TxDOT contract A00120927 bid tabulation
Surfacing/Roadway Restoration, US 60 (5TH STREET IN FRIONA to WALNUT AVE IN FRIONA). Let by Texas DOT on August 6, 2026, Parmer, Lubbock District. 5 bids received; low bid $9,764,859 by A. L. Helmcamp, Inc., -2.9% against the engineer's estimate of $10,053,819.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 108
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A. L. Helmcamp, Inc. | $9,764,859 | Low | -3.0% |
| 2 | J. Lee Milligan, Inc. | $10,064,052 | +3.0% | 0.0% |
| 3 | Duininck, Inc. | $10,975,634 | +12% | +9.0% |
| 4 | RK Hall, LLC | $11,340,406 | +16% | +13% |
| 5 | James Hamilton Construction Co. | $12,539,274 | +28% | +25% |
Engineer's estimate: $10,053,819.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. A. L. Helmcamp, Inc. | 2. J. Lee Milligan, Inc. | 3. Duininck, Inc. | 4. RK Hall, LLC | 5. James Hamilton Construction Co. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Subgr widen (OC) (112-7001) | STA | 23 | $875.00 | $2,500.00 | $3,300.00 | $2,345.92 | $2,500.00 | |
| 2 | Backfill (type B) (134-7002) | STA | 23 | $350.00 | $250.00 | $365.00 | $369.52 | $1,000.00 | |
| 3 | Blading (150-7001) | STA | 23 | $150.00 | $400.00 | $135.00 | $531.18 | $350.00 | |
| 4 | Proof rolling (216-7001) | HR | 40 | $160.00 | $200.00 | $280.00 | $220.00 | $179.82 | $150.00 |
| 5 | Rework BS metal (type D)(surface)(ord comp) (251-7083) | SY | 70,270 | $1.00 | $0.75 | $2.25 | $1.65 | $2.83 | $5.00 |
| 6 | Prime coat (MC-30) (310-7004) | GAL | 14,874 | $5.00 | $5.50 | $4.75 | $5.50 | $5.51 | $6.00 |
| 7 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 1,998 | $3.50 | $4.50 | $5.35 | $4.30 | $7.00 | |
| 8 | Fog seal (CSS-1H) (315-7004) | GAL | 12,649 | $5.00 | $2.75 | $4.50 | $5.30 | $4.31 | $4.00 |
| 9 | D-GR HMA type D sac-A PG76-28 (341-7060) | TON | 800 | $150.00 | $218.00 | $190.00 | $220.00 | $179.51 | $390.00 |
| 10 | Tack coat (341-7082) | GAL | 16,043 | $5.00 | $4.75 | $7.15 | $2.50 | $5.04 | $5.00 |
| 11 | D-GR HMA type-B sac-B PG76-28 (341-7087) | TON | 25,657 | $175.00 | $180.00 | $140.00 | $160.00 | $173.35 | $190.00 |
| 12 | Stone-MTRX-asphalt SMA-D sac-A PG76-28 (346-7010) | TON | 8,292 | $190.00 | $225.00 | $203.00 | $216.00 | $206.13 | $175.00 |
| 13 | Flexible pavement structure repair(3") (351-7002) | SY | 1,405 | $60.00 | $72.00 | $52.00 | $71.00 | $159.06 | $73.00 |
| 14 | Planing asphalt concrete pavement(0" to 8") (354-7036) | SY | 70,270 | $8.00 | $4.25 | $9.00 | $10.50 | $8.80 | $6.25 |
| 15 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 30 | $315.00 | $380.00 | $385.00 | $385.00 | $385.00 | |
| 16 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 44 | $630.00 | $760.00 | $770.00 | $770.00 | $770.00 | |
| 17 | Riprap (concrete)(5 in) (432-7002) | CY | 1.35 | $788.00 | $1,840.00 | $1,800.00 | $1,815.00 | $1,815.00 | |
| 18 | Clean existing culverts (480-7002) | CY | 48 | $100.00 | $196.00 | $550.00 | $110.00 | $110.00 | $825.00 |
| 19 | Remove STR (driveway culvert) (496-7038) | EACH | 1 | $2,017.00 | $3,300.00 | $1,100.00 | $550.00 | $2,250.00 | |
| 20 | Mobilization (500-7001) | LS | 1 | $914,000 | $750,000 | $1,107,000 | $1,075,000 | $1,253,918 | $1,500,000 |
| 21 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $20,000 | $11,000 | $55,000 | $65,000 | $50,836 | $98,000 |
