TxDOT contract A00061613 bid tabulation

Intersection Improvement, IH 35E (AT BEAR CREEK ROAD to .). Let by Texas DOT on March 5, 2025, Dallas, Dallas District. 4 bids received; low bid $16,449,139 by Ibctx, LLC, -3.5% against the engineer's estimate of $17,046,540.

Owner
Texas DOT
Letting
05 MAR 2025
Pay items
238
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ibctx, LLC$16,449,139Low-4.0%
2Ed Bell Construction Company$17,565,313+7.0%+3.0%
3Flatiron Dragados Constructors, Inc.$19,050,976+16%+12%
4Grey Sky Construction LLC$20,360,457+24%+19%
TxDOT contract A00061613: bids by rank

Engineer's estimate: $17,046,540.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ibctx, LLC2. Ed Bell Construction Company3. Flatiron Dragados Constructors, Inc.4. Grey Sky Construction LLC
1Preparing row (100-7002)STA12.25$130,000$25,000$34,000$57,500$141,666
2Removing concrete (riprap) (104-7006)SY218$26.00$22.00$23.15$65.00$50.00
3Removing concrete (driveways) (104-7011)SY592.29$14.00$16.00$36.34$30.00$50.00
4Removing concrete (curb) (104-7016)LF629$15.00$16.00$13.84$10.00$50.00
5Remove (8"-14") TRT/untrt base & asphalt pavement (105-7118)CY10,257.02$14.00$20.00$1.00$5.00$20.00
6Excavation (roadway) (110-7001)CY7,600.13$30.00$40.00$5.05$20.00$20.00
7Embankment (final)(DC)(type C1) (132-7008)CY14,869.90$25.00$40.00$29.15$20.00$40.00
8Embankment (final)(DC)(type C2) (132-7010)CY1,650.58$42.00$44.00$96.44$75.00$40.00
9Compost manuf topsoil (4") (161-7002)SY19,402$4.90$4.00$1.26$4.00$8.00
10Block sodding (162-7002)SY19,451$4.00$10.00$3.99$4.55$8.00
11Drill seed (temporary_warm_cool) (164-7015)SY1,983$0.22$2.00$1.03$0.75$1.00
12Vegetative watering (168-7001)TGL3,181$16.00$1.00$2.03$10.00$20.00
13FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY26$100.00$600.00$283.52$387.14$500.00
14Lime (quicklime (slurry)) (260-7003)TON509$350.00$440.00$366.67$502.40$400.00
15Lime TRT (existing material)(6") (260-7006)SY1,005$20.00$15.00$13.33$20.00$10.00
16Lime TRT (existing material)(10") (260-7008)SY16,839$20.00$5.00$16.83$25.00$12.00
17Tack coat (342-7015)GAL60$4.00$3.00$2.50$6.00$10.00
18SP mixes SP-B PG64-22 (344-7001)TON4,313$146.00$170.00$170.00$201.00$150.00
19SP mixes SP-C sac-B PG64-22 (344-7011)TON111$175.00$181.00$182.00$310.00$250.00
20Concrete pavement (CRCP) (10") (360-7004)SY15,512$120.00$130.00$108.75$155.00$100.00
21Concrete pavement (CRCP)(hes) (10") (360-7049)SY1,527$175.00$140.00$188.25$235.00$150.00
22Trench excavation protection (402-7001)LF2,728$7.80$25.00$32.59$2.50$10.00
23Temporary special shoring (403-7001)SF10,521.80$50.00$57.00$71.16$80.00$55.00
24Drilled shaft (36 in) (416-7006)LF596$255.00$420.00$357.28$380.92$400.00
25Drilled shaft (traffic signal pole) (30 in) (416-7043)LF11$650.00$520.00$255.00$495.00$550.00
26Drilled shaft (traffic signal pole) (36 in) (416-7044)LF39$700.00$660.00$330.00$628.00$600.00
27Drilled shaft (traffic signal pole) (48 in) (416-7046)LF44$800.00$776.00$550.00$739.00$750.00
28Class C concrete (abutment)(HPC) (420-7013)CY38.70$1,550.00$2,800.00$3,068.26$2,800.00$2,000.00
