,200.00
16Work zone marking sign (614E12460)EACH27$108.37$150.00$115.00$95.00$115.00
17Work zone center line, class III, 642 paint (614E21550)MI18.84$767.35$880.00$800.00$880.00$800.00
18Work zone edge line, class III, 6", 642 paint (614E22360)MI37.32$597.40$400.00$640.00$565.00$625.00
19Work zone channelizing line, class III, 12", 642 paint (614E23690)FT1,260$0.52$1.00$0.70$0.95$0.50
20Work zone stop line, class III, 642 paint (614E26610)FT279$7.21$3.15$8.00$3.15$7.00
21Premium for contract performance bond and for payment bond (103E05000)LS1$13,000$5,000.00$4,000.00$3,500.00$4,500.00
22Maintaining traffic (614E11000)LS1$13,457$35,000$25,000$56,250$67,625
23Construction layout stakes and surveying (623E10000)LS1$14,500$1,000.00$2,000.00$2,250.00$2,500.00
24Mobilization (624E10000)LS1$3,000.00$41,000$40,000$20,000$67,625
ODOT contract 260436: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy