TxDOT contract A00061424 bid tabulation
Resurface Roadway, FM 920 (RIC WILLIAMSON to FM 51). Let by Texas DOT on October 9, 2025, Parker, Fort Worth District. 10 bids received; low bid $5,006,549 by Jagoe-Public Company, -39% against the engineer's estimate of $8,229,059.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 92
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jagoe-Public Company | $5,006,549 | Low | -39% |
| 2 | Northeastern Pavers, LLC | $5,010,739 | 0.0% | -39% |
| 3 | Austin Bridge & Road Services, LP | $5,347,687 | +7.0% | -35% |
| 4 | Texas Materials Group, Inc. | $5,518,783 | +10% | -33% |
| 5 | Foutsco Paving Company, LLC | $5,671,822 | +13% | -31% |
| 6 | Peachtree Construction, LTD. | $6,444,366 | +29% | -22% |
| 7 | Overland Corporation | $6,547,525 | +31% | -20% |
| 8 | Zack Burkett Co. | $6,582,386 | +31% | -20% |
| 9 | Eurovia Atlantic Coast LLC | $7,109,246 | +42% | -14% |
| 10 | Grey Sky Construction LLC | $8,007,848 | +60% | -3.0% |
Engineer's estimate: $8,229,059.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jagoe-Public Company | 2. Northeastern Pavers, LLC | 3. Austin Bridge & Road Services, LP | 4. Texas Materials Group, Inc. | 5. Foutsco Paving Company, LLC | 6. Peachtree Construction, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $1,500.00 | $1,300.00 | $1,200.00 | $5,000.00 | $2,000.00 | $1,000.00 | $3,000.00 |
| 2 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 850 | $32.00 | $20.00 | $22.50 | $11.96 | $20.00 | $12.00 | $22.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 20 | $90.00 | $70.00 | $170.00 | $153.78 | $200.00 | $200.00 | $164.00 |
| 4 | Backfill (type A) (134-7001) | STA | 153 | $400.00 | $100.00 | $200.00 | $100.46 | $300.00 | $150.00 | $600.00 |
| 5 | Furn & place topsoil (3") (160-7001) | SY | 97 | $10.00 | $26.00 | $75.00 | $40.00 | $20.00 | $1.00 | $48.00 |
| 6 | Block sodding (162-7002) | SY | 97 | $15.00 | $26.00 | $12.00 | $10.00 | $20.00 | $10.00 | $25.00 |
| 7 | Vegetative watering (168-7001) | TGL | 3 | $100.00 | $100.00 | $500.00 | $450.00 | $500.00 | $450.00 | $1,100.00 |
| 8 | Salvage, haul & stockpile reclaimed asphalt PV (0 to 2") (305-7002) | SY | 1,076 | $5.00 | $2.00 | $5.00 | $7.00 | $2.05 | $4.00 | $2.25 |
| 9 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 15,389 | $200.00 | $145.50 | $150.00 | $159.20 | $150.00 | $171.50 | $168.00 |
| 10 | SP mixes SP-D sac-B PG70-28 (level-UP) (344-7059) | TON | 730 | $180.00 | $146.00 | $135.00 | $152.00 | $185.00 | $130.00 | $250.00 |
| 11 | Tack coat (344-7077) | GAL | 22,664 | $6.00 | $0.50 | $4.00 | $0.20 | $0.01 | $0.10 | $1.00 |
| 12 | Flexible pavement structure repair(6") (351-7005) | SY | 2,179 | $80.00 | $60.00 | $55.00 | $50.00 | $62.00 | $56.00 | $60.00 |
| 13 | Flexible pavement structure repair(8") (351-7007) | SY | 2,934 | $90.00 | $70.00 | $65.00 | $70.00 | $70.00 | $64.00 | $77.00 |
| 14 | Flexible pavement structure repair(10") (351-7009) | SY | 10,392 | $150.00 | $72.00 | $75.00 | $82.00 | $85.00 | $80.00 | $93.00 |
| 15 | Flexible pavement structure repair(15") (351-7014) | SY | 950 | $200.00 | $105.00 | $110.00 | $127.00 | $127.50 | $100.00 | $150.00 |
| 16 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 85,870 | $2.00 | $2.00 | $2.20 | $2.05 | $1.00 | $2.75 | |
| 17 | Plane & text asphalt concrete pavement(0" to 3") (354-7003) | SY | 29,592 | $6.00 | $3.00 | $2.25 | $2.50 | $3.05 | $1.20 | $3.55 |
| 18 | Plane & text asphalt concrete pavement(4" to 6") (354-7011) | SY | 5,000 | $9.00 | $5.00 | $5.50 | $8.98 | $3.00 | $10.00 | |
| 19 | Riprap (mow strip)(4 in) (432-7013) | CY | 11.10 | $700.00 | $1,100.00 | $850.00 | $758.70 | $750.00 | $580.00 | $815.00 |
| 20 | Adjusting manholes & inlets (479-7003) | EACH | 25 | $99.00 | $800.00 | $2,000.00 | $1,295.63 | $1,800.00 | $2,500.00 | $1,925.00 |
| 21 | Mobilization (500-7001) | LS | 1 | $748,096 | $556,000 | $500,000 | $588,246 | $550,000 | $500,000 | $575,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $12,000 | $5,000.00 | $15,000 | $3,185.64 | $61,600 | $100,000 | $25,000 |
| 23 | Portable changeable message sign (503-7001) | DAY | 342 | $130.00 | $25.00 | $0.01 | $0.93 | $30.00 | $1.00 | $50.00 |
| 24 | TMA (stationary) (505-7001) | DAY | 264 | $300.00 | $50.00 | $0.01 | $1.25 | $0.01 | $1.00 | $150.00 |
| 25 | TMA (mobile operation) (505-7003) | DAY | 24 | $500.00 | $200.00 | $0.01 | $2.00 | $0.01 | $1.00 | $250.00 |
| 26 | Temporary sediment control fence (install) (506-7039) | LF | 1,080 | $5.00 | $3.50 | $4.25 | $3.65 | $7.00 | $5.00 | $5.50 |
| 27 | Temporary sediment control fence (remove) (506-7041) | LF | 1,080 | $1.00 | $1.00 | $1.50 | $1.20 | $2.00 | $1.00 | $2.75 |
| 28 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 150 | $8.00 | $16.00 | $8.00 | $5.95 | $10.00 | $5.00 | $19.00 |
| 29 | Biodegradable erosion control logs (remove) (506-7046) | LF | 150 | $3.00 | $0.80 | $1.50 | $1.25 | $3.00 | $1.00 | $4.75 |
| 30 | One-way traffic control (flagger cont) (510-7001) | HR | 3,520 | $90.00 | $35.00 | $0.01 | $0.01 | $0.01 | $1.00 | $95.00 |
| 31 | One-way traffic control (pilot car) (510-7002) | HR | 704 | $255.00 | $100.00 | $0.01 | $398.61 | $0.01 | $1.00 | $200.00 |
| 32 | Concrete curb & gutter (type II) (529-7009) | LF | 850 | $55.00 | $50.00 | $65.00 | $37.75 | $61.00 | $37.00 | $65.00 |
| 33 | Driveways (ACP) (530-7010) | SY | 55 | $100.00 | $45.00 | $100.00 | $85.00 | $300.00 | $125.00 | $62.00 |
| 34 | Turnouts (ACP) (530-7018) | SY | 352 | $130.00 | $35.00 | $100.00 | $14.00 | $80.00 | $50.00 | $62.00 |
| 35 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 9,686 | $0.30 | $0.75 | $0.16 | $0.01 | $0.60 | $0.33 | |
| 36 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 6,399 | $0.30 | $0.75 | $0.18 | $0.01 | $0.20 | $0.33 | |
| 37 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $12.50 | $33.00 | $30.00 | $25.00 | $25.00 | $25.00 | $27.25 |
| 38 | Remove metal beam guard fence (542-7001) | LF | 50 | $4.00 | $3.75 | $3.50 | $3.00 | $3.00 | $3.00 | $3.25 |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $4,200.00 | $3,500.00 | $2,950.00 | $2,950.00 | $2,950.00 | $3,300.00 |
| 40 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $350.00 | $360.00 | $350.00 | $250.00 | $250.00 | $250.00 | $275.00 |
| 41 | Install delineator assembly (D-SW)SZ 1(WFLX)SRF (658-7006) | EACH | 3 | $110.00 | $110.00 | $100.00 | $100.00 | $120.00 | $89.00 | $120.00 |
