TxDOT contract A00131586 bid tabulation
Widen Road - Add Lanes, FM 548 (North of US 80 to Windmill Farms Blvd). Let by Texas DOT on March 5, 2025, Kaufman, Dallas District. 6 bids received; low bid $80,359,417 by Granite Construction Company, -19% against the engineer's estimate of $99,274,920.
- Owner
- Texas DOT
- Letting
- 05 MAR 2025
- Pay items
- 227
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Granite Construction Company | $80,359,417 | Low | -19% |
| 2 | Mario Sinacola & Sons Excavating, Inc. | $84,051,634 | +5.0% | -15% |
| 3 | Tiseo Paving Co. | $86,935,356 | +8.0% | -12% |
| 4 | Webber, LLC | $86,968,708 | +8.0% | -12% |
| 5 | RPM Xconstruction, LLC | $98,427,765 | +22% | -1.0% |
| 6 | Longview Bridge and Road, LTD. | $98,922,176 | +23% | 0.0% |
Engineer's estimate: $99,274,920.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Granite Construction Company | 2. Mario Sinacola & Sons Excavating, Inc. | 3. Tiseo Paving Co. | 4. Webber, LLC | 5. RPM Xconstruction, LLC | 6. Longview Bridge and Road, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 224.16 | $42,000 | $33,500 | $15,790 | $12,952 | $38,797 | $27,000 | $30,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 14,889 | $15.00 | $8.00 | $10.00 | $14.75 | $12.80 | $18.00 | $13.00 |
| 3 | Removing concrete (mowstrip) (104-7005) | LF | 661 | $10.00 | $5.00 | $10.00 | $3.15 | $12.80 | $7.50 | $25.00 |
| 4 | Removing concrete (riprap) (104-7006) | SY | 37 | $20.00 | $40.00 | $20.00 | $53.60 | $28.80 | $46.00 | $100.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 8,048 | $30.00 | $15.00 | $10.00 | $22.75 | $21.70 | $15.50 | $12.00 |
| 6 | Remove(12"-24") TRT/untrt base & asphalt pavement (105-7124) | SY | 95,787 | $15.00 | $5.00 | $7.00 | $6.90 | $11.30 | $10.60 | $15.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 128,585 | $26.00 | $15.00 | $24.00 | $21.60 | $14.40 | $24.00 | $20.00 |
| 8 | Excavation (channel) (110-7002) | CY | 3,033 | $20.00 | $35.00 | $30.00 | $24.65 | $39.00 | $25.00 | $32.00 |
| 9 | Embankment (final)(DC)(type C1) (132-7008) | CY | 81,645 | $22.00 | $17.00 | $15.00 | $13.95 | $19.00 | $20.00 | $25.00 |
| 10 | Embankment (final)(DC)(type C2) (132-7010) | CY | 548 | $70.00 | $125.00 | $25.00 | $47.25 | $27.75 | $48.00 | $50.00 |
| 11 | Compost manuf topsoil (4") (161-7002) | SY | 103,437 | $5.00 | $1.75 | $1.00 | $4.25 | $2.90 | $2.50 | $6.00 |
| 12 | Block sodding (162-7002) | SY | 103,437 | $4.00 | $4.00 | $3.99 | $6.45 | $4.50 | $4.25 | $4.50 |
| 13 | Drill seed (temporary_warm_cool) (164-7015) | SY | 86,475 | $0.39 | $0.32 | $0.19 | $0.25 | $0.35 | $0.20 | $0.22 |
| 14 | Vegetative watering (168-7001) | TGL | 30,787 | $25.00 | $9.00 | $0.10 | $9.00 | $4.50 | $1.00 | $10.00 |
| 15 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 2,755 | $31.00 | $24.00 | $30.00 | $35.90 | $25.40 | $30.00 | $45.00 |
| 16 | Lime (com or QK)(slurry) (260-7005) | TON | 19,452 | $330.00 | $290.00 | $290.00 | $312.00 | $284.00 | $277.00 | $355.00 |
| 17 | Lime TRT (existing material)(8") (260-7007) | SY | 4,852 | $10.00 | $4.10 | $10.00 | $15.20 | $17.50 | $14.00 | $5.00 |
| 18 | Lime TRT(existing material)(24") (260-7018) | SY | 238,814 | $18.00 | $12.00 | $15.00 | $15.20 | $17.10 | $13.00 | $7.00 |
| 19 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 551 | $12.00 | $10.00 | $9.00 | $10.35 | $9.60 | $10.20 | $8.00 |
| 20 | SP mixes SP-B PG64-22 (344-7001) | TON | 53,523 | $120.00 | $135.00 | $125.75 | $132.80 | $126.00 | $145.00 | $175.00 |
| 21 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 1,519 | $128.00 | $160.00 | $141.75 | $150.00 | $142.00 | $175.00 | $220.00 |
| 22 | Tack coat (344-7077) | GAL | 584 | $3.50 | $8.00 | $2.00 | $2.15 | $2.00 | $8.00 | $8.00 |
| 23 | Concrete pavement (CRCP) (10") (360-7004) | SY | 212,009 | $100.00 | $84.00 | $90.00 | $86.95 | $76.75 | $92.00 | $110.00 |
