| 1 | Removing concrete (riprap) (104-7006) | SY | 300 | $30.00 | $45.00 |
| 2 | Removing concrete (curb) (104-7016) | LF | 334 | | $16.00 |
| 3 | Removing concrete (flume) (104-7041) | SY | 35 | | $47.00 |
| 4 | Remove (0"-7") TRT/untrt base & asphalt pavement (105-7047) | SY | 2,764 | $8.00 | $5.65 |
| 5 | Remove (8"-19") TRT/untrt base & asphalt pavement (105-7119) | SY | 5,009 | $20.00 | $7.55 |
| 6 | Excavation (roadway) (110-7001) | CY | 79,600 | $13.00 | $14.00 |
| 7 | Embankment (final)(DC)(type B) (132-7004) | CY | 14,019 | $18.00 | $11.90 |
| 8 | Blading (150-7002) | HR | 127 | $275.00 | $375.00 |
| 9 | Drill seed (permanent_rural_sand) (164-7009) | SY | 368,824 | $0.30 | $0.13 |
| 10 | Proof rolling (216-7001) | HR | 252 | $125.00 | $150.00 |
| 11 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 5,162 | $30.00 | $19.50 |
| 12 | FL BS (compacted in place)(type A GR 4)(5") (247-7345) | SY | 179,731 | $15.00 | $6.42 |
| 13 | Prime coat (AE-P) (310-7001) | GAL | 65,090 | $5.00 | $4.70 |
| 14 | Asphalt (AC-20-5TR) (316-7007) | GAL | 59,244 | $5.00 | $3.87 |
| 15 | Asphalt (CRS-2P) (316-7012) | GAL | 59,244 | $5.00 | $4.90 |
| 16 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 2,855 | $150.00 | $124.00 |
| 17 | D-GR HMA type-C sac-B PG70-22 (341-7024) | TON | 1,120 | $220.00 | $150.00 |
| 18 | Tack coat (341-7082) | GAL | 502 | $15.00 | $8.76 |
| 19 | SP mixes SP-B sac-B PG70-22 (344-7005) | TON | 86,840 | $105.00 | $85.39 |
| 20 | Tack coat (344-7077) | GAL | 30,984 | $5.00 | $4.29 |
| 21 | Stone-MTRX-asphalt smar-F sac-A (346-7023) | TON | 25,564 | $150.00 | $127.00 |
| 22 | Flexible pavement structure repair(6") (351-7005) | SY | 28,131 | $55.00 | $41.50 |
| 23 | Plan & text concrete pavement(0" to 1.5") (354-7026) | SY | 137,871 | $3.00 | $1.05 |
| 24 | Cut & restoring pavement (400-7006) | SY | 874 | $100.00 | $190.00 |
| 25 | Cem stabil BKFL (400-7010) | CY | 539 | $415.00 | $210.00 |
| 26 | Temporary special shoring (403-7001) | SF | 10,554 | $35.00 | $26.25 |
| 27 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 32 | | $336.00 |
| 28 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 56 | | $525.00 |
| 29 | Class B concrete (flume) (420-7010) | CY | 5 | | $945.00 |
| 30 | Class S concrete utility protection pad (420-7149) | CY | 243 | $1,000.00 | $630.00 |
| 31 | Riprap (concrete)(5 in) (432-7002) | CY | 1,083.80 | $1,500.00 | $603.75 |
| 32 | Riprap (mow strip)(4 in) (432-7013) | CY | 52 | $1,000.00 | $603.75 |
| 33 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 136 | $430.00 | $417.17 |
| 34 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 350 | | $610.52 |
| 35 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 138 | $800.00 | $636.41 |
| 36 | Concrete box culvert (7 FT X 3 FT) (462-7015) | LF | 645 | $900.00 | $951.56 |
| 37 | Concrete box culvert (10 FT X 6 FT) (462-7034) | LF | 142 | $2,000.00 | $1,909.22 |
| 38 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 200 | $1,500.00 | $992.67 |
| 39 | Concrete box culvert (7 FT X 3 FT)(extend) (462-7070) | LF | 494 | $1,600.00 | $918.07 |
| 40 | Concrete box culvert (10 FT X 6 FT)(extend) (462-7089) | LF | 100 | $2,400.00 | $1,196.69 |
| 41 | RC pipe (CL III)(18 in) (464-7003) | LF | 0 | $90.00 | $0.00 |
| 42 | RC pipe (CL III)(24 in) (464-7005) | LF | 0 | $150.00 | $0.00 |
| 43 | RC pipe (CL III)(36 in) (464-7009) | LF | 0 | $230.00 | $0.00 |
| 44 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 2 | $60,000 | $53,432 |
| 45 | Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041) | EACH | 4 | $10,000 | $5,930.14 |
| 46 | Set (type I)(S= 5 FT)(HW= 4 FT)(4:1)(C) (467-7100) | EACH | 7 | | $8,856.38 |
| 47 | Set (type I)(S= 5 FT)(HW= 5 FT)(4:1)(C) (467-7104) | EACH | 3 | | $9,386.21 |
| 48 | Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128) | EACH | 8 | | $7,614.02 |