| 22 | Portable changeable message sign (503-7001) | DAY | 726 | $150.00 | $35.00 | $125.00 | $110.00 | $52.27 | $50.00 |
| 23 | TMA (stationary) (505-7001) | DAY | 422 | $150.00 | $325.00 | $325.00 | $275.00 | $558.06 | $300.00 |
| 24 | TMA (mobile operation) (505-7003) | DAY | 30 | $300.00 | $750.00 | $1,000.00 | $990.00 | $105.94 | $950.00 |
| 25 | Sandbags for erosion control (506-7035) | EACH | 110 | $15.00 | $26.00 | $25.00 | $27.50 | $27.50 | $75.00 |
| 26 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 500 | $12.00 | $10.00 | $13.00 | $13.20 | $10.00 | |
| 27 | Biodegradable erosion control logs (remove) (506-7046) | LF | 220 | $2.00 | $8.00 | $2.20 | $2.20 | $5.00 | |
| 28 | Intersections (ACP) (530-7002) | SY | 2,772 | $90.00 | $85.00 | $50.00 | $115.00 | $134.62 | $110.00 |
| 29 | In RD IL (type SA) 50T-12 (400W EQ) LED (610-7200) | EACH | 3 | $7,875.00 | $7,300.00 | $7,400.00 | $7,425.00 | $7,425.00 | |
| 30 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 1,335 | $16.00 | $26.00 | $26.50 | $26.40 | $26.00 | |
| 31 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 730 | $19.00 | $32.50 | $33.00 | $33.00 | $33.00 | |
| 32 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 35 | $21.00 | $43.25 | $44.00 | $44.00 | $44.00 | |
| 33 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 160 | $26.00 | $54.00 | $55.00 | $55.00 | $55.00 | |
| 34 | Electrical conductor (no.6) bare (620-7009) | LF | 1,112 | $3.15 | $2.90 | $2.90 | $2.92 | $3.00 | |
| 35 | Electrical conductor (no.6) insulated (620-7010) | LF | 1,703 | $3.40 | $3.35 | $3.40 | $3.41 | $3.50 | |
| 36 | Electrical conductor (no.2) insulated (620-7016) | LF | 165 | $5.25 | $6.95 | $7.05 | $7.04 | $7.00 | |
| 37 | Ground box type D (162922) (624-7007) | EACH | 2 | $1,050.00 | $2,055.00 | $2,100.00 | $2,090.00 | $2,400.00 | |
| 38 | Ground box type D (162922)W/apron (624-7008) | EACH | 3 | $1,470.00 | $2,325.00 | $2,400.00 | $2,365.00 | $2,365.00 | |
| 39 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $7,875.00 | $9,225.00 | $9,400.00 | $9,377.50 | $9,380.00 | |
| 40 | Aluminum signs (type A) (636-7001) | SF | 77.50 | $36.00 | $70.00 | $46.50 | $46.20 | $46.00 | |
| 41 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 15 | $1,040.00 | $865.00 | $1,100.00 | $1,089.00 | $1,090.00 | |
| 42 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 7 | $1,040.00 | $960.00 | $1,100.00 | $1,094.50 | $1,090.00 | |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 22 | $105.00 | $200.00 | $110.00 | $110.00 | $110.00 | |
| 44 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 20 | $16.00 | $425.00 | $16.50 | $16.50 | $16.50 | |
| 45 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 2 | $16.00 | $425.00 | $16.50 | $5.50 | $16.50 | |
| 46 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 22,944 | $0.28 | $0.22 | $0.35 | $0.23 | $0.23 | $0.33 |
| 47 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 50,025 | $0.25 | $0.22 | $0.35 | $0.23 | $0.23 | $0.33 |
| 48 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 16,744 | $0.30 | $0.22 | $0.35 | $0.23 | $0.23 | $0.33 |
| 49 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 155,250 | $0.25 | $0.20 | $0.35 | $0.21 | $0.21 | $0.33 |
| 50 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 2,596 | $2.78 | $4.50 | $4.35 | $4.70 | $4.68 | $4.40 |
| 51 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 5,192 | $1.89 | $4.50 | $4.35 | $4.70 | $4.68 | $4.40 |
