SCDOT contract 0268731 bid tabulation
S-145 (Storm Branch Road) over Tributary to Horse Creek. Let by South Carolina DOT on June 10, 2025. 4 bids received; low bid $3,059,774 by Eagle Construction Company.
- Owner
- South Carolina DOT
- Letting
- 10 JUN 2025
- Pay items
- 109
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eagle Construction Company | $3,059,774 | Low |
| 2 | Dane Construction, LLC | $3,102,968 | +1.0% |
| 3 | United Infrastructure Group, Inc. | $3,520,242 | +15% |
| 4 | Mastec Civil, LLC | $4,077,000 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Construction Company | 2. Dane Construction, LLC | 3. United Infrastructure Group, Inc. | 4. Mastec Civil, LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $151,000 | $155,145 | $176,012 | $203,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $85,000 | $155,145 | $176,012 | $203,000 |
| 0030 | Bridge construction access (1031200) | LS | 1 | $80,000 | $62,055 | $70,405 | $203,000 |
| 0040 | Bonds and insurance (1032010) | LS | 1 | $14,000 | $62,055 | $105,607 | $100,000 |
| 0050 | Construction stakes, lines & grades (1050800) | EACH | 1 | $40,000 | $25,000 | $50,000 | $100,000 |
| 0060 | Utility staking (1052001) | LS | 1 | $3,500.00 | $7,500.00 | $10,000 | $10,000 |
| 0070 | Small public water relocation no. ____ 01 (1052100) | EACH | 1 | $227,673 | $217,020 | $227,674 | $240,000 |
| 0080 | CPM progress schedule (1080300) | LS | 1 | $2,500.00 | $20,000 | $10,000 | $15,000 |
| 0090 | Clearing & grubbing within roadway (2012000) | LS | 1 | $105,400 | $75,000 | $209,821 | $340,000 |
| 0100 | Removal & disposal item no. 01 (2022000) | LS | 1 | $4,000.00 | $4,500.00 | $6,000.00 | $10,000 |
| 0101 | Removal & disposal item no. 002 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $5,000.00 |
| 0102 | Removal & disposal item no. 003 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $10,000 |
| 0103 | Removal & disposal item no. 004 (2022000) | LS | 1 | $2,200.00 | $10,000 | $100.00 | $5,000.00 |
| 0104 | Removal & disposal item no. 005 (2022000) | LS | 1 | $2,200.00 | $10,000 | $100.00 | $7,400.00 |
| 0105 | Removal & disposal item no. 006 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $948.55 |
| 0106 | Removal & disposal item no. 007 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $2,500.00 |
| 0107 | Removal & disposal item no. 008 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $4,000.00 |
| 0108 | Removal & disposal item no. 009 (2022000) | LS | 1 | $1,100.00 | $10,000 | $100.00 | $3,000.00 |
| 0109 | Removal & disposal item no. 010 (2022000) | LS | 1 | $1,100.00 | $1,000.00 | $100.00 | $3,000.00 |
| 0110 | Removal & disposal of existing asphalt pavement (2025000) | SY | 453 | $10.00 | $21.95 | $35.00 | $25.00 |
| 0120 | Removal of exist. guardrail (2027801) | LF | 386 | $3.00 | $2.00 | $2.00 | $3.00 |
| 0130 | Removal & disposal of existing bridge (2028100) | LS | 1 | $120,000 | $128,820 | $265,000 | $298,500 |
| 0140 | Unclassified excavation (2031000) | CY | 2,146 | $16.98 | $30.00 | $40.00 | $35.00 |
| 0150 | Borrow excavation (2033000) | CY | 1,838 | $48.00 | $32.00 | $50.00 | $25.00 |
| 0160 | Muck excavation (2034000) | CY | 280 | $20.00 | $45.00 | $55.00 | $20.00 |
| 0170 | Geotextile, separation (2036020) | SY | 275 | $5.00 | $11.00 | $12.00 | $9.00 |
| 0180 | Geogrid reinforcement (uniaxial) (2037000) | SY | 3,200 | $9.50 | $12.50 | $9.50 | $14.00 |
| 0190 | Geogrid stabilization (2037030) | SY | 275 | $10.50 | $11.00 | $14.00 | $8.00 |
| 0200 | Stone bridge lift material (2052010) | TON | 525 | $56.00 | $78.00 | $95.00 | $57.00 |
| 0210 | Granular bridge lift material (2052020) | CY | 355 | $71.60 | $70.00 | $145.00 | $36.00 |
| 0220 | Fine grading (2081001) | SY | 814 | $1.50 | $50.00 | $50.00 | $40.00 |
| 0230 | Flowable fill (2103000) | CY | 35 | $425.00 | $225.00 | $300.00 | $285.00 |
| 0240 | Maintenance stone (3059900) | TON | 61 | $48.00 | $85.00 | $122.50 | $60.00 |
| 0250 | Liquid asphalt binder PG64-22 (4011004) | TON | 45 | $750.00 | $705.00 | $717.48 | $705.00 |
| 0260 | Milling existing asphalt pavement (variable) (4013990) | SY | 657 | $19.00 | $15.00 | $15.27 | $15.00 |
| 0270 | Asphalt base course - type B (4020320) | TON | 133 | $170.00 | $158.00 | $160.80 | $165.00 |
| 0280 | Asphalt intermediate course type C (4030330) | TON | 425 | $140.00 | $134.00 | $136.37 | $134.00 |
| 0290 | Asphalt surface course type C (4040340) | TON | 223 | $140.00 | $132.00 | $134.34 | $132.00 |
| 0300 | Driveway paving-surface type D (4047230) | TON | 49 | $250.00 | $200.00 | $203.54 | $200.00 |
| 0310 | Traffic control (6011000) | LS | 1 | $35,000 | $29,120 | $25,000 | $150,000 |
| 0320 | Barricade - type III (6041200) | LF | 84 | $50.00 | $21.00 | $21.00 | $25.00 |
| 0330 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $12.50 | $7.40 | $7.40 | $7.00 |
| 0340 | Permanent construction signs (barricade mounted) (6051125) | SF | 70 | $15.00 | $7.40 | $7.40 | $9.00 |
| 0350 | Type B - flashing light (608100B) | EACH | 16 | $150.00 | $168.45 | $125.00 | $165.00 |
| 0360 | 4" white solid lines (PVT. edge lines) epoxy paint fast cure (6262010) | LF | 168 | $8.80 | $7.50 | $7.50 | $6.25 |
| 0370 | 4" yellow broken lines(gaps exc) epoxy paint fast cure (6262105) | LF | 20 | $8.80 | $7.50 | $7.50 | $6.75 |
| 0380 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint fast cure (6262110) | LF | 84 | $8.80 | $7.50 | $7.50 | $6.75 |
| 0390 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 38 | $3.00 | $2.50 | $2.50 | $1.00 |
| 0400 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,593 | $3.00 | $2.50 | $2.50 | $1.00 |
| 0410 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 16 | $18.00 | $15.00 | $15.00 | $15.00 |
| 0420 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 70 | $3.00 | $2.50 | $2.50 | $1.00 |
| 0430 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,365 | $3.00 | $2.50 | $2.50 | $1.00 |
| 0440 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 11 | $18.00 | $15.00 | $15.00 | $10.00 |
| 0450 | Milled-in rumble strip (6321000) | MI | 0.50 | $16,000 | $15,900 | $16,000 | $22,200 |
| 0460 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 500 | $30.00 | $32.00 | $20.00 | $25.00 |
| 0470 | Conc. for structures - class 4000 (7011400) | CY | 380 | $2,250.00 | $2,350.00 | $2,000.00 | $2,300.00 |
| 0480 | Grooved surface finish (7023200) | SY | 360 | $30.00 | $11.20 | $28.00 | $22.00 |
| 0490 | Reinf. steel for structures (bridge) (7031200) | LB | 87,877 | $3.50 | $2.10 | $1.50 | $1.85 |
| 0500 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 248 | $80.00 | $150.00 | $155.00 | $215.00 |
| 0510 | Pile driving set-UP (7110010) | EACH | 22 | $4,500.00 | $4,000.00 | $10,000 | $3,600.00 |
| 0520 | Prest. conc. piling (20"SQ.) (7110200) | LF | 390 | $250.00 | $125.00 | $210.00 | $275.00 |
| 0530 | Pile build-UP preparation (20"SQ) (7110201) | EACH | 2 | $2,500.00 | $2,000.00 | $1,800.00 | $7,000.00 |
| 0540 | Prestressed pile point (HP10X57) (7111115) | LF | 129 | $200.00 | $100.00 | $150.00 | $165.00 |
| 0550 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 370 | $80.00 | $65.00 | $90.00 | $175.00 |
| 0560 | 18" smooth wall pipe (7143618) | LF | 360 | $65.50 | $120.00 | $155.00 | $180.00 |
| 0570 | Cleaning existing pipe (7149999) | LF | 24 | $60.00 | $25.00 | $100.00 | $40.00 |
| 0580 | Catch basin -type 16 (7191605) | EACH | 1 | $10,000 | $6,000.00 | $9,000.00 | $8,500.00 |
| 0590 | Drop inlet (24" X 36") (7192020) | EACH | 1 | $8,750.00 | $6,000.00 | $7,000.00 | $6,000.00 |
| 0600 | Manhole (7192105) | EACH | 1 | $8,400.00 | $8,500.00 | $8,000.00 | $6,000.00 |
| 0610 | Beveling of pipe end (7199100) | EACH | 12 | $600.00 | $900.00 | $900.00 | $470.00 |
| 0620 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 15 | $350.00 | $299.00 | $250.00 | $420.00 |