29Class C concrete (cap)(HPC) (420-7023)CY20.50$1,825.00$2,800.00$2,836.58$3,000.00$2,000.00
30Class C concrete (column)(HPC) (420-7039)CY19.80$1,590.00$2,800.00$2,355.08$2,400.00$2,000.00
31Reinforced concrete slab (HPC) (422-7002)SF5,797$35.00$40.00$42.16$40.00$20.00
32Bridge sidewalk (422-7012)SF904$17.00$32.00$29.41$15.00$50.00
33Approach slab (422-7013)CY82$842.00$1,200.00$1,430.80$1,000.00$2,000.00
34Retaining wall (MSE) (423-7001)SF9,014.40$87.00$110.00$157.10$125.00$150.00
35Retaining wall (spread footing) (423-7015)SF975$85.00$140.00$182.10$150.00$85.00
36Prestressed concrete girder (TX28) (425-7001)LF908.22$200.00$330.00$464.35$250.00$210.00
37Riprap (concrete)(4 in) (432-7001)CY94.40$726.00$1,100.00$1,025.09$935.42$550.00
38Riprap (concrete)(CL B)(5 in) (432-7008)CY2$700.00$2,000.00$2,010.82$800.19$650.00
39Riprap (stone protection)(24 in) (432-7045)CY1,286$235.00$185.00$229.43$150.00$200.00
40STR steel (miscellaneous non-bridge) (442-7007)LB178$12.00$55.00$24.31$25.00$50.00
41Rail (type T221) (450-7004)LF160.40$70.00$190.00$123.96$125.00$185.00
42Rail (type T221)(HPC) (450-7005)LF120$78.00$195.00$172.77$150.00$250.00
43Rail (type C221) (450-7032)LF707.20$125.00$225.00$247.98$275.00$200.00
44Rail (type C221)(HPC) (450-7033)LF120.90$110.00$230.00$255.22$150.00$250.00
45Rail (type PR11) (450-7044)LF121$200.00$200.00$188.66$150.00$200.00
46Rail (handrail)(type F) (450-7063)LF134$161.00$250.00$290.39$50.00$185.00
47Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF102$176.00$320.00$291.57$434.68$100.00
48Concrete box culvert (5 FT X 3 FT) (462-7007)LF205$475.00$575.00$968.75$1,500.00$1,000.00
49Concrete box culvert (10 FT X 10 FT) (462-7038)LF1,370$1,800.00$975.00$1,080.66$1,550.00$2,200.00
50RC pipe (CL III)(18 in) (464-7003)LF265$99.50$75.00$187.83$213.94$85.00
51RC pipe (CL III)(24 in) (464-7005)LF1,174$142.00$110.00$215.72$250.00$125.00
52RC pipe (CL III)(30 in) (464-7007)LF961$150.00$145.00$268.64$260.00$150.00
53RC pipe (CL III)(36 in) (464-7009)LF497$190.00$200.00$289.53$270.00$200.00
54Manh (complete)(PRM)(48IN) (465-7002)EACH1$5,890.00$7,000.00$12,562$10,000$15,000
55Junction box(complete)(PJB)(4FTX4FT) (465-7006)EACH3$4,475.00$9,800.00$8,035.92$10,100$12,500
56Inlet (complete)(pcu)(3FT)(none) (465-7029)EACH2$6,045.00$9,500.00$15,818$12,000$12,500
57Inlet (complete)(pcu)(3FT)(left) (465-7030)EACH3$7,035.00$9,100.00$17,018$12,500$13,500
58Inlet (complete)(pcu)(3FT)(right) (465-7031)EACH2$6,800.00$11,500$17,018$12,500$13,500
59Inlet (complete)(pcu)(3FT)(both) (465-7032)EACH6$10,000$10,800$18,512$13,000$15,000
60Inlet (complete)(PMBD)(4FT) (465-7045)EACH1$6,500.00$9,200.00$17,727$10,000$12,500
61Inlet (complete)(PMBD)(5FT) (465-7046)EACH1$7,500.00$10,200$25,226$12,200$15,000
62Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH1$8,625.00$9,200.00$11,253$10,000$14,500
63Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128)EACH6$9,561.00$8,400.00$10,984$12,500$14,500
64Inlet (complete)(cob)(10 FT)(FTW) (465-7201)EACH1$12,000$7,000.00$14,134$22,000$20,000
65Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH1$24,200$30,000$39,985$34,000$55,500