| 49 | Set (type I)(S= 6 FT)(HW= 4 FT)(4:1)(C) (467-7129) | EACH | 28 | $13,500 | $8,929.46 |
| 50 | Set (type I)(S= 6 FT)(HW= 6 FT)(4:1)(C) (467-7137) | EACH | 12 | $28,000 | $11,073 |
| 51 | Set (type I)(S= 7 FT)(HW= 4 FT)(4:1)(C) (467-7154) | EACH | 56 | $18,700 | $9,938.88 |
| 52 | Set (type I)(S= 7 FT)(HW= 6 FT)(3:1)(C) (467-7161) | EACH | 36 | | $10,056 |
| 53 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 6 | $2,000.00 | $2,169.56 |
| 54 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 48 | $3,500.00 | $2,659.81 |
| 55 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 4 | $5,000.00 | $7,380.33 |
| 56 | Clean existing culverts (480-7001) | EACH | 31 | $3,500.00 | $2,625.00 |
| 57 | Removing structure (wingwall) (496-7005) | EACH | 28 | $1,500.00 | $1,260.00 |
| 58 | Removing structure (headwall) (496-7006) | EACH | 6 | | $1,260.00 |
| 59 | Removing structure (pipe) (496-7007) | LF | 408 | $200.00 | $21.00 |
| 60 | Mobilization (500-7001) | LS | 1 | $4,010,000 | $1,500,000 |
| 61 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $30,000 | $15,000 |
| 62 | Portable changeable message sign (503-7002) | EACH | 4 | $15,000 | $8,250.00 |
| 63 | TMA (stationary) (505-7001) | DAY | 400 | $200.00 | $50.00 |
| 64 | TMA (mobile operation) (505-7003) | DAY | 50 | $470.00 | $935.00 |
| 65 | Construction exits (install) (type 1) (506-7020) | SY | 1,600 | $15.00 | $5.55 |
| 66 | Construction exits (remove) (506-7024) | SY | 1,600 | $10.00 | $3.26 |
| 67 | Temporary sediment control fence (install) (506-7039) | LF | 1,300 | $10.00 | $7.65 |
| 68 | Temporary sediment control fence (remove) (506-7041) | LF | 1,300 | $2.00 | $1.68 |
| 69 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 8,400 | $10.00 | $13.35 |
| 70 | Biodegradable erosion control logs (remove) (506-7046) | LF | 8,400 | $5.00 | $2.10 |
| 71 | Constructing detours (508-7001) | SY | 6,719 | $70.00 | $51.25 |
| 72 | One-way traffic control (port traffic signal) (510-7003) | MO | 8 | $8,000.00 | $4,410.00 |
| 73 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 4,020 | $30.00 | $33.60 |
| 74 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 26,970 | $15.00 | $10.50 |
| 75 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 4,020 | | $27.30 |
| 76 | Concrete curb (type II) (529-7002) | LF | 334 | | $26.25 |
| 77 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 97,384 | $0.20 | $0.19 |
| 78 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 54,954 | $0.20 | $0.23 |
| 79 | Metal W-beam guard fence (steel post) (540-7002) | LF | 2,175 | $50.00 | $35.18 |
| 80 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | | $3,202.50 |
| 81 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 175 | $100.00 | $136.50 |
| 82 | Remove metal beam guard fence (542-7001) | LF | 3,311 | $5.00 | $5.25 |
| 83 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | | $525.00 |
| 84 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,500.00 | $3,412.50 |
| 85 | Guardrail end treatment (remove) (544-7003) | EACH | 14 | $500.00 | $525.00 |
| 86 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 82 | $4,000.00 | $1,050.00 |
| 87 | Crash cushion attenuator (remove) (545-7004) | EACH | 10 | $3,000.00 | $840.00 |
| 88 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 10 | $5,500.00 | $7,875.00 |
| 89 | Remove RD IL asm (trans-base) (610-7009) | EACH | 6 | | $577.50 |
| 90 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 7 | | $6,510.00 |
| 91 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 945 | | $12.60 |
| 92 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 220 | | $36.75 |
| 93 | Electrical conductor (no.8) bare (620-7007) | LF | 1,215 | | $1.84 |
| 94 | Electrical conductor (no.8) insulated (620-7008) | LF | 2,430 | | $2.10 |