| 24 | Concrete pavement (CRCP)(hes) (10") (360-7049) | SY | 1,656 | $120.00 | $123.00 | $110.00 | $181.15 | $135.00 | $147.00 | $160.00 |
| 25 | Trench excavation protection (402-7001) | LF | 39,412 | $9.00 | $1.00 | $5.00 | $1.05 | $2.80 | $1.50 | $8.00 |
| 26 | Temporary special shoring (403-7001) | SF | 1,359 | $43.00 | $35.00 | $75.00 | $78.75 | $55.25 | $30.00 | $85.00 |
| 27 | Drilled shaft (24 in) (416-7004) | LF | 3,404 | $160.00 | $150.00 | $170.00 | $199.50 | $120.00 | $174.00 | $200.00 |
| 28 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 44 | $300.00 | $449.15 | $415.20 | $417.90 | $398.00 | $495.00 | $460.00 |
| 29 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 52 | $420.00 | $709.83 | $428.70 | $660.45 | $629.00 | $510.00 | $475.00 |
| 30 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 264 | $550.00 | $863.31 | $663.80 | $803.25 | $765.00 | $790.00 | $730.00 |
| 31 | Sound wall (419-7001) | SF | 25,740 | $75.00 | $55.00 | $38.00 | $57.75 | $40.00 | $60.00 | $75.00 |
| 32 | Retaining wall (MSE) (423-7001) | SF | 3,261 | $100.00 | $115.00 | $160.00 | $147.00 | $121.00 | $148.00 | $155.00 |
| 33 | Riprap (concrete)(5 in) (432-7002) | CY | 269 | $2,500.00 | $400.00 | $910.00 | $941.85 | $580.00 | $655.00 | $750.00 |
| 34 | Riprap (mow strip)(4 in) (432-7013) | CY | 145 | $900.00 | $550.00 | $900.00 | $708.75 | $632.00 | $830.00 | $750.00 |
| 35 | Riprap (stone protection)(18 in) (432-7043) | CY | 153 | $325.00 | $234.19 | $215.00 | $262.50 | $296.00 | $255.00 | $230.00 |
| 36 | Riprap (stone protection)(21 in) (432-7044) | CY | 199 | $260.00 | $176.77 | $215.00 | $262.50 | $312.00 | $245.00 | $230.00 |
| 37 | Bedding material (6 in) (432-7050) | CY | 40 | $200.00 | $342.63 | $175.00 | $157.50 | $181.00 | $173.00 | $250.00 |
| 38 | Rail (type C402)(HPC) (450-7037) | LF | 738 | $137.00 | $315.22 | $230.00 | $278.25 | $203.00 | $258.00 | $215.00 |
| 39 | Rail (handrail)(type F) (450-7063) | LF | 1,463 | $250.00 | $107.91 | $130.00 | $133.20 | $122.00 | $170.00 | $190.00 |
| 40 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 1,038 | $410.00 | $240.00 | $310.00 | $451.50 | $265.00 | $595.00 | $375.00 |
| 41 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 719 | $450.00 | $290.00 | $405.00 | $504.00 | $332.00 | $660.00 | $500.00 |
| 42 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 254 | $490.00 | $450.00 | $680.00 | $514.50 | $509.00 | $610.00 | $740.00 |
| 43 | Concrete box culvert (6 FT X 4 FT) (462-7012) | LF | 3,467 | $520.00 | $300.00 | $415.00 | $420.00 | $412.00 | $977.00 | $700.00 |
| 44 | Concrete box culvert (8 FT X 6 FT) (462-7023) | LF | 480 | $750.00 | $600.00 | $860.00 | $840.00 | $615.00 | $1,055.00 | $975.00 |
| 45 | Concrete box culvert (9 FT X 8 FT) (462-7030) | LF | 585 | $900.00 | $750.00 | $1,040.00 | $1,050.00 | $775.00 | $1,300.00 | $1,350.00 |
| 46 | Concrete box culvert (10 FT X 8 FT)(extend) (462-7091) | LF | 5 | $1,885.00 | $5,000.00 | $2,000.00 | $2,625.00 | $3,180.00 | $3,035.00 | $5,000.00 |
| 47 | RC pipe (CL III)(18 in) (464-7003) | LF | 2,042 | $100.00 | $100.00 | $116.00 | $126.00 | $112.00 | $165.00 | $65.00 |
| 48 | RC pipe (CL III)(24 in) (464-7005) | LF | 14,917 | $120.00 | $125.00 | $129.00 | $147.00 | $107.00 | $231.00 | $85.00 |
| 49 | RC pipe (CL III)(30 in) (464-7007) | LF | 1,081 | $150.00 | $130.00 | $163.00 | $157.50 | $124.00 | $200.00 | $115.00 |
| 50 | RC pipe (CL III)(36 in) (464-7009) | LF | 8,370 | $180.00 | $150.00 | $190.00 | $199.50 | $151.00 | $250.00 | $150.00 |
| 51 | RC pipe (CL III)(42 in) (464-7010) | LF | 1,536 | $200.00 | $175.00 | $240.00 | $241.50 | $185.00 | $300.00 | $190.00 |
| 52 | RC pipe (CL III)(48 in) (464-7011) | LF | 2,826 | $250.00 | $225.00 | $267.00 | $273.00 | $234.00 | $335.00 | $245.00 |
| 53 | RC pipe (CL III)(54 in) (464-7012) | LF | 4,104 | $350.00 | $275.00 | $326.00 | $325.50 | $286.00 | $400.00 | $275.00 |