66Wingwall (PW-MSE) (466-7216)EACH1$50,620$50,000$49,207$130,000$100,000
67Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307)EACH3$1,500.00$1,500.00$1,554.67$2,000.00$1,850.00
68Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH9$1,900.00$2,000.00$2,079.87$5,000.00$2,500.00
69Adjusting manholes (479-7001)EACH5$2,540.00$2,000.00$7,588.50$4,000.00$2,500.00
70Removing structure (inlet) (496-7002)EACH3$1,225.00$2,000.00$1,907.23$1,300.00$2,500.00
71Removing structure (set) (496-7004)EACH7$605.00$500.00$341.11$500.00$500.00
72Removing structure (wingwall) (496-7005)EACH3$3,500.00$6,000.00$5,085.91$2,100.00$5,000.00
73Removing structure (pipe) (496-7007)LF846$36.00$20.00$25.40$20.00$50.00
74Removing structure (bridge 0 - 99 FT length) (496-7009)EACH2$24,000$100,000$47,112$40,000$150,000
75Removing structure (ret wall) (496-7019)LF88$40.00$150.00$115.52$60.00$150.00
76Mobilization (500-7001)LS1$1,512,275$1,640,001$1,700,000$1,905,098$2,000,000
77Barricades, signs and traffic handling (502-7001)MO16$30,000$25,000$51,750$19,000$15,000
78Portable changeable message sign (503-7002)EACH4$14,000$35,000$15,000$17,000$20,000
79TMA (stationary) (505-7001)DAY61$250.00$150.00$420.00$191.67$250.00
80TMA (mobile operation) (505-7003)DAY15$390.00$300.00$1,575.00$850.00$550.00
81Rock filter dams (install) (type 2) (506-7002)LF652$36.50$48.00$69.88$35.00$50.00
82Rock filter dams (install) (type 3) (506-7003)LF158$84.00$58.00$80.63$65.00$50.00
83Rock filter dams (install) (type 4) (506-7004)LF31$73.00$79.00$91.38$80.00$50.00
84Rock filter dams (remove) (506-7011)LF842$14.00$37.00$48.38$13.00$20.00
85Construction exits (install) (type 1) (506-7020)SY1,832$26.50$20.00$32.25$35.00$55.00
86Construction exits (remove) (506-7024)SY1,832$10.00$16.00$17.74$11.00$20.00
87Temporary sediment control fence (install) (506-7039)LF4,054$3.50$5.00$2.96$3.50$4.00
88Temporary sediment control fence (remove) (506-7041)LF4,054$1.10$2.00$1.34$1.10$2.00
89Biodegradable erosion control logs (install) (12") (506-7044)LF435$5.00$10.00$5.38$5.75$18.00
90Biodegradable erosion control logs (remove) (506-7046)LF435$2.20$5.00$2.69$1.25$9.00
91Constructing detours (508-7001)SY5,455$150.00$122.00$151.00$150.00$55.00
92Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF120$77.00$150.00$163.43$140.00$120.00
93Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF1,200$40.00$60.00$30.87$81.69$100.00
94Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF200$60.00$60.00$57.91$115.90$100.00
95Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF140$7.00$25.00$24.56$27.60$30.00
96Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF60$14.00$25.00$57.30$91.40$30.00
97Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF1,200$10.00$30.00$14.81$11.78$30.00
98Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF200$12.50$30.00$34.38$19.32$30.00
99Portable concrete traffic barrier (pinning) (512-7071)EACH14$72.00$350.00$100.00$196.51$500.00
100Permanent CTB (single slope) (type 1) (42 ) (514-7001)LF714$115.00$150.00$180.39$244.26$250.00
101Concrete curb (mono) (type II) (529-7007)LF6,529$17.00$12.00$6.50$13.80$20.00
102Driveways (concrete) (530-7006)SY786$115.00$127.00$153.45$141.33$100.00
103Concrete sidewalks (4") (531-7001)SY1,257$125.00$110.00$106.16$140.00$55.00
104Curb ramps (type 2) (531-7006)EACH2$3,450.00$3,200.00$3,553.50$3,300.00$3,250.00
105Curb ramps (type 5) (531-7008)EACH3$2,750.00$3,900.00$5,257.93$3,100.00$3,250.00
106Curb ramps (type 7) (531-7010)EACH5$2,900.00$3,300.00$4,094.47$3,100.00$3,250.00
107Curb ramps (type 10) (531-7011)EACH2$2,700.00$3,300.00$4,094.47$2,800.00$3,250.00
108Concrete median (536-7002)SY27$125.00$160.00$408.47$200.00$250.00
109Right of way markers (538-7001)EACH10$306.00$600.00$600.00$500.00$500.00
110Metal W-beam guard fence (steel post) (540-7002)LF143$40.00$34.00$32.25$32.00$30.00
111Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,300.00$2,200.00$3,245.84$2,100.00$1,850.00
112Downstream anchor terminal section (540-7015)EACH1$1,540.00$1,250.00$2,100.00$1,190.00$1,850.00
113Remove metal beam guard fence (542-7001)LF496$5.00$10.00$5.25$3.00$5.00
114Remove terminal anchor section (542-7002)EACH3$135.00$500.00$630.00$215.00$500.00
115RM metal beam guard fence trans (thrie-beam) (542-7004)EACH6$247.00$500.00$630.00$250.00$500.00
116Guardrail end treatment (install) (544-7001)EACH1$3,390.00$3,100.00$3,360.00$2,900.00$3,520.00
117Guardrail end treatment (remove) (544-7003)EACH4$335.00$500.00$735.00$325.00$1,500.00
118Crash cushion attenuator (remove) (545-7004)EACH1$800.00$2,500.00$735.00$800.00$3,000.00
119Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH1$26,000$35,000$36,500$28,000$31,000
120Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH3$12,000$11,000$11,000$7,755.00$21,000
121Chain link fence (install) (6') (550-7001)LF18$40.00$67.00$105.00$63.00$20.00
122Chain link fence (remove) (550-7007)LF28$15.00$30.00$21.00$11.00$3.00
123Gate (install)(6'X10') (550-7014)EACH1$2,000.00$1,700.00$2,625.00$1,600.00$5,000.00
124Pipe underdrains (type 6) (6") (556-7006)LF1,026.60$41.50$15.00$45.00$62.83$60.00
125Relocate existing mailbox (560-7012)EACH1$550.00$1,500.00$500.00$500.00$1,500.00
126Remove RD IL asm (trans-base) (610-7009)EACH4$1,055.00$1,400.00$945.00$1,328.00$1,500.00
127Remove RD IL asm (U/P) (610-7010)EACH6$525.00$735.00$525.00$700.00$1,500.00
128In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH6$1,470.00$2,265.00$1,155.00$2,155.00$8,500.00
129In RD IL (U/P) (type 2) (150W EQ) LED (610-7016)EACH2$2,100.00$2,540.00$1,155.00$2,418.00$10,000
130Conduit (PVC) (schedule 40) (2") (618-7030)LF452$19.00$13.00$10.00$11.76$30.00
131Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF717$45.00$35.00$25.00$33.00$60.00
132Conduit (PVC) (schedule 40) (3") (618-7036)LF1,355$20.00$14.00$16.00$13.21$40.00
133Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF888$68.00$43.00$33.00$41.00$70.00
134Conduit (PVC) (schedule 40) (4") (618-7040)LF218$20.00$27.00$18.00$25.48$50.00
135Conduit (PVC) (schedule 40) (4") (bore) (618-7041)LF167$34.00$54.00$36.00$51.00$80.00
