TDOT contract CN262036 bid tabulation
R2bvar-m3-066 the on-call guardrail repair and new guardrail installation on various interstate and state routes. Let by Tennessee DOT on March 20, 2026, Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White. 4 bids received; low bid $4,306,678 by Reynolds Fence and Guardrail, Inc..
- Owner
- Tennessee DOT
- Letting
- 20 MAR 2026
- Pay items
- 60
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Reynolds Fence and Guardrail, Inc. | $4,306,678 | Low |
| 2 | Cumberland Guardrail, Inc. | $4,503,872 | +5.0% |
| 3 | Tennessee Guardrail, Inc. | $4,973,507 | +15% |
| 4 | Superior Traffic Control, LLC | $6,207,720 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Reynolds Fence and Guardrail, Inc. | 2. Cumberland Guardrail, Inc. | 3. Tennessee Guardrail, Inc. | 4. Superior Traffic Control, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Guardrail at bridge ends (705-01.01) | LF | 150 | $110.00 | $40.00 | $100.00 | $150.00 |
| 2 | Guardrail at bridge piers (705-01.02) | LF | 18 | $40.00 | $20.00 | $75.00 | $170.00 |
| 3 | Metal beam guard fence (705-01.04) | LF | 100 | $80.00 | $73.94 | $90.00 | $120.00 |
| 4 | Single guardrail, with rub-rail (type 2) (705-02.01) | LF | 25 | $45.00 | $50.00 | $35.00 | $75.00 |
| 5 | Single guardrail (type 2) (705-02.02) | LF | 30,000 | $27.00 | $27.00 | $33.00 | $33.00 |
| 6 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 75 | $100.00 | $125.00 | $100.00 | $300.00 |
| 7 | Single guardrail (type 2) long post (6 FT-9 FT) (705-02.20) | LF | 3,200 | $30.00 | $32.00 | $34.00 | $48.00 |
| 8 | Single guardrail (type 2) long post (9 FT-12 FT) (705-02.25) | LF | 50 | $30.00 | $32.00 | $40.00 | $55.00 |
| 9 | Median divider guardrail, with rub-rail (type 2) (705-03.01) | LF | 30 | $75.00 | $32.00 | $52.50 | $75.00 |
| 10 | Median divider guardrail (type 2) (705-03.02) | LF | 30 | $25.00 | $32.00 | $40.00 | $50.00 |
| 11 | Median divider guardrail (type 2) (27" MT HT) (705-03.03) | LF | 25 | $25.00 | $32.00 | $35.50 | $80.00 |
| 12 | Median divider guardrail at concrete barrier (705-03.04) | LF | 18 | $25.00 | $32.00 | $55.00 | $90.00 |
| 13 | Guardrail terminal (type 12) (705-04.02) | EACH | 2 | $500.00 | $2,400.00 | $3,000.00 | $3,500.00 |
| 14 | Guardrail terminal (type 13) (705-04.03) | EACH | 5 | $1,900.00 | $1,400.00 | $1,300.00 | $2,500.00 |
| 15 | Guardrail terminal (type-in-line) (705-04.05) | EACH | 30 | $1,200.00 | $1,400.00 | $1,000.00 | $2,500.00 |
| 16 | Stone for guardrail end terminal pad (705-04.11) | TON | 75 | $7.50 | $40.00 | $66.50 | $150.00 |
| 17 | Guardrail end terminal delineation sheeting (705-04.24) | SF | 50 | $21.00 | $17.00 | $61.00 | $30.00 |
| 18 | C-A-T crash cushion attenuating terminal (705-04.29) | EACH | 1 | $6,400.00 | $4,000.00 | $9,400.00 | $17,500 |
| 19 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 10,000 | $21.00 | $27.00 | $30.00 | $36.00 |
| 20 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 300 | $21.00 | $28.00 | $33.00 | $40.00 |
| 21 | Weak-post guardrail attachment to culvert(MASH TL-3) (705-06.09) | LF | 50 | $75.00 | $150.00 | $280.00 | $500.00 |
| 22 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 4 | $1,700.00 | $1,200.00 | $1,500.00 | $1,600.00 |
| 23 | GR terminal (in-inline) MASH TL-3 (705-06.11) | EACH | 3 | $500.00 | $900.00 | $1,200.00 | $2,500.00 |
| 24 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 400 | $3,000.00 | $3,100.00 | $3,500.00 | $4,000.00 |
| 25 | Tangent energy absorbing term MASH TL-3 (powder coating) (705-06.21) | EACH | 1 | $5,100.00 | $32.00 | $6,590.00 | $6,500.00 |