| 52 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 18,247 | $0.63 | $1.00 | $1.10 | $1.05 | $1.05 | $1.10 |
| 53 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 29,812 | $0.66 | $1.00 | $1.10 | $1.05 | $1.05 | $1.10 |
| 54 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 870 | $1.27 | $1.10 | $1.50 | $1.70 | $1.98 | $1.30 |
| 55 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,128 | $1.21 | $1.10 | $1.50 | $1.70 | $1.98 | $1.25 |
| 56 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 31 | $3.15 | $1.35 | $3.30 | $3.30 | $1.40 | |
| 57 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 96 | $1.00 | $3.15 | $1.60 | $3.30 | $3.30 | $1.65 |
| 58 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 987 | $1.00 | $1.26 | $1.50 | $1.30 | $1.32 | $1.50 |
| 59 | RE prof PM (W)6"(solid) raisd prof only (666-7279) | LF | 677 | $2.63 | $4.35 | $2.75 | $2.75 | $4.40 | |
| 60 | RE prof PM (Y)6"(solid) raisd prof only (666-7280) | LF | 770 | $2.63 | $4.35 | $2.75 | $2.75 | $4.40 | |
| 61 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 5,010 | $1.00 | $1.26 | $1.05 | $1.30 | $1.32 | $1.00 |
| 62 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 6,886 | $1.00 | $1.26 | $1.00 | $1.30 | $1.32 | $1.00 |
| 63 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 4,080 | $1.00 | $1.26 | $1.05 | $1.30 | $1.32 | $1.00 |
| 64 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 25,465 | $1.00 | $0.95 | $1.00 | $0.99 | $0.99 | $1.00 |
| 65 | Prefabricated PM type B (W)(6")(broken) (668-7008) | LF | 550 | $12.50 | $9.00 | $9.20 | $9.35 | $9.35 | $9.35 |
| 66 | Prefabricated PM type B (W)(8")(solid) (668-7014) | LF | 550 | $9.50 | $13.00 | $10.80 | $13.00 | $13.20 | $11.00 |
| 67 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 595 | $33.00 | $34.00 | $38.40 | $35.50 | $35.20 | $39.00 |
| 68 | Prefabricated PM type B (W)(arrow) (668-7023) | EACH | 9 | $650.00 | $470.00 | $760.00 | $490.00 | $491.70 | $770.00 |
| 69 | Prefabricated PM type B (W)(36")(yld tri) (668-7038) | EACH | 10 | $60.00 | $63.00 | $110.00 | $66.00 | $66.00 | $110.00 |
| 70 | Prefabricated PM type B (Y)(6")(broken) (668-7049) | LF | 260 | $6.50 | $9.00 | $9.20 | $9.35 | $9.35 | $9.35 |
| 71 | Prefabricated PM type B (Y)(6")(solid) (668-7051) | LF | 2,774 | $8.00 | $8.50 | $8.65 | $8.80 | $8.80 | $8.80 |
| 72 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 873 | $16.00 | $15.00 | $16.25 | $15.50 | $15.40 | $16.50 |
| 73 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 9 | $225.00 | $404.00 | $325.00 | $425.00 | $423.50 | $330.00 |
| 74 | Reflectorized pavement marker type I-C (672-7002) | EACH | 153 | $4.00 | $4.75 | $6.75 | $4.95 | $4.95 | $6.90 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 189 | $4.00 | $4.75 | $6.75 | $4.95 | $4.95 | $6.90 |
| 76 | Eliminating existing PM & markers (6") (677-7002) | LF | 11,586 | $0.50 | $0.90 | $2.15 | $0.94 | $0.94 | $2.20 |
| 77 | Eliminating existing PM & markers (8") (677-7004) | LF | 688 | $0.50 | $1.00 | $2.45 | $1.05 | $1.05 | $2.50 |
| 78 | Eliminating existing PM & markers (12") (677-7006) | LF | 882 | $1.50 | $2.10 | $3.90 | $2.20 | $2.20 | $4.00 |
| 79 | Eliminating existing PM & markers (24") (677-7008) | LF | 252 | $3.00 | $6.30 | $5.95 | $6.60 | $6.60 | $6.10 |
| 80 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 9 | $40.00 | $126.00 | $110.00 | $130.00 | $132.00 | $110.00 |