| 54 | RC pipe (CL III)(60 in) (464-7013) | LF | 1,535 | $425.00 | $325.00 | $400.00 | $378.00 | $321.00 | $460.00 | $370.00 |
| 55 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 23 | $8,000.00 | $5,800.00 | $9,600.00 | $5,250.00 | $6,530.00 | $6,200.00 | $9,000.00 |
| 56 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 20 | $10,000 | $6,800.00 | $13,000 | $10,500 | $7,860.00 | $12,400 | $11,000 |
| 57 | Junction box(complete)(PJB)(6FTX6FT) (465-7011) | EACH | 22 | $12,000 | $9,500.00 | $16,000 | $11,025 | $10,250 | $13,000 | $12,000 |
| 58 | Junction box(complete)(PJB)(8FTX8FT) (465-7012) | EACH | 31 | $25,000 | $14,500 | $23,500 | $26,250 | $13,980 | $31,000 | $22,000 |
| 59 | Inlet (complete)(pcu)(3FT)(left) (465-7030) | EACH | 64 | $9,000.00 | $5,600.00 | $11,350 | $14,700 | $8,360.00 | $11,150 | $8,750.00 |
| 60 | Inlet (complete)(pcu)(3FT)(right) (465-7031) | EACH | 80 | $9,000.00 | $5,600.00 | $11,350 | $12,075 | $8,370.00 | $8,050.00 | $8,750.00 |
| 61 | Inlet (complete)(pcu)(3FT)(both) (465-7032) | EACH | 43 | $10,000 | $6,100.00 | $12,575 | $16,800 | $8,750.00 | $13,600 | $10,750 |
| 62 | Inlet (complete)(pcu)(4FT)(both) (465-7036) | EACH | 1 | $11,000 | $6,400.00 | $14,250 | $17,850 | $9,750.00 | $14,900 | $13,500 |
| 63 | Inlet(complete)(PSL)(SFG)(3FTX3FT-3FTX3FT) (465-7146) | EACH | 1 | $8,000.00 | $5,000.00 | $7,800.00 | $6,300.00 | $6,460.00 | $7,420.00 | $11,000 |
| 64 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 33 | $12,000 | $5,300.00 | $10,000 | $8,400.00 | $6,350.00 | $11,600 | $10,250 |
| 65 | JCT box (complete)(special) (465-7332) | EACH | 1 | $50,000 | $70,000 | $70,000 | $68,250 | $53,600 | $66,100 | $100,000 |
| 66 | Inlet(complete)(type MSE1) (465-7362) | EACH | 1 | $10,000 | $5,500.00 | $7,275.00 | $7,350.00 | $3,670.00 | $8,700.00 | $20,000 |
| 67 | Wingwall (PW - 1) (HW=12 FT) (466-7182) | EACH | 1 | $125,000 | $25,000 | $25,500 | $21,000 | $68,000 | $21,500 | $70,000 |
| 68 | Wingwall (PW - 1) (HW=13 FT) (466-7183) | EACH | 1 | $100,000 | $18,000 | $34,000 | $31,500 | $62,000 | $32,150 | $60,000 |
| 69 | Set (type I)(S= 8 FT)(HW= 7 FT)(4:1)(C) (467-7192) | EACH | 6 | $25,000 | $13,000 | $20,000 | $17,850 | $15,000 | $16,850 | $25,000 |
| 70 | Set (type I)(S= 9 FT)(HW= 8 FT)(4:1)(C) (467-7217) | EACH | 6 | $28,000 | $22,000 | $30,000 | $26,250 | $21,825 | $23,750 | $30,000 |
| 71 | Removing structure (inlet) (496-7002) | EACH | 8 | $1,450.00 | $500.00 | $2,000.00 | $1,050.00 | $1,290.00 | $1,250.00 | $795.00 |
| 72 | Removing structure (set) (496-7004) | EACH | 121 | $1,380.00 | $500.00 | $850.00 | $525.00 | $1,015.00 | $620.00 | $1,050.00 |
| 73 | Removing structure (wingwall) (496-7005) | EACH | 4 | $3,100.00 | $1,000.00 | $8,000.00 | $4,200.00 | $4,182.00 | $4,950.00 | $2,000.00 |
| 74 | Removing structure (headwall) (496-7006) | EACH | 4 | $2,130.00 | $1,000.00 | $1,750.00 | $2,100.00 | $2,091.00 | $2,475.00 | $1,750.00 |
| 75 | Removing structure (pipe) (496-7007) | LF | 5,026 | $25.00 | $25.00 | $40.00 | $52.50 | $29.50 | $62.00 | $13.00 |
| 76 | Removing structure (box culvert) (496-7008) | LF | 1,326 | $100.00 | $35.00 | $100.00 | $73.50 | $102.00 | $87.00 | $40.00 |
| 77 | Removing structure (small) (496-7036) | EACH | 1 | $3,850.00 | $500.00 | $1,500.00 | $1,575.00 | $2,126.73 | $1,860.00 | $3,500.00 |
| 78 | Mobilization (500-7001) | LS | 1 | $9,331,615 | $7,700,000 | $8,400,000 | $8,636,140 | $8,696,800 | $9,800,000 | $10,000,000 |
| 79 | Barricades, signs and traffic handling (502-7001) | MO | 32 | $30,000 | $20,500 | $70,000 | $56,450 | $139,216 | $50,000 | $20,000 |
| 80 | Portable changeable message sign (503-7002) | EACH | 4 | $22,500 | $11,000 | $9,500.00 | $20,000 | $25,510 | $26,000 | $22,000 |
| 81 | TMA (stationary) (505-7001) | DAY | 2,000 | $350.00 | $100.00 | $150.00 | $250.00 | $150.00 | $400.00 | $265.00 |