| 42 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 14 | $120.00 | $110.00 | $100.00 | $100.00 | $120.00 | $89.00 | $120.00 |
| 43 | Remove delin & object marker assms (658-7078) | EACH | 14 | $75.00 | $30.00 | $30.00 | $35.00 | $20.00 | $25.00 | $20.00 |
| 44 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 3,060 | $0.20 | $0.24 | $0.20 | $0.20 | $0.20 | $0.26 | |
| 45 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 43,989 | $1.00 | $0.20 | $0.20 | $0.20 | $0.20 | $0.20 | $0.22 |
| 46 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 4,850 | $3.00 | $0.30 | $0.35 | $0.40 | $0.40 | $0.40 | $0.38 |
| 47 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 344 | $1.00 | $1.50 | $2.00 | $2.00 | $2.00 | $1.65 | |
| 48 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 2,222 | $8.00 | $2.00 | $2.35 | $3.00 | $3.00 | $3.00 | $2.55 |
| 49 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 42 | $100.00 | $75.00 | $80.00 | $50.00 | $50.00 | $50.00 | $87.30 |
| 50 | Work zone pavement marking non-removing (W)(double arrow) (662-7019) | EACH | 1 | $170.00 | $100.00 | $100.00 | $80.00 | $80.00 | $80.00 | $110.00 |
| 51 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 29 | $115.00 | $70.00 | $90.00 | $55.00 | $55.00 | $55.00 | $98.00 |
| 52 | Work zone pavement marking non-removing(W)36"(yld tri) (662-7032) | EACH | 24 | $30.00 | $25.00 | $40.00 | $60.00 | $60.00 | $60.00 | $44.00 |
| 53 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 2,702 | $0.20 | $0.24 | $0.20 | $0.20 | $0.20 | $0.25 | |
| 54 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 45,187 | $1.00 | $0.20 | $0.20 | $0.20 | $0.20 | $0.20 | $0.22 |
| 55 | Work zone pavement marking non-removing (Y)12"(solid) (662-7040) | LF | 123 | $1.00 | $1.30 | $1.25 | $1.25 | $1.25 | $1.40 | |
| 56 | Work zone pavement marking non-removing (Y)24"(solid) (662-7042) | LF | 707 | $5.00 | $2.00 | $2.35 | $2.35 | $2.35 | $2.35 | $2.60 |
| 57 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 504 | $2.00 | $3.00 | $2.00 | $0.50 | $0.84 | $1.00 | $3.00 |
| 58 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 5,696 | $2.00 | $3.00 | $2.00 | $0.50 | $0.84 | $1.00 | $3.00 |
| 59 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 4,850 | $4.00 | $1.00 | $0.90 | $0.80 | $0.80 | $0.80 | $1.00 |
| 60 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 344 | $4.00 | $3.70 | $3.25 | $3.25 | $3.25 | $4.00 | |
| 61 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,222 | $10.00 | $7.00 | $6.50 | $6.00 | $6.00 | $6.00 | $7.10 |
| 62 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 42 | $200.00 | $170.00 | $125.00 | $140.00 | $140.00 | $140.00 | $136.00 |
| 63 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 1 | $250.00 | $260.00 | $185.00 | $215.00 | $215.00 | $215.00 | $202.00 |
| 64 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 29 | $200.00 | $180.00 | $140.00 | $145.00 | $145.00 | $145.00 | $153.00 |
| 65 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 24 | $55.00 | $70.00 | $50.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 66 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 123 | $4.00 | $3.70 | $3.25 | $3.25 | $3.25 | $4.00 | |
