TDOT contract CNZ077 bid tabulation
The interchange lighting on i-40 at the junction of u.s. 70 (s.r. 1) (exit 66, l.m. 0.65). Let by Tennessee DOT on February 7, 2025, Haywood County. 4 bids received; low bid $989,715 by Davis H. Elliot Construction Company, Inc..
- Owner
- Tennessee DOT
- Letting
- 07 FEB 2025
- Pay items
- 27
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Davis H. Elliot Construction Company, Inc. | $989,715 | Low |
| 2 | Wade Electric Company, Inc. | $1,204,665 | +22% |
| 3 | Stansell Electric Company, Inc. | $1,292,107 | +31% |
| 4 | Shelby Electric Company, Inc. | $1,450,933 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Davis H. Elliot Construction Company, Inc. | 2. Wade Electric Company, Inc. | 3. Stansell Electric Company, Inc. | 4. Shelby Electric Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Temporary silt fence (without backing) (209-08.03) | LF | 9,200 | $2.00 | $5.75 | $2.00 | $7.00 |
| 2 | High-visibility construction fence (707-08.11) | LF | 810 | $1.75 | $4.00 | $3.00 | $5.00 |
| 3 | Traffic control (712-01) | LS | 1 | $10,000 | $5,000.00 | $34,950 | $50,000 |
| 4 | Signs (construction) (712-06) | SF | 688 | $8.10 | $7.35 | $15.00 | $11.00 |
| 5 | Arrow board (type C) (712-08.03) | EACH | 2 | $200.00 | $1,250.00 | $2,500.00 | $2,925.00 |
| 6 | Jacked or bored conduit (714-03) | LF | 1,225 | $10.00 | $24.00 | $56.00 | $28.25 |
| 7 | Direct burial conduit (2" PVC, schedule 40) (714-03.01) | LF | 8,872 | $6.50 | $10.00 | $13.50 | $12.00 |
| 8 | Pull boxes (type C) (714-05.04) | EACH | 23 | $2,500.00 | $1,000.00 | $1,265.00 | $1,725.75 |
| 9 | Cable (1/C # 10 AWG) (714-06.03) | LF | 4,225 | $0.63 | $1.50 | $1.50 | $1.30 |
| 10 | Cable (1/C # 8 AWG) (714-06.04) | LF | 3,630 | $0.88 | $1.75 | $1.90 | $1.65 |
| 11 | Cable (1/C # 6 AWG) (714-06.05) | LF | 23,986 | $1.17 | $2.00 | $2.30 | $2.25 |
| 12 | Light standards (40' M.H. with metal foundation) (714-08.09) | EACH | 32 | $4,900.00 | $6,369.00 | $6,665.00 | $6,033.50 |
| 13 | Light standards (high mast - 80' M.H.) (714-08.10) | EACH | 1 | $50,900 | $51,924 | $40,800 | $60,000 |
| 14 | Light standards (high mast - 100' M.H.) (714-08.11) | EACH | 2 | $59,000 | $54,703 | $44,000 | $67,500 |
| 15 | Light standards (high mast - 120' M.H.) (714-08.12) | EACH | 3 | $71,000 | $71,665 | $53,950 | $82,500 |
| 16 | Foundation for light standards - high mast (80' to 120' M.H.) (714-08.27) | EACH | 6 | $3,500.00 | $15,000 | $19,850 | $15,288 |
| 17 | Foundation for light standards - roadway (40' M.H.) (714-08.28) | EACH | 32 | $500.00 | $2,000.00 | $1,065.00 | $2,000.00 |
| 18 | Luminaires (180 watt LED for offset poles) (714-09.09) | EACH | 32 | $1,500.00 | $1,355.00 | $1,315.00 | $1,130.00 |
| 19 | Luminaires (295 watt LED high mast) (714-09.11) | EACH | 32 | $2,500.00 | $1,738.00 | $1,865.00 | $2,400.00 |
| 20 | Control center (no. 1) (714-12.01) | LS | 1 | $11,000 | $15,000 | $12,700 | $21,000 |
| 21 | Control center (no. 2) (714-12.02) | LS | 1 | $11,000 | $15,000 | $12,700 | $21,000 |
| 22 | Electrical connection (control center no. 1) (714-25.01) | LS | 1 | $5,000.00 | $5,000.00 | $4,690.00 | $35,000 |
| 23 | Electrical connection (control center no. 2) (714-25.02) | LS | 1 | $5,000.00 | $6,500.00 | $4,835.00 | $35,000 |
| 24 | Mobilization (717-01) | LS | 1 | $49,491 | $54,000 | $131,000 | $50,000 |
| 25 | Temporary seeding (with mulch) (801-01.07) | UNIT | 9 | $37.00 | $55.00 | $51.00 | $65.00 |
| 26 | Water (seeding & sodding) (801-03) | MG | 1 | $200.00 | $50.00 | $276.00 | $60.00 |
| 27 | Sodding (new sod) (803-01) | SY | 915 | $7.50 | $5.50 | $10.50 | $6.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.