TxDOT contract A00128677 bid tabulation
Highway Improvement, SH 152 (Gray C/L, East to FM 2473). Let by Texas DOT on March 5, 2025, Wheeler, Childress District. 6 bids received; low bid $14,172,579 by RK Hall, LLC, -19% against the engineer's estimate of $17,564,060.
- Owner
- Texas DOT
- Letting
- 05 MAR 2025
- Pay items
- 76
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | RK Hall, LLC | $14,172,579 | Low | -19% |
| 2 | JCCC, Inc. | $14,491,382 | +2.0% | -17% |
| 3 | Duininck, Inc. | $15,542,465 | +10% | -12% |
| 4 | J. Lee Milligan, Inc. | $16,081,108 | +13% | -8.0% |
| 5 | Overland Corporation | $16,382,883 | +16% | -7.0% |
| 6 | Kiewit Infrastructure South Co. | $18,125,883 | +28% | +3.0% |
Engineer's estimate: $17,564,060.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. RK Hall, LLC | 2. JCCC, Inc. | 3. Duininck, Inc. | 4. J. Lee Milligan, Inc. | 5. Overland Corporation | 6. Kiewit Infrastructure South Co. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 32.90 | $3,000.00 | $1,855.00 | $646.47 | $1,800.00 | $12,250 | $13,900 | $658.13 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 564 | $350.00 | $450.50 | $192.73 | $440.00 | $475.00 | $210.00 | $919.35 |
| 3 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 82 | $900.00 | $530.00 | $290.71 | $515.00 | $770.00 | $290.00 | $1,838.70 |
| 4 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 26 | $2,000.00 | $742.00 | $524.58 | $725.00 | $1,615.00 | $480.00 | $2,758.05 |
| 5 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 14 | $2,500.00 | $901.00 | $1,103.23 | $880.00 | $3,100.00 | $560.00 | $3,677.40 |
| 6 | Preparation row (tree remove) (48"-60" diameter) (100-7007) | EACH | 6 | $3,000.00 | $1,166.00 | $3,348.28 | $1,100.00 | $4,650.00 | $3,007.63 | $4,596.75 |
| 7 | Preparation row (tree remove) (>61" diameter) (100-7008) | EACH | 17 | $3,500.00 | $1,325.00 | $5,368.70 | $1,300.00 | $5,750.00 | $6,461.77 | $5,745.93 |
| 8 | Excavation (channel) (110-7002) | CY | 720 | $25.00 | $44.39 | $15.00 | $15.50 | $32.00 | $15.00 | $29.87 |
| 9 | Subgr widen (OC) (112-7001) | STA | 461 | $600.00 | $314.93 | $96.76 | $340.00 | $410.00 | $540.93 | $180.81 |
| 10 | Embankment (final)(DC)(type A) (132-7002) | CY | 10,839 | $75.00 | $21.89 | $31.58 | $38.00 | $30.00 | $21.00 | $70.96 |
| 11 | Embankment (final)(OC)(type B) (132-7003) | CY | 928 | $55.00 | $36.82 | $55.87 | $32.00 | $20.00 | $16.30 | $48.33 |
| 12 | Backfill (type A) (134-7001) | STA | 884 | $265.00 | $214.27 | $158.14 | $360.00 | $275.00 | $250.00 | $163.43 |
| 13 | Blading (150-7002) | HR | 12 | $175.00 | $253.93 | $149.56 | $170.00 | $515.00 | $225.00 | $303.91 |
| 14 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 37.43 | $900.00 | $689.00 | $590.00 | $610.00 | $625.00 | $590.00 | $829.97 |
| 15 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 37.43 | $900.00 | $583.00 | $640.00 | $660.00 | $675.00 | $640.00 | $702.28 |
| 16 | Vegetative watering (168-7001) | TGL | 3,320.10 | $35.00 | $43.03 | $37.00 | $29.00 | $10.00 | $52.10 | $80.56 |
| 17 | Proof rolling (216-7001) | HR | 20 | $75.00 | $171.52 | $109.55 | $190.00 | $100.00 | $210.00 | $232.34 |
| 18 | Cement (275-7001) | TON | 565 | $275.00 | $236.23 | $235.86 | $305.00 | $255.00 | $250.00 | $327.59 |
| 19 | Cement treat (subgrade) (8") (275-7017) | SY | 48,222 | $4.81 | $4.58 | $2.43 | $5.45 | $2.75 | $5.25 | $3.24 |
| 20 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 63,000 | $5.00 | $3.83 | $3.42 | $3.95 | $4.00 | $4.50 | $5.41 |
| 21 | D-GR HMA type-B PG76-28 (341-7013) | TON | 15,915 | $165.00 | $138.03 | $149.59 | $140.00 | $145.00 | $149.00 | $147.78 |