136Conduit (PVC) (schedule 80) (2") (618-7054)LF30$21.50$15.00$14.00$14.00$35.00
137Conduit (RM) (3/4") (618-7070)LF70$22.00$41.00$26.50$39.00$95.00
138Conduit (RM) (1") (618-7072)LF420$30.00$46.00$37.00$43.00$100.00
139Conduit (RM) (2") (618-7078)LF100$45.00$58.00$48.00$55.00$150.00
140Conduit (prepare) (618-7090)LF40$4.50$8.00$4.25$7.37$50.00
141ITS multi-duct CND (PVC-40) (619-7001)LF570$25.50$41.00$42.00$38.55$200.00
142ITS multi-duct CND (RMC) (619-7008)LF490$147.60$296.00$120.00$281.75$500.00
143Electrical conductor (no.8) bare (620-7007)LF1,365$1.75$2.00$2.20$1.89$4.00
144Electrical conductor (no.8) insulated (620-7008)LF5,819$2.15$3.00$2.20$1.95$4.00
145Electrical conductor (no.6) bare (620-7009)LF2,778$2.00$4.00$2.70$2.93$4.00
146Electrical conductor (no.6) insulated (620-7010)LF1,987$2.90$4.00$2.70$3.43$4.00
147ITS GND box(pcast) type 2 (366060)W/aprn (623-7012)EACH1$8,635.00$9,220.00$6,100.00$8,780.00$5,000.00
148Remove ITS ground box (623-7041)EACH1$835.00$1,630.00$2,700.00$1,550.00$500.00
149Ground box type A (122311)W/apron (624-7002)EACH6$1,170.00$2,226.00$1,400.00$2,119.95$1,500.00
150Ground box type C (162911)W/apron (624-7006)EACH6$1,825.00$2,930.00$1,500.00$2,788.99$1,500.00
151Ground box type D (162922)W/apron (624-7008)EACH6$2,450.00$2,750.00$1,600.00$2,617.18$1,500.00
152Remove ground box (624-7013)EACH4$495.00$268.00$550.00$255.00$150.00
153Zinc-coat steel wire strand (3/8") (625-7004)LF100$11.00$7.00$6.30$6.30$10.00
154Timber pole (CL 2) 40 FT (627-7003)EACH2$2,325.00$5,850.00$2,750.00$5,570.00$5,000.00
155Remove electrical services (628-7002)EACH1$450.00$735.00$1,100.00$700.00$6,500.00
156Elc SRV type D 120/240 060(NS)SS(N)PS(U) (628-7154)EACH1$10,136$17,530$8,200.00$16,696$12,500
157Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190)EACH1$11,507$15,450$9,000.00$14,715$12,500
158Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH9$785.00$750.00$750.00$705.00$1,500.00
159Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH9$950.00$980.00$900.00$930.00$1,500.00
160Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH2$1,260.00$1,250.00$1,300.00$1,190.00$1,500.00
161Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034)EACH2$1,400.00$1,360.00$1,500.00$1,295.00$1,500.00
162In bridge MNT clearance sign assembly(type N) (644-7061)EACH2$3,500.00$2,170.00$3,100.00$2,060.00$5,000.00
163In bridge MNT clearance sign assembly(type S) (644-7062)EACH2$4,500.00$2,780.00$3,150.00$2,640.00$5,000.00
164Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH2$1,340.00$720.00$800.00$670.00$1,150.00
165Remove BRDG MNT clearance sign assembly (644-7074)EACH2$360.00$120.00$900.00$110.00$250.00
166In SRSS & AM (rail)(130 MPH)(P mount) (644-7083)EACH2$5,000.00$4,450.00$7,000.00$4,220.00$15,000
167In SRSS & AM (rail)(130 MPH)(T mount) (644-7085)EACH2$7,000.00$4,600.00$7,000.00$4,370.00$15,000
168Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH6$75.00$50.00$150.00$44.00$100.00
169Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH17$26.50$25.00$80.00$22.00$100.00
