TxDOT letting results, March 5, 2025
40 contracts let by Texas DOT on March 5, 2025, $226,836,657 in low bids, a median of 5 bidders per contract. On the 40 with an engineer's estimate, the low bid came in under it 37 times; median low bid -14% against the estimate.
- Owner
- Texas DOT
- Contracts
- 40
- Low bids, total
- $226,836,657
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| A00131586 | Widen Road - Add Lanes, FM 548 (North of US 80 to Windmill Farms Blvd) | Dallas District | 6 | Granite Construction Company | $80,359,417 | $84,051,634 | +5.0% | -19% | TxDOT |
| A00209380 | Resurface Roadway, US 57 (2.887 MILES EAST OF FM 481 to RM 392) | Laredo District | 2 | CK Newberry, LLC | $16,867,638 | $17,801,646 | +6.0% | -5.0% | TxDOT |
| A00061613 | Intersection Improvement, IH 35E (AT BEAR CREEK ROAD to .) | Dallas District | 4 | Ibctx, LLC | $16,449,139 | $17,565,313 | +7.0% | -4.0% | TxDOT |
| A00128677 | Highway Improvement, SH 152 (Gray C/L, East to FM 2473) | Childress District | 6 | RK Hall, LLC | $14,172,579 | $14,491,382 | +2.0% | -19% | TxDOT |
| A00208564 | Highway Improvement, US 285 (CR 232 to SH 302) | Odessa District | 2 of 6 | FNF Construction, Inc. | $10,373,162 | $10,994,155 | +6.0% | -23% | TxDOT |
| A00138848 | Rehabilitate Existing Roadway, SH 34 (SH 276 to Kaufman County Line) | Paris District | 5 | CDM Holdings | $9,373,273 | $10,827,326 | +16% | -4.0% | TxDOT |
| A00195145 | Hazard Elimination & Safety, SH 276 (FM 751 to CR 3609) | Paris District | 3 | RK Hall, LLC | $7,646,073 | $9,346,063 | +22% | -5.0% | TxDOT |
| A00187704 | Bridge Replacement, SH 317 (at BNSF Railroad to .) | Waco District | 5 | Orion Construction, LLC | $6,597,547 | $6,697,725 | +2.0% | -3.0% | TxDOT |
| A00124555 | Surfacing/Roadway Restoration, FM 530 (3.066 MILES SOUTH OF FM 2616 to CR 124) | Yoakum District | 8 | Hunter Industries, LTD. | $5,948,468 | $6,622,943 | +11% | -21% | TxDOT |
| A00140284 | Surfacing/Roadway Restoration, SH 6 (Harris C/L to N of UA 90) | Houston District | 3 | Durwood Greene Construction Co. | $5,168,419 | $5,174,407 | 0.0% | -28% | TxDOT |
| A00212937 | Install Traffic Signal, SL 12 (Forsythe Drive to Mystic Trail) | Dallas District | 2 | Garret Shields Infrastructure | $4,443,437 | $6,021,719 | +36% | -13% | TxDOT |
| A00209808 | Preventive Maintenance, FM 1660 (King Ln to FM 973) | Austin District | 5 | Lone Star Paving Company | $3,853,030 | $4,565,624 | +18% | -33% | TxDOT |
| A00212359 | TRAFFIC CONTROL SERVICES, IH0010 (Various to Various) | Beaumont District | 2 | Ross Sa Enterprise LLC | $3,671,201 | $4,998,352 | +36% | -3.0% | TxDOT |
| A00044436 | Bridge Replacement, FM 731 (AT VILLAGE CREEK to .) | Fort Worth District | 3 | Westfield Insurance Company | $3,569,154 | $3,741,531 | +5.0% | -1.0% | TxDOT |
| A00213856 | HOT MIX, US0069 (SMITH COUNTY to SMITH MTCE SECTION) | Tyler District | 2 | Big Creek Construction, LTD. | $2,966,600 | $2,989,300 | +1.0% | +6.0% | TxDOT |
| A00184772 | Install Illumination, US 380 (Stonebridge Dr to West of Bois D'' Arc Rd in McKinney) | Dallas District | 6 | Sice, Inc. | $2,885,948 | $3,100,676 | +7.0% | -27% | TxDOT |
| A00183345 | Construct Pedestrian Infrastructure, IH 410 (Callaghan Rd. to Pin Oak Dr.) | San Antonio District | 5 of 6 | E-Z Bel Construction, LLC | $2,872,934 | $3,460,984 | +20% | -1.0% | TxDOT |
| A00212610 | Bridge Maintenance, Various (EL PASO COUNTYWIDE to .) | El Paso District | 7 | International Eagle Enterprises, Inc. | $2,373,713 | $2,514,323 | +6.0% | -9.0% | TxDOT |
| A00207986 | Rehabilitate Existing Roadway, Various (Various locations to On IH 27 in Lubbock County) | Lubbock District | 5 | O. Trevino Construction, LLC | $2,186,699 | $2,590,965 | +18% | -29% | TxDOT |
| A00209741 | LARGE SIGN REPLACEMENT, IH0030 (Various Roadways in the to Dallas District) | Dallas District | 3 | Rise Up Construction LLC | $2,186,275 | $2,600,108 | +19% | -16% | TxDOT |