| 22 | D-GR HMA type D sac-A PG76-28 (341-7060) | TON | 48,596 | $165.00 | $143.78 | $154.06 | $148.00 | $140.00 | $157.00 | $154.91 |
| 23 | Tack coat (341-7082) | GAL | 44,180 | $8.00 | $5.51 | $4.59 | $4.00 | $4.35 | $5.00 | $5.49 |
| 24 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 4,445 | $3.00 | $5.84 | $2.95 | $9.80 | $4.30 | $2.39 | $3.51 |
| 25 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 2,222 | $3.10 | $8.00 | $2.60 | $8.20 | $5.75 | $3.43 | $5.62 |
| 26 | Planing asphalt concrete pavement(0" to 4") (354-7034) | SY | 2,222 | $3.20 | $8.54 | $3.94 | $8.55 | $5.95 | $3.43 | $5.62 |
| 27 | Planing asphalt concrete pavement(2") (354-7051) | SY | 30,694 | $2.85 | $2.18 | $3.77 | $3.65 | $2.15 | $1.63 | $2.27 |
| 28 | Planing asphalt concrete pavement(3") (354-7052) | SY | 911 | $4.75 | $9.27 | $5.10 | $9.85 | $7.40 | $4.42 | $8.53 |
| 29 | Planing asphalt concrete pavement(4") (354-7053) | SY | 911 | $5.20 | $9.57 | $9.52 | $9.85 | $7.70 | $4.42 | $8.90 |
| 30 | Riprap (mow strip)(4 in) (432-7013) | CY | 458.50 | $650.00 | $795.00 | $690.00 | $730.00 | $687.00 | $725.00 | $829.97 |
| 31 | Header type expansion joint (454-7009) | CF | 56 | $400.00 | $488.66 | $543.95 | $475.00 | $550.00 | $900.00 | $588.64 |
| 32 | Joint sealant (454-7010) | LF | 338 | $9.00 | $32.86 | $33.29 | $32.00 | $85.00 | $30.00 | $39.58 |
| 33 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 131 | $900.00 | $742.00 | $650.08 | $755.00 | $1,595.00 | $730.00 | $1,248.71 |
| 34 | Concrete box culvert (3 FT X 3 FT)(extend) (462-7057) | LF | 11 | $1,100.00 | $795.00 | $728.11 | $870.00 | $1,945.00 | $840.00 | $1,369.56 |
| 35 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 16 | $1,100.00 | $848.00 | $809.01 | $1,000.00 | $1,445.00 | $975.00 | $1,553.87 |
| 36 | Concrete box culvert (4 FT X 4 FT)(extend) (462-7060) | LF | 7 | $1,200.00 | $901.00 | $1,052.88 | $1,100.00 | $3,000.00 | $1,100.00 | $1,768.24 |
| 37 | Concrete box culvert (5 FT X 5 FT)(extend) (462-7064) | LF | 16 | $1,500.00 | $1,060.00 | $1,482.32 | $1,300.00 | $2,075.00 | $1,300.00 | $1,998.73 |
| 38 | Concrete box culvert (6 FT X 4 FT)(extend) (462-7067) | LF | 8 | $1,500.00 | $1,166.00 | $1,341.85 | $1,400.00 | $2,780.00 | $1,315.00 | $2,176.42 |
| 39 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 12 | $12,000 | $25,440 | $9,460.00 | $23,500 | $24,000 | $22,750 | $29,454 |
| 40 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 1 | $14,000 | $31,800 | $13,675 | $40,500 | $29,000 | $39,000 | $52,013 |
| 41 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 2 | $18,000 | $44,520 | $18,720 | $59,500 | $36,500 | $57,500 | $74,656 |
| 42 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 1 | $25,000 | $79,500 | $33,220 | $100,000 | $71,500 | $98,000 | $127,477 |
| 43 | Wingwall (PW - 2) (HW=10 FT) (466-7194) | EACH | 1 | $75,000 | $100,700 | $53,380 | $60,000 | $61,000 | $58,000 | $79,683 |
| 44 | Mobilization (500-7001) | LS | 1 | $1,700,000 | $566,903 | $1,215,217 | $1,300,000 | $1,600,000 | $1,630,000 | $1,767,671 |
| 45 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $12,000 | $12,619 | $5,746.94 | $25,000 | $32,000 | $5,000.00 | $40,000 |
| 46 | Portable changeable message sign (503-7002) | EACH | 2 | $20,000 | $18,039 | $9,000.00 | $18,500 | $26,000 | $20,000 | $25,670 |
| 47 | TMA (stationary) (505-7001) | DAY | 240 | $320.00 | $443.58 | $200.00 | $260.00 | $485.00 | $450.00 | $548.25 |
| 48 | TMA (mobile operation) (505-7003) | DAY | 20 | $320.00 | $1,212.58 | $120.00 | $930.00 | $1,055.00 | $1,500.00 | $1,080.99 |