| 82 | TMA (mobile operation) (505-7003) | DAY | 150 | $700.00 | $900.00 | $1,500.00 | $1,000.00 | $150.00 | $800.00 | $330.00 |
| 83 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,921 | $45.00 | $40.00 | $30.00 | $68.25 | $35.00 | $80.00 | $58.00 |
| 84 | Rock filter dams (install) (type 3) (506-7003) | LF | 336 | $88.00 | $75.00 | $33.00 | $78.75 | $65.00 | $92.00 | $170.00 |
| 85 | Rock filter dams (remove) (506-7011) | LF | 2,257 | $17.00 | $13.00 | $1.00 | $36.75 | $13.00 | $43.00 | $26.00 |
| 86 | Construction exits (install) (type 1) (506-7020) | SY | 1,229 | $28.50 | $55.00 | $50.00 | $31.50 | $35.00 | $37.00 | $47.00 |
| 87 | Construction exits (remove) (506-7024) | SY | 1,229 | $11.00 | $12.00 | $5.00 | $17.35 | $11.50 | $20.50 | $16.00 |
| 88 | Temporary sediment control fence (install) (506-7039) | LF | 55,027 | $3.90 | $5.00 | $1.75 | $2.75 | $3.50 | $3.05 | $4.00 |
| 89 | Temporary sediment control fence (remove) (506-7041) | LF | 55,027 | $1.25 | $1.00 | $0.10 | $1.35 | $1.00 | $1.55 | $1.20 |
| 90 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 3,588 | $7.00 | $9.00 | $2.70 | $5.50 | $5.75 | $6.10 | $8.00 |
| 91 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,588 | $2.75 | $1.00 | $0.10 | $2.65 | $1.20 | $3.05 | $2.00 |
| 92 | Constructing detours (508-7001) | SY | 9,648 | $145.00 | $200.00 | $130.00 | $147.00 | $137.00 | $223.00 | $165.00 |
| 93 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 10,760 | $70.00 | $55.00 | $25.00 | $33.60 | $45.75 | $74.00 | $90.00 |
| 94 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 5,520 | $15.00 | $9.00 | $10.00 | $15.75 | $13.20 | $5.00 | $10.00 |
| 95 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 10,760 | $15.00 | $9.00 | $5.00 | $21.00 | $14.70 | $7.00 | $12.00 |
| 96 | Portable concrete traffic barrier (pinning) (512-7071) | EACH | 543 | $10.00 | $50.00 | $100.00 | $63.00 | $28.20 | $52.00 | $55.00 |
| 97 | Concrete curb (mono) (type I) (529-7006) | LF | 589 | $5.00 | $6.32 | $32.00 | $10.00 | $2.55 | $1.60 | $15.00 |
| 98 | Concrete curb (mono) (type II) (529-7007) | LF | 85,709 | $8.00 | $2.32 | $1.00 | $4.00 | $5.05 | $3.00 | $8.00 |
| 99 | Driveways (concrete) (530-7006) | SY | 5,705 | $95.00 | $85.00 | $80.00 | $102.05 | $91.00 | $122.00 | $115.00 |
| 100 | Driveways (concrete) (hes) (530-7007) | SY | 2,531 | $150.00 | $95.00 | $110.00 | $142.30 | $105.00 | $136.00 | $130.00 |
| 101 | Concrete sidewalks (4") (531-7001) | SY | 23,954 | $65.00 | $55.00 | $70.00 | $56.20 | $71.00 | $68.25 | $65.00 |
| 102 | Curb ramps (type 1) (531-7005) | EACH | 23 | $3,670.00 | $2,500.00 | $3,400.00 | $3,150.00 | $2,540.00 | $2,800.00 | $3,000.00 |
| 103 | Curb ramps (type 2) (531-7006) | EACH | 20 | $3,255.00 | $2,700.00 | $3,400.00 | $3,360.00 | $2,650.00 | $2,950.00 | $3,000.00 |
| 104 | Curb ramps (type 5) (531-7008) | EACH | 1 | $4,500.00 | $3,100.00 | $5,500.00 | $5,460.00 | $3,950.00 | $3,050.00 | $4,000.00 |
| 105 | Curb ramps (type 10) (531-7011) | EACH | 12 | $2,920.00 | $2,600.00 | $3,400.00 | $3,360.00 | $2,650.00 | $2,750.00 | $3,000.00 |
| 106 | Curb ramps (type 22) (531-7014) | EACH | 2 | $5,090.00 | $2,400.00 | $5,500.00 | $5,670.00 | $4,550.00 | $7,500.00 | $4,500.00 |
| 107 | Concrete median (536-7002) | SY | 6,742 | $75.00 | $50.00 | $80.00 | $89.35 | $115.00 | $85.00 | $85.00 |
| 108 | Right of way markers (538-7001) | EACH | 119 | $420.00 | $300.00 | $400.00 | $1,400.00 | $513.00 | $430.00 | $350.00 |
| 109 | Metal W-beam guard fence (timber post) (540-7001) | LF | 902 | $33.00 | $23.38 | $25.00 | $25.20 | $25.30 | $27.00 | $26.00 |
| 110 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $2,500.00 | $1,709.23 | $1,800.00 | $2,310.00 | $2,185.00 | $2,305.00 | $1,900.00 |
| 111 | Remove metal beam guard fence (542-7001) | LF | 661 | $4.50 | $2.01 | $2.75 | $9.00 | $2.75 | $2.90 | $2.50 |