| A00203668 | Bridge Maintenance, SH 16 (AT OATMAN CREEK to .) | Austin District | 10 | Structural Integrity Group LLC | $2,089,129 | $2,263,826 | +8.0% | +9.0% | TxDOT |
| A00210821 | Hazard Elimination & Safety, Various (VARIOUS LOCATIONS IN to THE TYLER DISTRICT) | Tyler District | 7 | Stripe-A-Zone, LLC | $2,004,522 | $2,030,350 | +1.0% | -42% | TxDOT |
| A00193914 | Bridge Replacement, BAGBY RD (AT BRUSHY CREEK to STR# AA01-21-001 (BAGBY RD)) | Yoakum District | 6 | Lakey, Inc. | $1,929,627 | $1,955,626 | +1.0% | -7.0% | TxDOT |
| A00139797 | ACP OVERLAY, SH0035 (N. of 10th St to CR 691) | Houston District | 6 | Environmental Allies, Inc. | $1,892,569 | $1,898,948 | 0.0% | -7.0% | TxDOT |
| A00193322 | Widen Road - Add Shoulders, FM 382 (FM 604 to RUNNELS COUNTY) | Abilene District | 6 | J. H. Strain & Sons, Inc. | $1,784,682 | $2,156,894 | +21% | -24% | TxDOT |
| A00191310 | Hazard Elimination & Safety, Various (Various locations in to the Lubbock District) | Lubbock District | 5 | The Confidence Group, Inc | $1,428,552 | $1,851,166 | +30% | -15% | TxDOT |
| A00213021 | MILL AND INLAY, US0290 (RM 676 + 0.56 to RM 678 + 0.06) | Bryan District | 9 | Cornerstone Paving and Construction, L.L.C. | $1,299,406 | $1,362,797 | +5.0% | -11% | TxDOT |
| A00184249 | Off System Signal System Upgrades, TRINITY BLVD (Greenbelt Rd to Amon Carter Blvd) | Fort Worth District | 4 | Synergy Signs & Services LLC | $1,235,855 | $1,337,375 | +8.0% | -21% | TxDOT |
| A00213858 | HOT MIX, US0080 (VAN ZANDT COUNTY to VAN ZANDT MTCE SECTION) | Tyler District | 3 | Texas Materials Group, Inc. | $1,200,800 | $1,251,000 | +4.0% | -9.0% | TxDOT |
| A00213980 | DRAINAGE IMPROVEMENT AND/OR REPAIRS, FM0907 (Durante Ave to Intersection of IH 2 Frontage) | Pharr District | 7 | Lucania Contractors LLC | $1,183,371 | $1,267,047 | +7.0% | -15% | TxDOT |
| A00213976 | HOT MIX, FM1692 (VARIOUS LOCATIONS IN THE SAN ANGELO DIST to VARIOUS LOCATIONS IN THE SAN ANGELO DIST) | San Angelo District | 1 | Csa Materials Inc. | $1,144,684 | -9.0% | TxDOT | ||
| A00130696 | Surfacing/Roadway Restoration, FS 149 (FM 1488 to FM 149) | Houston District | 6 | Vulcan Materials Asphalt and Construction, LLC | $1,063,539 | $1,090,280 | +3.0% | -33% | TxDOT |
| A00210443 | Highway Improvement, FM 933 (Patton Lake Rd to FM 1133) | Waco District | 8 | Centerline Technologies, LLC | $926,962 | $948,681 | +2.0% | -44% | TxDOT |
| A00206151 | MOWING HIGHWAY RIGHT OF WAY, US0069 (Hardin County to Hardin County) | Beaumont District | 3 | P-Ville, Incorporated | $905,969 | $1,026,144 | +13% | -29% | TxDOT |
| A00213863 | Travel Information Center, IH0010 (Orange County Travel Information Center to Orange County Travel Information Center) | Maintenance Division District | 6 | Apex Alliance, LLC | $835,675 | $999,999 | +20% | -34% | TxDOT |
| A00140131 | Bridge Maintenance, Various (Various Locations Districtwide to .) | Lufkin District | 14 | Blacksmith Ventures LLC | $821,221 | $821,374 | 0.0% | -25% | TxDOT |
| A00206419 | Install/Rehabilitate Its, IH 30 (MacArthur Blvd to Belt Line Rd) | Dallas District | 2 | Light It Up Electric | $462,427 | $479,355 | +4.0% | +18% | TxDOT |
| A00176801 | Traffic Signal Improvements, AIRLINE RD (On Airline Rd in Nueces to At McArdle Rd. Intersection N and S) | Corpus Christi District | 5 | Third Coast Services LLC | $335,262 | $361,751 | +8.0% | -10% | TxDOT |
| A00184051 | Hazard Elimination & Safety, US 190 (0.1 MI W OF FM 777, EAST to 0.1 MI E OF FM 777) | Beaumont District | 5 | Third Coast Services LLC | $241,008 | $256,689 | +7.0% | -4.0% | TxDOT |
| A00209768 | Hazard Elimination & Safety, Various (Various Locations (off-system) to .) | Paris District | 9 | Rhino Equity, LLC | $86,690 | $91,520 | +6.0% | -33% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way