| 81 | Pavement surface preparation for marking (6") (678-7002) | LF | 550 | $0.25 | $0.60 | $2.15 | $0.61 | $0.61 | $2.20 |
| 82 | Pavement surface preparation for marking (8") (678-7004) | LF | 550 | $0.25 | $0.70 | $1.35 | $0.72 | $0.72 | $1.40 |
| 83 | Pavement surface preparation for marking (12") (678-7006) | LF | 922 | $1.50 | $2.10 | $3.25 | $2.20 | $2.20 | $3.30 |
| 84 | Pavement surface preparation for marking (24") (678-7008) | LF | 285 | $3.50 | $4.20 | $4.35 | $4.40 | $4.40 | $4.40 |
| 85 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 9 | $12.00 | $100.00 | $110.00 | $105.00 | $104.50 | $110.00 |
| 86 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 10 | $12.00 | $8.50 | $21.65 | $8.80 | $8.80 | $22.00 |
| 87 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $42,000 | $34,500 | $35,000 | $34,925 | $34,925 | |
| 88 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 4 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 89 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 3 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 90 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 4 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 91 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 4 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 92 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 4 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 93 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 3 | $352.00 | $415.00 | $425.00 | $423.50 | $424.00 | |
| 94 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 6 | $137.00 | $350.00 | $360.00 | $357.50 | $358.00 | |
| 95 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 1 | $210.00 | $415.00 | $425.00 | $423.50 | $423.00 | |
| 96 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 390 | $4.20 | $4.90 | $4.95 | $4.95 | $5.00 | |
| 97 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 80 | $5.25 | $6.25 | $6.35 | $6.33 | $6.30 | |
| 98 | Traffic signal CBL (type A)(12 AWG)(12 conductor) (684-7017) | LF | 215 | $9.50 | $7.90 | $8.05 | $8.03 | $8.00 | |
| 99 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 1 | $42,000 | $40,500 | $41,000 | $40,911 | $40,910 | |
| 100 | Ins traffic signal PL AM(S)2 arm(55-28')lum (686-7207) | EACH | 1 | $44,625 | $47,000 | $47,500 | $47,564 | $47,600 | |
| 101 | Install of cables (690-7011) | LF | 425 | $4.50 | $3.25 | $3.30 | $3.30 | $3.30 | |
| 102 | Full - width mowing (730-7019) | CYC | 1 | $6,000.00 | $5,790.00 | $5,300.00 | $1,205.27 | $4,600.00 | |
| 103 | Litter removal (734-7002) | CYC | 2 | $1,000.00 | $3,600.00 | $3,325.00 | $4,500.00 | $1,312.75 | $3,000.00 |
| 104 | Cleaning / sweeping (outside main lane) (738-7028) | CYC | 4 | $3,000.00 | $6,000.00 | $3,100.00 | $1,700.00 | $2,750.00 | $5,400.00 |
| 105 | Reinforced fab for asphalt PVMNT overlays (3002-7001) | SY | 83,234 | $7.00 | $4.20 | $4.50 | $5.05 | $4.51 | $6.00 |
| 106 | Asphalt for reinforced fab (PG76-28) (3002-7002) | GAL | 12,485 | $6.00 | $5.60 | $4.00 | $3.80 | $4.11 | $6.00 |
| 107 | Temporary speed monitor sys (6016-7001) | EACH | 2 | $15,000 | $15,000 | $11,000 | $16,500 | $9,005.92 | $23,000 |
| 108 | LED roadside sign (6066-7001) | EACH | 2 | $3,675.00 | $5,100.00 | $3,900.00 | $3,850.00 | $4,300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.