| 112 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,625.00 | $2,840.34 | $2,800.00 | $3,150.00 | $3,025.00 | $3,200.00 | $3,200.00 |
| 113 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $670.00 | $201.09 | $250.00 | $620.00 | $300.00 | $320.00 | $250.00 |
| 114 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 18 | $2,300.00 | $493.54 | $1,500.00 | $2,100.00 | $1,295.00 | $1,375.00 | $2,200.00 |
| 115 | Crash cushion attenuator (remove) (545-7004) | EACH | 46 | $1,500.00 | $183.23 | $750.00 | $1,050.00 | $890.00 | $940.00 | $900.00 |
| 116 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 46 | $9,000.00 | $5,613.63 | $7,954.90 | $8,400.00 | $7,575.00 | $9,400.00 | $8,550.00 |
| 117 | Pipe underdrains (type 6) (6") (556-7006) | LF | 800 | $40.00 | $26.74 | $65.00 | $42.00 | $31.00 | $40.00 | $38.00 |
| 118 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 17 | $410.00 | $539.98 | $306.00 | $440.00 | $225.00 | $248.00 | $330.00 |
| 119 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 1 | $438.00 | $630.29 | $365.00 | $445.00 | $275.00 | $303.00 | $330.00 |
| 120 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 440 | $21.00 | $13.97 | $20.20 | $13.00 | $12.40 | $24.25 | $23.00 |
| 121 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 1,445 | $28.50 | $17.67 | $22.50 | $16.45 | $15.70 | $26.75 | $25.00 |
| 122 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 50 | $44.50 | $48.53 | $32.70 | $45.15 | $43.00 | $39.00 | $36.00 |
| 123 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 295 | $35.00 | $34.98 | $27.70 | $32.55 | $31.00 | $33.00 | $31.00 |
| 124 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 2,600 | $58.00 | $64.33 | $39.80 | $59.85 | $57.00 | $47.50 | $45.00 |
| 125 | Conduit (prepare) (618-7090) | LF | 740 | $1.60 | $6.18 | $2.50 | $5.75 | $5.50 | $3.00 | $3.00 |
| 126 | Electrical conductor (no.12) insulated (620-7004) | LF | 1,840 | $1.60 | $1.75 | $1.60 | $1.75 | $1.55 | $1.90 | $2.00 |
| 127 | Electrical conductor (no.8) insulated (620-7008) | LF | 7,990 | $2.00 | $2.83 | $2.40 | $2.65 | $2.50 | $2.85 | $2.75 |
| 128 | Electrical conductor (no.6) bare (620-7009) | LF | 4,730 | $2.00 | $3.31 | $2.70 | $3.10 | $2.95 | $3.25 | $3.00 |
| 129 | Ground box type A (122311)W/apron (624-7002) | EACH | 6 | $1,171.00 | $1,193.97 | $1,708.70 | $1,110.90 | $1,060.00 | $2,050.00 | $2,000.00 |
| 130 | Ground box type C (162911)W/apron (624-7006) | EACH | 22 | $1,776.00 | $1,576.53 | $2,003.80 | $1,466.85 | $1,400.00 | $2,400.00 | $2,200.00 |
| 131 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 6 | $10,901 | $11,647 | $9,080.70 | $10,837 | $10,320 | $10,800 | $10,000 |
| 132 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 49 | $780.00 | $610.00 | $615.00 | $640.50 | $793.00 | $650.00 | $1,250.00 |
| 133 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 9 | $970.00 | $865.00 | $695.00 | $908.25 | $889.00 | $730.00 | $1,600.00 |
| 134 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 17 | $890.00 | $700.00 | $725.00 | $735.00 | $825.00 | $770.00 | $1,350.00 |
| 135 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,200.00 | $1,075.00 | $969.00 | $1,128.75 | $1,185.00 | $1,020.00 | $2,150.00 |
| 136 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,890.00 | $1,235.00 | $1,195.00 | $1,296.75 | $1,200.00 | $1,260.00 | $2,400.00 |
| 137 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 1 | $1,150.00 | $1,295.00 | $1,290.00 | $1,359.75 | $1,220.00 | $1,360.00 | $2,600.00 |
| 138 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 12,511 | $0.67 | $0.31 | $0.30 | $0.50 | $0.30 | $0.55 | $0.55 |
| 139 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 1,489 | $0.85 | $0.67 | $0.65 | $0.75 | $0.65 | $0.82 | $0.85 |