170Install object marker assembly (OM-3R)(TWT)GND (658-7070)EACH4$250.00$275.00$250.00$260.00$100.00
171Work zone pavement marking removing (W)4"(DOT) (662-7062)LF517$2.00$3.00$3.23$2.30$1.00
172Work zone pavement marking removing (W)4"(solid) (662-7064)LF17,675$1.00$1.00$1.56$0.90$1.00
173Work zone pavement marking removing (W)24"(solid) (662-7077)LF542$7.80$7.00$16.93$6.85$20.00
174Work zone pavement marking removing (Y)4"(solid) (662-7097)LF9,884$1.00$1.00$1.56$0.90$1.00
175Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF118$1.70$3.00$3.23$2.10$6.00
176Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF1,639$1.20$2.00$2.42$1.05$6.00
177Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF20$4.00$5.00$10.75$4.40$6.00
178Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF721$9.00$9.00$16.13$8.00$20.00
179Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH14$55.00$72.00$129.00$69.00$150.00
180Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123)LF246$7.30$9.00$16.13$8.15$20.00
181Type I high perf PM (W)6"(broken)(100MIL) (666-7290)LF370$0.75$1.00$5.38$0.78$1.00
182Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF4,554$0.55$1.00$3.23$0.69$1.00
183Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF6,038$0.60$1.00$3.23$0.69$1.00
184Pavement sler 6" (666-7347)LF10,962$0.57$0.25$0.54$0.19$1.00
185Pavement sler 8" (666-7348)LF1,757$0.59$0.50$1.08$0.29$1.00
186Pavement sler 12" (666-7350)LF20$1.20$1.00$3.23$0.87$5.00
187Pavement sler 24" (666-7352)LF967$3.00$2.00$6.45$1.65$20.00
188Pavement sler (yld tri) (666-7365)EACH14$52.00$15.00$53.75$13.50$150.00
189Prefabricated PM type C (W)(arrow) (668-7091)EACH10$215.00$290.00$392.38$277.00$250.00
190Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH3$420.00$492.00$833.13$468.00$250.00
191Prefabricated PM type C (W)(word) (668-7103)EACH10$250.00$384.00$559.00$365.00$250.00
192Reflectorized pavement marker type I-C (672-7002)EACH93$4.20$6.00$16.13$5.00$6.00
193Reflectorized pavement marker type II-A-A (672-7004)EACH88$3.90$6.00$16.13$5.00$6.00
194Reflectorized pavement marker type II-C-R (672-7006)EACH26$5.20$6.00$16.13$5.00$6.00
195Pavement surface preparation for marking (6") (678-7002)LF10,962$0.36$0.05$0.48$0.02$1.00
196Pavement surface preparation for marking (8") (678-7004)LF1,757$0.35$0.10$0.81$0.08$3.00
197Pavement surface preparation for marking (12") (678-7006)LF20$0.90$0.50$2.96$0.27$6.00
198Pavement surface preparation for marking (24") (678-7008)LF967$1.40$0.75$5.91$0.58$20.00
199Pavement surface preparation for marking (36")(yld tri) (678-7023)EACH14$15.50$7.00$43.00$6.65$150.00
200Install highway traffic signal (system) (680-7003)EACH1$35,950$51,200$60,000$48,760$65,000
201Removing traffic signals (680-7004)EACH1$8,000.00$10,230$6,000.00$9,740.00$15,000
202Temporary traffic signals (681-7001)EACH1$90,000$91,770$125,000$87,400$95,000
203Vehicle signal section (12")LED(green) (682-7001)EACH10$345.00$480.00$450.00$455.00$325.00
204Vehicle signal section (12")LED(green arrow) (682-7002)EACH7$344.00$492.00$450.00$468.00$325.00
205Vehicle signal section (12")LED(yel) (682-7003)EACH14$344.00$480.00$450.00$455.00$325.00
