| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $1,000.00 |
| 2 | Excavation (203E10000) | CY | 65 | $50.00 | $50.00 |
| 3 | Embankment (203E20000) | CY | 76 | $55.00 | $15.00 |
| 4 | Subgrade compaction (204E10000) | SY | 396 | $5.00 | $1.00 |
| 5 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $400.00 |
| 6 | Topsoil (659E00300) | CY | 92 | $95.00 | $70.00 |
| 7 | Seeding and mulching (659E10000) | SY | 830 | $4.50 | $4.00 |
| 8 | Repair seeding and mulching (659E14000) | SY | 42 | $1.90 | $10.00 |
| 9 | Commercial fertilizer (659E20000) | TON | 0.11 | $1,250.00 | $2,000.00 |
| 10 | Lime (659E31000) | ACRE | 0.17 | $150.00 | $1.00 |
| 11 | Water (659E35000) | MGAL | 5 | $1.00 | $300.00 |
| 12 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 13 | Partial depth pavement repair (441) (251E01010) | CY | 300 | $550.00 | $425.00 |
| 14 | Pavement planing, asphalt concrete (1 1/2") (254E01000) | SY | 738 | $5.75 | $3.00 |
| 15 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 49 | $350.00 | $400.00 |
| 16 | Aggregate base (304E20000) | CY | 66 | $125.00 | $150.00 |
| 17 | Tack coat (407E10000) | GAL | 32,618 | $3.50 | $3.50 |
| 18 | Prime coat, as per plan (408E10001) | GAL | 16,037 | $5.00 | $5.50 |
| 19 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 10,632 | $285.00 | $275.00 |
| 20 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 48 | $500.00 | $300.00 |
| 21 | Compacted aggregate, as per plan (617E10101) | CY | 1,117 | $92.50 | $45.00 |
| 22 | Shoulder preparation, as per plan (617E20001) | SY | 80,194 | $0.65 | $0.80 |
| 23 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 173,605 | $0.16 | $0.16 |
| 24 | Pavement planing, asphalt concrete, class A (1") (897E01010) | SY | 382,763 | $1.95 | $2.15 |
| 25 | RPM (621E00100) | EACH | 947 | $36.00 | $35.40 |
| 26 | RPM reflector (621E00300) | EACH | 38 | $20.00 | $8.00 |
| 27 | Raised pavement marker removed (621E54000) | EACH | 947 | $10.00 | $1.00 |
| 28 | Edge line, 6" (646E10010) | MI | 0.62 | $3,500.00 | $5,060.00 |
| 29 | Channelizing line, 12" (646E10310) | FT | 323 | $1.60 | $2.25 |
| 30 | Stop line (646E10400) | FT | 52 | $12.50 | $12.50 |
| 31 | Chevron marking (646E10620) | FT | 297 | $11.00 | $12.00 |
| 32 | Lane arrow (646E20300) | EACH | 1 | $165.00 | $175.00 |
| 33 | Wrong way arrow (646E20320) | EACH | 4 | $225.00 | $225.00 |
| 34 | Speed measurement marking (646E20710) | EACH | 20 | $100.00 | $270.00 |
| 35 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 34.78 | $3,905.00 | $3,500.00 |
| 36 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 16.74 | $1,895.00 | $1,800.00 |
| 37 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 3,566 | $2.10 | $2.75 |
| 38 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 3,018 | $1.40 | $1.25 |
| 39 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 50.20 | $1,320.00 | $1,100.00 |
| 40 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 3,018 | $1.50 | $1.00 |
| 41 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 1,940 | $1.55 | $1.50 |
| 42 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 1.32 | $2,200.00 | $2,500.00 |
| 43 | Grooving for 12" recessed pavement marking, (concrete) (850E20130) | FT | 1,616 | $1.75 | $1.50 |
| 44 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $100.00 | $150.00 |
| 45 | Work zone marking sign (614E12460) | EACH | 10 | $95.00 | $110.00 |
| 46 | Work zone increased penalties sign (614E12484) | EACH | 16 | $95.00 | $250.00 |
| 47 | Replacement sign (614E12500) | EACH | 4 | $150.00 | $250.00 |
| 48 | Replacement drum (614E12600) | EACH | 10 | $80.00 | $55.00 |
| 49 | Asphalt concrete for maintaining traffic, as per plan (614E13001) | CY | 50 | $300.00 | $175.00 |
| 50 | Work zone lane line, class I, 6", 807 paint (614E20056) | MI | 17.02 | $880.00 | $1,495.00 |
| 51 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 17.02 | $575.00 | $505.00 |
| 52 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 35.66 | $1,950.00 | $2,595.00 |
| 53 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 35.66 | $850.00 | $850.00 |
| 54 | Work zone channelizing line, class I, 12", 807 paint (614E23110) | FT | 3,566 | $1.05 | $2.00 |
| 55 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 3,566 | $0.72 | $1.75 |
| 56 | Work zone dotted line, class I, 6", 807 paint (614E24102) | FT | 3,088 | $0.82 | $1.50 |
| 57 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 3,088 | $0.66 | $1.25 |
| 58 | Water (616E10000) | MGAL | 5 | $175.00 | $1.07 |
| 59 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 128 | $600.00 | $550.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $23,000 | $50,000 |
| 61 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $175,000 | $300,000 |
| 62 | Field office, type B (619E16010) | MNTH | 5 | $5,000.00 | $3,000.00 |
| 63 | Mobilization (624E10000) | LS | 1 | $131,000 | $320,000 |