TDOT contract CNZ223 bid tabulation
The ada curb ramp upgrades on various state routes. Let by Tennessee DOT on August 15, 2025, Sullivan And Washington Counties. 3 bids received; low bid $437,159 by Southern Constructors, Inc..
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 13
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Constructors, Inc. | $437,159 | Low |
| 2 | Baker's Construction Services, Inc. | $631,696 | +45% |
| 3 | Summers-Taylor, Inc. | $694,482 | +59% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Constructors, Inc. | 2. Baker's Construction Services, Inc. | 3. Summers-Taylor, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $27,000 | $29,119 | $16,000 |
| 2 | Removal of trash and debris (202-01.03) | LS | 1 | $10,000 | $25,000 | $12,400 |
| 3 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 99 | $25.00 | $100.49 | $871.00 |
| 4 | Removal of curb and gutter (description) (202-08.15) | LF | 675 | $13.00 | $45.68 | $92.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 39 | $68.00 | $89.65 | $572.00 |
| 6 | Concrete sidewalk (4 ") (701-01.01) | SF | 887 | $25.00 | $42.08 | $53.50 |
| 7 | Concrete curb ramp (retrofit) (701-02.01) | SF | 3,986 | $42.00 | $59.80 | $65.00 |
| 8 | Detectable warning surface (rehabilitation) (701-02.06) | SF | 42 | $60.00 | $95.06 | $300.00 |
| 9 | Concrete curb (702-01) | CY | 4 | $1,750.00 | $1,936.40 | $4,500.00 |
| 10 | Concrete combined curb & gutter (702-03) | CY | 31 | $1,050.00 | $1,202.34 | $1,100.00 |
| 11 | Traffic control (712-01) | LS | 1 | $110,000 | $135,000 | $75,500 |
| 12 | Mobilization (717-01) | LS | 1 | $43,000 | $72,000 | $42,500 |
| 13 | Seeding (with mulch) (801-01) | UNIT | 4 | $400.00 | $400.00 | $1,550.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.