| 49 | Rock filter dams (install) (type 1) (506-7001) | LF | 420 | $250.00 | $44.52 | $30.82 | $62.00 | $51.00 | $100.00 | $53.63 |
| 50 | Rock filter dams (remove) (506-7011) | LF | 420 | $50.00 | $15.90 | $13.09 | $15.50 | $16.00 | $22.00 | $19.15 |
| 51 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 5,150 | $6.25 | $7.42 | $4.50 | $4.65 | $8.00 | $4.50 | $8.94 |
| 52 | Biodegradable erosion control logs (remove) (506-7046) | LF | 5,150 | $2.50 | $1.06 | $0.80 | $0.83 | $4.00 | $0.80 | $1.28 |
| 53 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 171,600 | $0.20 | $0.13 | $0.13 | $0.07 | $0.25 | $0.13 | $0.09 |
| 54 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 85,800 | $0.25 | $0.13 | $0.23 | $0.07 | $0.25 | $0.13 | $0.09 |
| 55 | Metal W-beam guard fence (steel post) (540-7002) | LF | 5,360 | $34.00 | $32.78 | $34.25 | $32.00 | $33.00 | $30.75 | $39.48 |
| 56 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 12 | $2,900.00 | $3,543.02 | $2,100.00 | $3,100.00 | $3,175.00 | $2,100.00 | $3,833.18 |
| 57 | TL-2 31" short radius (complete) (540-7036) | EACH | 1 | $28,000 | $1,060.00 | $22,480 | $1,000.00 | $1,055.00 | $22,480 | $1,276.87 |
| 58 | Remove metal beam guard fence (542-7001) | LF | 5,360 | $3.30 | $2.12 | $2.00 | $2.05 | $2.10 | $2.00 | $2.55 |
| 59 | Guardrail end treatment (install) (544-7001) | EACH | 29 | $3,500.00 | $3,429.10 | $2,920.00 | $3,300.00 | $3,425.00 | $2,920.00 | $4,130.69 |
| 60 | Guardrail end treatment (remove) (544-7003) | EACH | 29 | $355.00 | $212.00 | $325.00 | $205.00 | $215.00 | $325.00 | $255.37 |
| 61 | Relocate existing mailbox (560-7012) | EACH | 1 | $490.00 | $424.00 | $280.00 | $415.00 | $425.00 | $280.00 | $510.75 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 14 | $850.00 | $901.98 | $700.00 | $880.00 | $900.00 | $700.00 | $1,086.52 |
| 63 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 19 | $675.00 | $783.02 | $768.92 | $765.00 | $780.00 | $655.00 | $943.23 |
| 64 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 610 | $1.25 | $1.92 | $1.00 | $1.50 | $1.55 | $2.00 | $2.55 |
| 65 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,710 | $1.50 | $2.07 | $1.00 | $1.50 | $1.55 | $2.00 | $2.55 |
| 66 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,350 | $1.25 | $0.85 | $0.75 | $0.83 | $1.05 | $2.00 | $0.96 |
| 67 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 40 | $2.25 | $0.95 | $0.90 | $0.93 | $10.55 | $3.00 | $1.15 |
| 68 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 210 | $9.50 | $6.36 | $6.00 | $6.20 | $18.50 | $15.00 | $7.66 |
| 69 | Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060) | EACH | 8 | $550.00 | $424.00 | $400.00 | $415.00 | $635.00 | $585.00 | $510.75 |
| 70 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 12,150 | $0.50 | $0.56 | $0.52 | $0.55 | $0.80 | $0.83 | $0.77 |
| 71 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 171,600 | $0.50 | $0.55 | $0.49 | $0.54 | $0.75 | $0.67 | $0.77 |
| 72 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 4,937 | $0.60 | $0.56 | $0.52 | $0.55 | $0.80 | $0.83 | $0.77 |
| 73 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 95,958 | $0.55 | $0.55 | $0.49 | $0.54 | $0.75 | $0.67 | $0.77 |
| 74 | Reflectorized pavement marker type I-C (672-7002) | EACH | 610 | $4.00 | $4.77 | $4.50 | $4.65 | $5.30 | $5.65 | $6.07 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,710 | $3.75 | $4.77 | $4.50 | $4.65 | $5.30 | $5.65 | $6.07 |
| 76 | Reloct RDSD FLSH BCN AM (solar PWRD) (685-7005) | EACH | 1 | $6,500.00 | $5,830.00 | $2,500.00 | $5,700.00 | $5,800.00 | $4,500.00 | $7,022.81 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.