| 67 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 707 | $10.00 | $10.00 | $6.50 | $8.00 | $8.00 | $8.00 | $7.00 |
| 68 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 5,441 | $1.00 | $0.99 | $0.80 | $0.80 | $0.80 | $1.10 | |
| 69 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 3,060 | $0.70 | $0.65 | $0.54 | $0.54 | $0.54 | $0.70 | |
| 70 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 38,548 | $1.00 | $0.60 | $0.60 | $0.51 | $0.51 | $0.51 | $0.65 |
| 71 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 2,702 | $0.70 | $0.65 | $0.54 | $0.54 | $0.54 | $0.70 | |
| 72 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 45,187 | $1.00 | $0.60 | $0.60 | $0.51 | $0.51 | $0.51 | $0.65 |
| 73 | Pavement sler 6" (666-7347) | LF | 521 | $1.00 | $0.30 | $0.17 | $0.23 | $0.23 | $0.23 | $0.20 |
| 74 | Pavement sler 8" (666-7348) | LF | 72 | $1.00 | $0.40 | $0.24 | $0.35 | $0.35 | $0.35 | $0.25 |
| 75 | Pavement sler 12" (666-7350) | LF | 208 | $1.25 | $0.76 | $1.00 | $1.00 | $1.00 | $0.80 | |
| 76 | Pavement sler 24" (666-7352) | LF | 172 | $2.00 | $2.50 | $1.35 | $2.00 | $2.00 | $2.00 | $1.50 |
| 77 | Pavement sler (yld tri) (666-7365) | EACH | 24 | $20.00 | $30.00 | $10.75 | $25.00 | $25.00 | $25.00 | $11.75 |
| 78 | Reflectorized pavement marker type I-C (672-7002) | EACH | 264 | $6.00 | $4.50 | $3.95 | $3.75 | $3.75 | $3.75 | $4.30 |
| 79 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,510 | $6.00 | $4.50 | $3.95 | $3.75 | $3.75 | $3.75 | $4.30 |
| 80 | Eliminating existing PM & markers (4") (677-7001) | LF | 2 | $1.00 | $1.25 | $5.00 | $1.00 | $1.00 | $1.00 | $5.45 |
| 81 | Eliminating existing PM & markers (8") (677-7004) | LF | 1 | $1.00 | $1.25 | $5.00 | $1.00 | $1.00 | $1.00 | $5.45 |
| 82 | Eliminating existing PM & markers (12") (677-7006) | LF | 312 | $2.00 | $1.25 | $1.60 | $1.00 | $1.00 | $1.00 | $1.75 |
| 83 | Eliminating existing PM & markers (24") (677-7008) | LF | 25 | $5.00 | $3.75 | $2.70 | $3.00 | $3.00 | $3.00 | $2.95 |
| 84 | Pavement surface preparation for marking (6") (678-7002) | LF | 3,424 | $1.00 | $0.15 | $0.02 | $0.15 | $0.15 | $0.15 | $0.02 |
| 85 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,159 | $1.00 | $0.25 | $0.06 | $0.25 | $0.25 | $0.25 | $0.07 |
| 86 | Pavement surface preparation for marking (12") (678-7006) | LF | 208 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | $0.55 | |
| 87 | Pavement surface preparation for marking (24") (678-7008) | LF | 251 | $2.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.10 |
| 88 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 7 | $50.00 | $35.00 | $10.00 | $35.00 | $35.00 | $35.00 | $11.00 |
| 89 | Pavement surface preparation for marking (word) (678-7016) | EACH | 7 | $50.00 | $40.00 | $15.00 | $40.00 | $40.00 | $40.00 | $16.00 |
| 90 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 24 | $20.00 | $30.00 | $5.00 | $30.00 | $30.00 | $30.00 | $5.50 |
| 91 | Tree removal (36" - 42" diameter) (752-7010) | EACH | 1 | $1,000.00 | $9,000.00 | $5,000.00 | $3,350.00 | $6,000.00 | $500.00 | $4,000.00 |
| 92 | Drain inlet cleaning (764-7001) | EACH | 11 | $100.00 | $1,000.00 | $3,000.00 | $1,278.54 | $2,780.00 | $2,000.00 | $2,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.