206Vehicle signal section (12")LED(yel arrow) (682-7004)EACH6$345.00$492.00$450.00$468.00$325.00
207Vehicle signal section (12")LED(red) (682-7005)EACH14$344.00$480.00$450.00$455.00$325.00
208Vehicle signal section (12")LED(red arrow) (682-7006)EACH6$347.00$492.00$450.00$468.00$325.00
209Pedestrian signal section (LED)(countdown) (682-7018)EACH12$925.00$925.00$800.00$881.00$6,500.00
210Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH14$295.00$270.00$350.00$256.00$200.00
211Backplate W/ref border(5 sec)(vent)aluminum (682-7044)EACH3$315.00$285.00$360.00$267.00$250.00
212Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF4,853$3.00$4.00$3.20$3.28$1.00
213Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF203$4.00$4.00$3.20$3.55$1.00
214Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042)LF1,782$5.00$5.00$8.50$3.98$1.00
215Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079)LF4,392$6.00$4.00$2.15$2.95$1.00
216Ins traffic signal PL AM(S)1 arm(32')lum (686-7035)EACH1$14,500$15,270$16,000$14,539$32,500
217Ins traffic signal PL AM(S)1 arm(36')lum (686-7039)EACH1$16,500$17,710$18,000$16,865$35,000
218Ins traffic signal PL AM(S)1 arm(40')lum (686-7043)EACH1$15,515$18,555$20,000$17,670$40,000
219Ins traffic signal PL AM(S)1 arm(44')lum (686-7047)EACH1$20,015$22,650$22,000$21,540$45,000
220Ins traffic signal PL AM(S)1 arm(55')lum (686-7059)EACH2$32,275$41,510$45,000$39,530$50,000
221Pedestrian pole assembly (687-7001)EACH11$3,920.00$4,100.00$2,500.00$3,895.00$6,500.00
222Pedestrian detect push button (APS) (688-7001)EACH12$1,260.00$930.00$1,200.00$882.00$1,850.00
223Pedestrian detector controller unit (688-7003)EACH2$4,150.00$4,200.00$4,000.00$4,000.00$6,500.00
224Removal of conduit (690-7001)LF360$3.80$5.00$1.10$4.58$20.00
225Removal of timber poles (690-7021)EACH2$560.00$1,725.00$1,100.00$1,540.00$1,500.00
226Install down guy W/guard (690-7078)EACH2$1,040.00$525.00$700.00$500.00$1,500.00
227Remove down guy W/guard (690-7080)EACH2$280.00$265.00$300.00$250.00$500.00
228Anti-graffiti coating (permnent-type II) (740-7005)SF6,069.80$1.70$5.00$3.00$1.50$5.00
229VIVDS temporary (6006-7006)EACH1$7,720.00$80,000$18,000$75,380$80,000
230Bbu system (external battery cabinet) (6007-7001)EACH1$43,775$11,500$10,000$10,896$8,500.00
231RVDS (presence detection only) (6008-7001)EACH6$8,070.00$10,500$9,000.00$9,895.00$20,000
232RVDS (advance detection only) (6008-7002)EACH4$8,830.00$13,200$9,000.00$12,530$20,000
233Ground box (prepare) (6013-7006)EACH3$540.00$1,210.00$500.00$1,145.78$2,500.00
234Fiber optic CBL (single-mode)(36 fiber) (6027-7002)LF2,480$2.00$15.00$4.25$13.86$25.00
235Fiber optic fusion splice (6027-7004)EACH144$275.00$261.00$60.00$248.00$500.00
236FO splice enclosure (type 1) (6027-7009)EACH4$1,920.00$3,900.00$1,000.00$3,675.00$6,500.00
237Fiber optic CBL (single-mode)(6 fiber) (6027-7011)LF130$7.50$13.00$3.50$11.65$20.00
238Remove fiber optic cable (6027-7018)LF2,190$1.40$2.00$1.60$1.18$3.00
TxDOT contract A00061613: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy