SCDOT contract 3766490 bid tabulation
S-106 (Clearmont Road) RBO Colonels Fork Creek. Let by South Carolina DOT on September 9, 2025, Oconee, District 3. 5 bids received; low bid $3,435,606 by K. West Group, LLC.
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2025
- Pay items
- 82
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | K. West Group, LLC | $3,435,606 | Low |
| 2 | Eagle Construction Company | $3,463,607 | +1.0% |
| 3 | United Infrastructure Group, Inc. | $3,634,462 | +6.0% |
| 4 | Ipc Paving LLC | $3,999,867 | +16% |
| 5 | Dane Construction, LLC | $4,046,734 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. K. West Group, LLC | 2. Eagle Construction Company | 3. United Infrastructure Group, Inc. | 4. Ipc Paving LLC | 5. Dane Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $170,000 | $150,000 | $181,723 | $200,000 | $202,335 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $68,000 | $24,500 | $109,034 | $80,000 | $80,930 |
| 0030 | Construction stakes, lines & grades (1050801) | EACH | 1 | $50,000 | $56,500 | $90,000 | $65,000 | $45,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $10,000 | $4,500.00 | $5,000.00 | $55,000 | $25,000 |
| 0050 | Clearing & grubbing within right of way (2011001) | ACRE | 2.20 | $50,000 | $41,500 | $31,000 | $19,800 | $20,000 |
| 0060 | Removal & disposal of existing asphalt pavement (2025000) | SY | 430 | $5.00 | $11.00 | $65.00 | $24.15 | $25.00 |
| 0070 | Removal of exist. guardrail (2027801) | LF | 932 | $1.00 | $2.50 | $1.00 | $1.75 | $1.00 |
| 0080 | Removal & disposal of existing bridge (2028100) | LS | 1 | $443,500 | $112,000 | $300,000 | $150,000 | $326,640 |
| 0090 | Unclassified excavation (2031000) | CY | 4,557 | $25.00 | $19.40 | $30.00 | $32.00 | $35.00 |
| 0100 | Borrow excavation (2033000) | CY | 4,804 | $15.00 | $48.50 | $45.00 | $86.50 | $45.00 |
| 0110 | Fine grading (2081001) | SY | 2,443 | $15.00 | $2.00 | $18.00 | $3.50 | $20.00 |
| 0120 | Graded aggregate base course (6" uniform) (3050106) | SY | 150 | $40.00 | $32.50 | $69.32 | $20.30 | $50.00 |
| 0130 | Maintenance stone (3059900) | TON | 100 | $20.00 | $39.00 | $69.95 | $130.00 | $65.00 |
| 0140 | Prime coat (4010005) | GAL | 41 | $25.00 | $40.00 | $5.00 | $3.50 | $100.00 |
| 0150 | Liquid asphalt binder PG64-22 (4011004) | TON | 72 | $750.00 | $850.00 | $757.49 | $750.00 | $750.00 |
| 0160 | Full depth asph. pav. patching 10"unif (4012100) | SY | 244 | $180.00 | $225.00 | $181.80 | $180.00 | $180.00 |
| 0170 | Milling existing asphalt pavement (variable) (4013990) | SY | 149 | $102.00 | $125.00 | $103.02 | $102.00 | $102.00 |
| 0180 | Asphalt base course - type B (4020320) | TON | 718 | $150.00 | $158.00 | $151.50 | $150.00 | $150.00 |
| 0190 | Asphalt intermediate course type B (4030320) | TON | 88 | $245.00 | $300.00 | $247.45 | $245.00 | $245.00 |
| 0200 | Asphalt intermediate course type C (4030330) | TON | 230 | $175.00 | $200.00 | $176.75 | $175.00 | $175.00 |
| 0210 | Asphalt surface course type C (4040340) | TON | 284 | $170.00 | $190.00 | $171.70 | $170.00 | $170.00 |
| 0220 | Asphalt surface course type E (4040360) | TON | 14 | $350.00 | $500.00 | $353.49 | $350.00 | $350.00 |
| 0230 | Traffic control (6011000) | LS | 1 | $50,000 | $48,500 | $283,400 | $96,000 | $35,000 |
| 0240 | Barricade - type III (6041200) | LF | 90 | $20.00 | $50.00 | $21.00 | $24.75 | $22.00 |
| 0250 | Permanent construction signs (ground mounted) (6051120) | SF | 190 | $9.00 | $12.00 | $7.40 | $9.50 | $7.00 |
| 0260 | Permanent construction signs (barricade mounted) (6051125) | SF | 107 | $9.00 | $15.00 | $7.40 | $7.00 | $7.00 |
| 0270 | Type B - flashing light (608100B) | EACH | 16 | $150.00 | $225.00 | $125.00 | $78.50 | $175.00 |
| 0280 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,300 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 |
| 0290 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 2,300 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 |
| 0300 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 15 | $7.50 | $9.00 | $7.50 | $7.50 | $7.50 |
| 0310 | 6.0" schedule 40 PVC conduit (6750232) | LF | 8 | $25.00 | $100.00 | $37.10 | $162.00 | $150.00 |
| 0320 | 6.0" schedule 40 PVC conduit - 90 degree bend (675024O) | EACH | 1 | $50.00 | $50.00 | $31.80 | $1,290.00 | $275.00 |
| 0330 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,234 | $18.00 | $35.00 | $10.00 | $16.45 | $16.00 |
| 0340 | Conc. for structures - class 4000 (7011400) | CY | 426 | $1,500.00 | $1,350.00 | $500.00 | $1,400.00 | $1,680.00 |
| 0350 | Grooved surface finish (7023200) | SY | 397 | $25.00 | $30.00 | $25.00 | $44.00 | $7.79 |
| 0360 | Reinf. steel for structures (bridge) (7031200) | LB | 93,890 | $2.50 | $1.75 | $2.00 | $1.90 | $2.50 |
| 0370 | Prestressed concrete bulb tee beam(54"mod.) (7044554) | LF | 520 | $450.00 | $490.00 | $500.00 | $730.00 | $830.00 |
| 0380 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 615 | $150.00 | $475.00 | $115.00 | $141.00 | $110.00 |
| 0390 | Pile driving set-UP (7110010) | EACH | 10 | $2,500.00 | $5,600.00 | $7,500.00 | $15,000 | $4,750.00 |
| 0400 | Reinf. pile tips (HP14 X 89) (7111565) | EACH | 10 | $150.00 | $225.00 | $185.00 | $193.18 | $550.00 |
| 0410 | Steel H bearing piling (HP14 X 89) (7112230) | LF | 180 | $125.00 | $85.00 | $70.00 | $180.00 | $77.00 |
| 0420 | Mech. stab.earth retaining wall backfill(stone) (7137007) | CY | 760 | $150.00 | $130.00 | $175.00 | $260.00 | $80.00 |
| 0430 | Mechanically stabilized earth retaining wall(panel facing) B (7137230) | SF | 2,808 | $100.00 | $105.00 | $130.00 | $80.00 | $180.00 |
| 0440 | Coping for MSE retaining wall(bridge) (7137290) | LF | 416 | $100.00 | $380.00 | $250.00 | $120.00 | $210.50 |
| 0450 | 18" smooth wall pipe (7143618) | LF | 112 | $125.00 | $81.00 | $300.00 | $190.00 | $85.00 |
| 0460 | Drop inlet (24" X 36") (7192020) | EACH | 1 | $5,000.00 | $9,000.00 | $15,000 | $12,900 | $4,750.00 |
| 0470 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 28 | $185.00 | $115.00 | $253.00 | $250.00 | $350.00 |
| 0480 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 105 | $60.00 | $75.00 | $71.50 | $50.00 | $150.00 |
| 0490 | Elastomeric bearing (7243100) | EACH | 10 | $250.00 | $170.00 | $2,000.00 | $650.00 | $385.00 |
| 0500 | Waterproofing (7282000) | SY | 22 | $100.00 | $175.00 | $537.33 | $265.00 | $100.00 |
| 0510 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 127 | $100.00 | $120.00 | $170.62 | $175.00 | $80.50 |
| 0520 | Rip-rap (class A) (8041010) | TON | 164 | $85.00 | $67.50 | $149.83 | $97.45 | $100.00 |
| 0530 | Rip-rap (class B) (8041020) | TON | 217 | $85.00 | $63.00 | $124.51 | $109.30 | $100.00 |
| 0540 | Rip-rap (class C) (8041030) | TON | 453 | $85.00 | $71.00 | $134.32 | $137.90 | $100.00 |
| 0550 | Geotextile for erosion control under riprap(class 1)type C (8048110) | SY | 670 | $3.00 | $4.00 | $10.00 | $5.00 | $4.50 |
| 0560 | Geotextile for erosion control under riprap(class 2)type A (8048200) | SY | 395 | $3.00 | $4.00 | $10.00 | $5.00 | $4.75 |
| 0570 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 115 | $3.00 | $6.50 | $10.00 | $5.00 | $5.50 |
| 0580 | MT2 leading end treatment TL2 (8051155) | EACH | 4 | $2,443.00 | $3,000.00 | $3,450.00 | $3,450.00 | $2,443.00 |
| 0590 | MGS3 GR standard shoulder (8052100) | LF | 350 | $27.50 | $35.00 | $26.00 | $26.00 | $27.50 |
| 0600 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 4 | $2,217.00 | $2,700.00 | $2,100.00 | $2,100.00 | $2,217.00 |
| 0610 | Flume inlet at guardrail (handwork) (8053257) | EACH | 1 | $3,000.00 | $6,800.00 | $4,400.00 | $4,800.00 | $3,000.00 |
| 0620 | Non-mow strip under guardrail (8055250) | SY | 146 | $25.00 | $180.00 | $75.00 | $50.00 | $110.00 |
| 0630 | Temporary barrier fence (orange) (8068301) | LF | 1,000 | $4.00 | $5.00 | $3.50 | $4.25 | $2.55 |
| 0640 | Right of way marker(rebar and cap) (8091010) | EACH | 25 | $500.00 | $185.00 | $150.00 | $150.00 | $215.00 |
| 0650 | Right of way plat (8091050) | LS | 1 | $2,000.00 | $3,500.00 | $5,000.00 | $4,700.00 | $8,750.00 |
| 0660 | Permanent cover (8100100) | ACRE | 1.34 | $1,500.00 | $1,800.00 | $1,850.00 | $1,500.00 | $1,489.28 |
| 0670 | Temporary cover (8100200) | ACRE | 0.67 | $1,950.00 | $2,500.00 | $1,250.00 | $927.00 | $940.15 |
| 0680 | Fertilizer (nitrogen) (8104005) | LB | 134 | $5.00 | $6.00 | $2.00 | $1.60 | $1.60 |
| 0690 | Fertilizer (phosphoric acid) (8104010) | LB | 134 | $5.00 | $6.00 | $2.00 | $1.60 | $1.60 |
| 0700 | Fertilizer (potash) (8104015) | LB | 134 | $5.00 | $6.00 | $2.00 | $1.60 | $1.60 |
| 0710 | Agricultural granular lime (8105005) | LB | 2,683 | $0.40 | $0.60 | $1.00 | $0.95 | $0.95 |
| 0720 | Selective watering (8109050) | GAL | 54,300 | $0.09 | $0.10 | $0.01 | $0.15 | $0.15 |
| 0730 | Mowing (8109901) | ACRE | 4.03 | $600.00 | $720.00 | $500.00 | $436.65 | $437.74 |
| 0740 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 0.26 | $6,500.00 | $8,000.00 | $4,250.00 | $3,347.00 | $3,347.38 |
| 0750 | Temporary erosion control blanket (ecb) (8151110) | MSY | 5.68 | $1,600.00 | $1,950.00 | $1,850.00 | $2,559.00 | $2,500.94 |
| 0760 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 10 | $15.00 | $50.00 | $100.00 | $9.71 | $15.00 |
| 0770 | Sediment tubes for ditch checks (8152007) | LF | 872 | $10.00 | $14.00 | $10.50 | $12.00 | $15.00 |
| 0780 | Silt fence (8153000) | LF | 1,225 | $3.25 | $4.00 | $3.75 | $4.45 | $4.45 |
| 0790 | Cleaning silt basins (8154010) | CY | 788 | $10.00 | $12.00 | $13.00 | $125.00 | $20.00 |
| 0800 | Inlet filter cleaning (8154155) | EACH | 1 | $1,000.00 | $250.00 | $500.00 | $250.00 | $750.00 |
| 0810 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 32 | $125.00 | $90.00 | $200.00 | $155.00 | $85.00 |
| 0820 | Stabilized construction entrance (8156490) | SY | 550 | $15.00 | $23.00 | $10.00 | $57.54 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.