| 95 | Ground box type A (122311)W/apron (624-7002) | EACH | 4 | | $1,837.50 |
| 96 | Remove ground box (624-7013) | EACH | 1 | | $525.00 |
| 97 | Aluminum signs (type G) (636-7002) | SF | 266.50 | | $35.22 |
| 98 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 13 | $1,000.00 | $757.05 |
| 99 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 47 | $1,100.00 | $904.05 |
| 100 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 7 | $1,500.00 | $1,215.90 |
| 101 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 1 | | $2,040.15 |
| 102 | Remove SM RD SN sup&AM (644-7073) | EACH | 40 | $200.00 | $105.00 |
| 103 | Install LRSS (struct steel) (647-7001) | LB | 1,858.80 | | $7.77 |
| 104 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 31 | $45.00 | $47.25 |
| 105 | Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045) | EACH | 27 | | $84.00 |
| 106 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 40 | $110.00 | $89.25 |
| 107 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 12 | $150.00 | $89.25 |
| 108 | Remove delin & object marker assms (658-7078) | EACH | 48 | $30.00 | $43.50 |
| 109 | Work zone pavement marking non-removing (W)6"(lane drop) (662-7007) | LF | 698 | | $2.10 |
| 110 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 19,480 | $0.30 | $0.30 |
| 111 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,320 | | $0.41 |
| 112 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 261,050 | $0.30 | $0.20 |
| 113 | Work zone pavement marking removing (reflectorized) type I-C (662-7050) | LF | 132 | | $7.35 |
| 114 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 3,978 | $7.00 | $4.73 |
| 115 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 8,924 | $0.60 | $0.14 |
| 116 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 222,990 | $0.60 | $0.20 |
| 117 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 192 | $25.00 | $15.75 |
| 118 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,782 | $2.00 | $2.00 |
| 119 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 47,928 | $2.00 | $2.00 |
| 120 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,054 | $1.00 | $2.10 |
| 121 | Reflectorized pavement marking type I (W)6"(lane drop)(100MIL) (666-7012) | LF | 1,353 | $1.00 | $1.58 |
| 122 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 937 | | $1.26 |
| 123 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 470 | | $3.68 |
| 124 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 556,592 | $1.00 | $0.76 |
| 125 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 556,685 | $1.00 | $0.76 |
| 126 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 8,576 | $1.00 | $0.68 |
| 127 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 101,257 | $1.00 | $0.58 |
| 128 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 111,447 | $1.00 | $0.58 |
| 129 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 75 | $30.00 | $14.70 |
| 130 | Prefabricated PM type B (W)(LN RDCT arrow) (668-7029) | EACH | 8 | $700.00 | $630.00 |
| 131 | Reflectorized pavement marker type I-C (672-7002) | EACH | 536 | $8.00 | $4.73 |
| 132 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,931 | $5.00 | $3.94 |
| 133 | Eliminating existing PM & markers (4") (677-7001) | LF | 50,010 | $0.50 | $0.49 |
| 134 | Eliminating existing PM & markers (6") (677-7002) | LF | 470,802 | $0.50 | $0.49 |
| 135 | Bonding course (3007-7001) | GAL | 61,661 | $5.00 | $2.55 |
| 136 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 0 | $150.00 | $0.00 |
| 137 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 316 | $90.00 | $77.73 |
| 138 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 1,524 | $150.00 | $93.74 |
| 139 | Thermoplastic pipe (PP) (36") (468-7004) | LF | 144 | $230.00 | $146.31 |