| 0630 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 83 | $80.00 | $65.00 | $60.00 | $158.00 |
| 0640 | Elastomeric bearing assembly (flat slab) (7243150) | EACH | 4 | $6,000.00 | $3,000.00 | $7,500.00 | $6,800.00 |
| 0650 | Waterproofing (7282000) | SY | 7 | $200.00 | $250.00 | $350.00 | $270.00 |
| 0660 | Rip-rap (class B) (8041020) | TON | 500 | $72.50 | $85.00 | $95.00 | $110.00 |
| 0670 | Geotextile for erosion control under riprap(class 1)type C (8048110) | SY | 410 | $3.50 | $11.00 | $6.00 | $10.00 |
| 0680 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 197 | $3.50 | $11.00 | $8.00 | $14.00 |
| 0690 | MT2 leading end treatment TL2 (8051155) | EACH | 4 | $3,400.00 | $2,550.00 | $2,550.00 | $2,550.00 |
| 0700 | MGS3 GR standard shoulder (8052100) | LF | 500 | $30.00 | $27.00 | $27.00 | $27.00 |
| 0710 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 4 | $2,800.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0720 | Flume inlet at guardrail (handwork) (8053257) | EACH | 1 | $8,000.00 | $4,400.00 | $4,500.00 | $4,600.00 |
| 0730 | Non-mow strip under guardrail (8055250) | SY | 80 | $250.00 | $150.00 | $130.00 | $100.00 |
| 0740 | Temporary barrier fence (orange) (8068301) | LF | 600 | $4.50 | $4.00 | $3.75 | $4.00 |
| 0741 | Moving item no. 001 (8081000) | LS | 1 | $350.00 | $5,000.00 | $250.00 | $1,100.00 |
| 0750 | Right of way marker(rebar and cap) (8091010) | EACH | 19 | $160.00 | $150.00 | $130.00 | $145.00 |
| 0760 | Right of way plat (8091050) | LS | 1 | $1,500.00 | $4,175.00 | $3,000.00 | $5,000.00 |
| 0770 | Permanent cover (8100100) | ACRE | 1.36 | $2,300.00 | $1,942.80 | $1,850.00 | $2,300.00 |
| 0780 | Temporary cover (8100200) | ACRE | 0.68 | $1,500.00 | $1,235.25 | $1,250.00 | $1,425.00 |
| 0790 | Compost (8101105) | CY | 36 | $80.00 | $5.00 | $89.00 | $5.70 |
| 0800 | Fertilizer (nitrogen) (8104005) | LB | 136 | $2.50 | $2.00 | $2.00 | $2.30 |
| 0810 | Fertilizer (phosphoric acid) (8104010) | LB | 136 | $2.50 | $2.00 | $2.00 | $2.30 |
| 0820 | Fertilizer (potash) (8104015) | LB | 136 | $2.50 | $2.00 | $2.00 | $2.30 |
| 0830 | Agricultural granular lime (8105005) | LB | 2,710 | $2.25 | $1.00 | $1.00 | $1.15 |
| 0840 | Selective watering (8109050) | GAL | 54,300 | $0.02 | $0.01 | $0.01 | $0.01 |
| 0850 | Mowing (8109901) | ACRE | 4.07 | $600.00 | $499.38 | $500.00 | $570.00 |
| 0860 | Temporary erosion control blanket (ecb) (8151110) | MSY | 1.26 | $3,350.00 | $2,750.00 | $1,850.00 | $2,800.00 |
| 0870 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 1.52 | $2,050.00 | $1,750.00 | $1,450.00 | $1,800.00 |
| 0880 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 1.19 | $4,100.00 | $3,500.00 | $3,250.00 | $3,550.00 |
| 0890 | Inlet structure filter - type F (weighted) (8152004) | LF | 14 | $18.00 | $75.00 | $25.00 | $10.00 |
| 0900 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 14 | $18.00 | $35.00 | $10.50 | $10.00 |
| 0910 | Sediment tubes for ditch checks (8152007) | LF | 200 | $16.00 | $15.00 | $10.50 | $10.00 |
| 0920 | Silt fence (8153000) | LF | 1,533 | $4.20 | $4.75 | $4.00 | $4.00 |
| 0930 | Replace/repair silt fence (8153090) | LF | 153 | $8.00 | $4.00 | $3.00 | $4.00 |
| 0940 | Cleaning silt basins (8154010) | CY | 5 | $60.00 | $175.00 | $90.00 | $300.00 |
| 0950 | Removal of silt retained by silt fence (8154050) | LF | 383 | $5.00 | $25.00 | $9.00 | $5.00 |
| 0960 | Inlet filter cleaning (8154155) | EACH | 2 | $200.00 | $1,500.00 | $450.00 | $250.00 |
| 0970 | Inlet structure filter - type D2 (8156215) | EACH | 1 | $650.00 | $750.00 | $500.00 | $750.00 |
| 0980 | Filter material for inlet structure filter - type D2 (8156217) | EACH | 1 | $500.00 | $750.00 | $225.00 | $150.00 |
| 0990 | Stabilized construction entrance (8156490) | SY | 550 | $24.50 | $28.00 | $20.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of June 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.