| 140 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 21 | $130.00 | $118.45 | $115.00 | $120.75 | $115.00 | $220.00 | $220.00 |
| 141 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 12,872 | $0.60 | $0.31 | $0.30 | $0.50 | $0.30 | $0.55 | $0.55 |
| 142 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 4,676 | $1.20 | $1.29 | $1.26 | $1.35 | $1.25 | $1.65 | $1.70 |
| 143 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 50 | $2.50 | $2.06 | $2.00 | $2.10 | $2.00 | $3.30 | $3.50 |
| 144 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 73,591 | $1.25 | $1.13 | $1.10 | $1.25 | $1.10 | $1.65 | $1.65 |
| 145 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 2,633 | $2.75 | $1.39 | $1.35 | $1.50 | $1.35 | $1.65 | $1.65 |
| 146 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 11 | $225.00 | $252.35 | $245.00 | $257.25 | $245.00 | $245.00 | $245.00 |
| 147 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 77,335 | $1.12 | $1.13 | $1.10 | $1.20 | $1.10 | $1.65 | $1.70 |
| 148 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,520 | $4.75 | $2.47 | $2.40 | $2.55 | $2.40 | $1.35 | $1.35 |
| 149 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 11,167 | $2.13 | $1.39 | $1.35 | $1.45 | $1.35 | $1.35 | $1.35 |
| 150 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,135 | $5.00 | $4.64 | $4.50 | $4.75 | $4.50 | $4.75 | $4.75 |
| 151 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,403 | $10.00 | $10.30 | $10.00 | $10.50 | $10.00 | $8.00 | $8.00 |
| 152 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 92 | $190.00 | $195.70 | $190.00 | $199.50 | $190.00 | $165.00 | $165.00 |
| 153 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 7 | $240.00 | $293.55 | $285.00 | $299.25 | $285.00 | $215.00 | $215.00 |
| 154 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 4 | $208.00 | $386.25 | $375.00 | $393.75 | $375.00 | $280.00 | $285.00 |
| 155 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 93 | $215.00 | $257.50 | $250.00 | $262.50 | $250.00 | $205.00 | $205.00 |
| 156 | Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087) | EACH | 12 | $70.00 | $87.55 | $85.00 | $89.25 | $85.00 | $82.25 | $85.00 |
| 157 | Reflectorized pavement marking type I (W)(bike arrow)(100MIL) (666-7093) | EACH | 16 | $220.00 | $169.95 | $165.00 | $173.25 | $165.00 | $192.00 | $200.00 |
| 158 | Reflectorized pavement marking type I(W)(bike syml)(100MIL) (666-7099) | EACH | 16 | $420.00 | $200.85 | $195.00 | $204.75 | $195.00 | $192.00 | $200.00 |
| 159 | Pavement sler 6" (666-7347) | LF | 109,027 | $0.56 | $0.31 | $0.30 | $0.35 | $0.30 | $0.22 | $0.25 |
| 160 | Pavement sler 8" (666-7348) | LF | 11,167 | $0.68 | $0.46 | $0.45 | $0.50 | $0.45 | $0.40 | $0.40 |
| 161 | Pavement sler 12" (666-7350) | LF | 1,135 | $1.10 | $1.24 | $1.20 | $1.30 | $1.20 | $1.65 | $1.70 |
| 162 | Pavement sler 24" (666-7352) | LF | 2,403 | $2.61 | $2.27 | $2.20 | $2.35 | $2.20 | $2.75 | $2.75 |
| 163 | Pavement sler (arrow) (666-7353) | EACH | 92 | $53.00 | $53.56 | $52.00 | $54.60 | $52.00 | $82.25 | $83.00 |
| 164 | Pavement sler (word) (666-7354) | EACH | 93 | $52.00 | $66.95 | $65.00 | $68.25 | $65.00 | $100.00 | $100.00 |
| 165 | Pavement sler (double arrow) (666-7356) | EACH | 7 | $75.00 | $103.00 | $100.00 | $105.00 | $100.00 | $135.00 | $135.00 |
| 166 | Pavement sler (uturn arrow) (666-7358) | EACH | 4 | $75.00 | $103.00 | $100.00 | $105.00 | $100.00 | $140.00 | $140.00 |
| 167 | Pavement sler (yld tri) (666-7365) | EACH | 12 | $20.00 | $30.90 | $30.00 | $31.50 | $30.00 | $55.00 | $55.00 |
| 168 | Pavement sler (bike arrow) (666-7368) | EACH | 16 | $58.00 | $56.65 | $55.00 | $57.75 | $55.00 | $110.00 | $110.00 |
| 169 | Pavement sler (bike symbol) (666-7369) | EACH | 16 | $90.00 | $61.80 | $60.00 | $63.00 | $60.00 | $110.00 | $110.00 |
| 170 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 19,227 | $2.00 | $1.03 | $1.00 | $1.05 | $1.00 | $1.00 | $1.00 |
| 171 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 48,680 | $1.35 | $0.88 | $0.85 | $0.90 | $0.85 | $0.90 | $1.00 |
| 172 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 45,633 | $1.80 | $0.88 | $0.85 | $0.90 | $0.85 | $0.90 | $1.00 |
| 173 | Reflectorized pavement marker type I-C (672-7002) | EACH | 564 | $7.50 | $6.95 | $6.75 | $7.10 | $6.75 | $5.50 | $6.00 |
| 174 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 247 | $8.75 | $6.95 | $6.75 | $7.10 | $6.75 | $5.50 | $6.00 |
| 175 | Eliminating existing PM & markers (4") (677-7001) | LF | 65,574 | $0.86 | $0.57 | $0.55 | $0.60 | $0.55 | $0.60 | $0.60 |
| 176 | Eliminating existing PM & markers (8") (677-7004) | LF | 12,972 | $1.75 | $1.13 | $1.10 | $1.20 | $1.10 | $0.85 | $0.85 |
| 177 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,413 | $2.75 | $2.06 | $2.00 | $2.10 | $2.00 | $2.20 | $2.25 |
| 178 | Eliminating existing PM & markers (24") (677-7008) | LF | 561 | $7.00 | $4.12 | $4.00 | $4.20 | $4.00 | $3.85 | $4.00 |
| 179 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 35 | $98.00 | $82.40 | $80.00 | $84.00 | $80.00 | $165.00 | $165.00 |
| 180 | Eliminating existing PM & markers (word) (677-7015) | EACH | 22 | $100.00 | $103.00 | $100.00 | $105.00 | $100.00 | $165.00 | $165.00 |
| 181 | Eliminating existing PM & markers (med nose) (677-7021) | EACH | 1 | $147.00 | $144.20 | $140.00 | $147.00 | $140.00 | $275.00 | $275.00 |
| 182 | Pavement surface preparation for marking (6") (678-7002) | LF | 109,027 | $0.45 | $0.21 | $0.20 | $0.25 | $0.20 | $0.12 | $0.11 |
| 183 | Pavement surface preparation for marking (8") (678-7004) | LF | 11,167 | $0.25 | $0.41 | $0.40 | $0.45 | $0.40 | $0.22 | $0.22 |
| 184 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,135 | $0.75 | $1.03 | $1.00 | $1.05 | $1.00 | $0.55 | $0.60 |
| 185 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,403 | $1.00 | $2.06 | $2.00 | $2.10 | $2.00 | $1.10 | $1.10 |
| 186 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 92 | $40.00 | $46.35 | $45.00 | $47.25 | $45.00 | $55.00 | $55.00 |
| 187 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 7 | $30.00 | $87.55 | $85.00 | $89.25 | $85.00 | $55.00 | $55.00 |
| 188 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 4 | $30.00 | $77.25 | $75.00 | $78.75 | $75.00 | $55.00 | $55.00 |
| 189 | Pavement surface preparation for marking (word) (678-7016) | EACH | 93 | $55.00 | $56.65 | $55.00 | $57.75 | $55.00 | $55.00 | $55.00 |
| 190 | Pavement surface preparation for marking (18")(yld tri) (678-7022) | EACH | 12 | $11.75 | $25.75 | $25.00 | $26.25 | $25.00 | $55.00 | $55.00 |
| 191 | Pavement surface preparation for marking (bike arrow) (678-7026) | EACH | 16 | $14.75 | $36.05 | $35.00 | $36.75 | $35.00 | $55.00 | $55.00 |
| 192 | Pavement surface preparation for marking (bike symbol) (678-7028) | EACH | 16 | $34.00 | $41.20 | $40.00 | $42.00 | $40.00 | $55.00 | $55.00 |
| 193 | Install highway traffic signal (isolated) (680-7002) | EACH | 6 | $50,000 | $61,000 | $57,535 | $56,574 | $53,900 | $68,500 | $64,000 |
| 194 | Removing traffic signals (680-7004) | EACH | 5 | $12,000 | $25,000 | $8,592.80 | $11,666 | $11,110 | $10,250 | $9,500.00 |
| 195 | Temporary traffic signals (681-7001) | EACH | 6 | $110,000 | $150,000 | $119,042 | $98,312 | $93,630 | $141,500 | $135,000 |
| 196 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 53 | $351.00 | $506.70 | $364.10 | $471.45 | $449.00 | $435.00 | $400.00 |
| 197 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 20 | $353.00 | $513.47 | $364.10 | $477.75 | $455.00 | $435.00 | $400.00 |
| 198 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 53 | $351.00 | $506.70 | $364.10 | $471.45 | $449.00 | $435.00 | $400.00 |
| 199 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 35 | $353.00 | $513.47 | $364.10 | $477.75 | $455.00 | $435.00 | $400.00 |