| 26 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 2 | $700.00 | $22.50 | $2,305.00 | $3,100.00 |
| 27 | Thrie beam bridge transition MASH TL-2 (705-06.26) | EACH | 1 | $250.00 | $750.00 | $1,800.00 | $2,800.00 |
| 28 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 2 | $2,600.00 | $2,900.00 | $3,500.00 | $3,200.00 |
| 29 | Guardrail attachment to slope face endpost (705-10.30) | LF | 20 | $25.00 | $95.00 | $200.00 | $400.00 |
| 30 | Guardrail attachment to vertical face endpost (705-10.31) | LF | 15 | $25.00 | $95.00 | $200.00 | $400.00 |
| 31 | Guardrail attachment to existing bridge pier protection (705-10.32) | EACH | 3 | $1,900.00 | $2,500.00 | $3,500.00 | $3,000.00 |
| 32 | Guardrail end terminal SKT 350 bolt conversion (705-10.98) | EACH | 25 | $10.00 | $42.00 | $52.00 | $500.00 |
| 33 | Guardrail end terminal anchor cable assembly (705-10.99) | EACH | 3 | $50.00 | $85.00 | $418.00 | $2,000.00 |
| 34 | Guardrail at bridge ends (powder coated) (705-11.01) | LF | 18 | $50.00 | $85.00 | $125.00 | $100.00 |
| 35 | Single guardrail (type 2) (powder coated) (705-11.03) | LF | 50 | $45.00 | $43.00 | $54.00 | $55.00 |
| 36 | Guardrail terminal (type 13) (powder coated) (705-11.08) | EACH | 1 | $1,500.00 | $2,000.00 | $2,210.00 | $2,500.00 |
| 37 | Median attenuating trend terminal (matt) (705-16.01) | EACH | 1 | $6,500.00 | $9,000.00 | $14,500 | $20,000 |
| 38 | Guardrail removed (706-01) | LF | 500 | $3.10 | $0.50 | $4.00 | $12.00 |
| 39 | Reset single guardrail (type 2) (706-02.21) | LF | 100 | $3.00 | $6.50 | $19.00 | $20.00 |
| 40 | Posts furnished (706-03.01) | EACH | 10 | $65.00 | $120.00 | $125.00 | $140.00 |
| 41 | Single thrie rail (type 2) (706-06.01) | LF | 18 | $25.00 | $18.00 | $35.00 | $55.00 |
| 42 | Median divider thrie rail (type 2) (706-06.02) | LF | 18 | $25.00 | $28.00 | $142.00 | $50.00 |
| 43 | Radius rail (706-06.03) | LF | 1,300 | $30.00 | $36.00 | $33.00 | $55.00 |
| 44 | Radius rail long post (6-9 FT) (706-06.05) | LF | 45 | $30.00 | $37.00 | $35.00 | $60.00 |
| 45 | Radius rail long post (9-12 FT) (706-06.06) | LF | 15 | $30.00 | $35.00 | $40.50 | $65.00 |
| 46 | Rounded end element (706-10.26) | EACH | 50 | $60.00 | $125.00 | $100.00 | $250.00 |
| 47 | RE-align guardrail (706-10.54) | LF | 5,000 | $12.00 | $5.00 | $5.00 | $22.00 |
| 48 | Buffer ends 88" (706-10.56) | EACH | 4 | $50.00 | $10.00 | $100.00 | $500.00 |
| 49 | Hazard markers (706-10.71) | EACH | 4 | $50.00 | $45.00 | $45.00 | $250.00 |
| 50 | Pull and reinstall guardarail post for verification (706-10.72) | EACH | 5 | $30.00 | $100.00 | $139.00 | $200.00 |
| 51 | Concrete barrier wall repair (706-10.74) | CY | 1 | $5,000.00 | $4,500.00 | $3,500.00 | $5,000.00 |
| 52 | Michigan and modified michigan end shoe (706-10.80) | EACH | 3 | $290.00 | $24.00 | $78.00 | $250.00 |
| 53 | Guardrail reflectors (706-10.81) | EACH | 1,500 | $17.00 | $15.00 | $22.00 | $25.00 |
| 54 | Concrete bridge end or pier protection repair (706-10.82) | CY | 1 | $4,700.00 | $1,500.00 | $3,500.00 | $6,000.00 |
| 55 | Drill BR. par. wall for michigan end shoe (706-10.83) | EACH | 5 | $1,000.00 | $250.00 | $500.00 | $500.00 |
| 56 | Guardrail post hinge reflectors (706-10.84) | EACH | 1,500 | $22.00 | $15.00 | $22.00 | $7.50 |
| 57 | Lane closure (712-01.02) | EACH | 1,000 | $1,200.00 | $1,360.00 | $1,000.00 | $1,750.00 |
| 58 | Truck mounted attenuator W/mssage board (712-08.20) | DAY | 200 | $520.00 | $1,000.00 | $1,500.00 | $1,200.00 |
| 59 | Mobilization (717-01) | LS | 1 | $200,000 | $200,000 | $400,000 | $450,000 |
| 60 | Mobilization (emergency call-out) (717-01.04) | EACH | 25 | $6,500.00 | $1,500.00 | $4,750.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.