| 200 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 53 | $351.00 | $506.70 | $364.10 | $471.45 | $449.00 | $435.00 | $400.00 |
| 201 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 36 | $353.00 | $513.47 | $364.10 | $477.75 | $455.00 | $435.00 | $400.00 |
| 202 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 50 | $800.00 | $1,007.76 | $664.70 | $937.65 | $893.00 | $790.00 | $750.00 |
| 203 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 51 | $281.00 | $285.51 | $221.50 | $265.65 | $253.00 | $265.00 | $250.00 |
| 204 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 3 | $301.00 | $294.54 | $233.80 | $274.05 | $261.00 | $280.00 | $260.00 |
| 205 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 17 | $285.00 | $302.44 | $279.90 | $281.40 | $268.00 | $335.00 | $310.00 |
| 206 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 7,150 | $2.50 | $3.62 | $2.70 | $3.40 | $3.20 | $3.25 | $3.00 |
| 207 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 5,415 | $3.15 | $4.25 | $3.10 | $4.00 | $3.80 | $3.70 | $4.00 |
| 208 | Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036) | LF | 620 | $4.05 | $4.47 | $3.70 | $4.20 | $3.95 | $4.40 | $4.00 |
| 209 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 3,210 | $5.95 | $4.94 | $5.60 | $4.60 | $4.40 | $6.70 | $6.50 |
| 210 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 8,555 | $2.50 | $5.26 | $2.10 | $4.90 | $4.65 | $2.50 | $2.50 |
| 211 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 1 | $13,225 | $14,513 | $14,158 | $13,503 | $12,860 | $16,850 | $16,000 |
| 212 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 2 | $15,000 | $14,868 | $14,405 | $13,834 | $13,175 | $17,150 | $16,000 |
| 213 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 1 | $18,000 | $15,765 | $14,897 | $14,669 | $13,970 | $17,750 | $16,500 |
| 214 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 1 | $25,000 | $17,937 | $16,745 | $16,689 | $15,895 | $19,950 | $18,500 |
| 215 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 3 | $15,900 | $18,666 | $17,630 | $17,367 | $16,540 | $21,000 | $20,000 |
| 216 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 5 | $37,697 | $40,468 | $33,250 | $37,653 | $35,860 | $39,550 | $37,000 |
| 217 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 4 | $54,046 | $41,103 | $34,112 | $38,243 | $36,425 | $40,550 | $38,000 |
| 218 | Ins traffic signal PL AM(S)1 arm(65')lum (686-7067) | EACH | 3 | $48,000 | $42,748 | $34,728 | $39,774 | $37,880 | $41,300 | $39,000 |
| 219 | Pedestrian pole assembly (687-7001) | EACH | 39 | $3,349.00 | $4,378.63 | $3,633.30 | $4,074.00 | $3,880.00 | $4,320.00 | $4,000.00 |
| 220 | Pedestrian detect push button (APS) (688-7001) | EACH | 44 | $1,200.00 | $987.45 | $1,174.70 | $918.75 | $875.00 | $1,400.00 | $1,300.00 |
| 221 | Pedestrian detect push button (standard) (688-7002) | EACH | 6 | $350.00 | $884.75 | $504.20 | $823.20 | $784.00 | $600.00 | $550.00 |
| 222 | Pedestrian detector controller unit (688-7003) | EACH | 7 | $4,892.00 | $5,134.73 | $4,408.50 | $4,777.50 | $4,550.00 | $5,250.00 | $5,000.00 |
| 223 | Full - width mowing (730-7019) | CYC | 9 | $4,215.00 | $5,000.00 | $4,000.00 | $18,410 | $4,360.00 | $4,350.00 | $8,500.00 |
| 224 | Bbu system (external battery cabinet) (6007-7001) | EACH | 6 | $9,526.00 | $12,244 | $9,408.40 | $11,393 | $10,850 | $11,200 | $10,500 |
| 225 | RVDS (presence detection only) (6008-7001) | EACH | 20 | $9,021.00 | $11,229 | $11,015 | $10,448 | $9,950.00 | $13,100 | $12,200 |
| 226 | RVDS (advance detection only) (6008-7002) | EACH | 11 | $10,100 | $14,140 | $11,993 | $13,157 | $12,530 | $14,300 | $13,200 |
| 227 | Ground box (prepare) (6013-7006) | EACH | 8 | $240.00 | $620.68 | $319.40 | $577.50 | $550.00 | $380.00 | $350.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.