TxDOT contract A00061613 bid tabulation
Intersection Improvement, IH 35E (AT BEAR CREEK ROAD to .). Let by Texas DOT on March 5, 2025, Dallas, Dallas District. 4 bids received; low bid $16,449,139 by Ibctx, LLC, -3.5% against the engineer's estimate of $17,046,540.
- Owner
- Texas DOT
- Letting
- 05 MAR 2025
- Pay items
- 238
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ibctx, LLC | $16,449,139 | Low | -4.0% |
| 2 | Ed Bell Construction Company | $17,565,313 | +7.0% | +3.0% |
| 3 | Flatiron Dragados Constructors, Inc. | $19,050,976 | +16% | +12% |
| 4 | Grey Sky Construction LLC | $20,360,457 | +24% | +19% |
Engineer's estimate: $17,046,540.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ibctx, LLC | 2. Ed Bell Construction Company | 3. Flatiron Dragados Constructors, Inc. | 4. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 12.25 | $130,000 | $25,000 | $34,000 | $57,500 | $141,666 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 218 | $26.00 | $22.00 | $23.15 | $65.00 | $50.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 592.29 | $14.00 | $16.00 | $36.34 | $30.00 | $50.00 |
| 4 | Removing concrete (curb) (104-7016) | LF | 629 | $15.00 | $16.00 | $13.84 | $10.00 | $50.00 |
| 5 | Remove (8"-14") TRT/untrt base & asphalt pavement (105-7118) | CY | 10,257.02 | $14.00 | $20.00 | $1.00 | $5.00 | $20.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 7,600.13 | $30.00 | $40.00 | $5.05 | $20.00 | $20.00 |
| 7 | Embankment (final)(DC)(type C1) (132-7008) | CY | 14,869.90 | $25.00 | $40.00 | $29.15 | $20.00 | $40.00 |
| 8 | Embankment (final)(DC)(type C2) (132-7010) | CY | 1,650.58 | $42.00 | $44.00 | $96.44 | $75.00 | $40.00 |
| 9 | Compost manuf topsoil (4") (161-7002) | SY | 19,402 | $4.90 | $4.00 | $1.26 | $4.00 | $8.00 |
| 10 | Block sodding (162-7002) | SY | 19,451 | $4.00 | $10.00 | $3.99 | $4.55 | $8.00 |
| 11 | Drill seed (temporary_warm_cool) (164-7015) | SY | 1,983 | $0.22 | $2.00 | $1.03 | $0.75 | $1.00 |
| 12 | Vegetative watering (168-7001) | TGL | 3,181 | $16.00 | $1.00 | $2.03 | $10.00 | $20.00 |
| 13 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 26 | $100.00 | $600.00 | $283.52 | $387.14 | $500.00 |
| 14 | Lime (quicklime (slurry)) (260-7003) | TON | 509 | $350.00 | $440.00 | $366.67 | $502.40 | $400.00 |
| 15 | Lime TRT (existing material)(6") (260-7006) | SY | 1,005 | $20.00 | $15.00 | $13.33 | $20.00 | $10.00 |
| 16 | Lime TRT (existing material)(10") (260-7008) | SY | 16,839 | $20.00 | $5.00 | $16.83 | $25.00 | $12.00 |
| 17 | Tack coat (342-7015) | GAL | 60 | $4.00 | $3.00 | $2.50 | $6.00 | $10.00 |
| 18 | SP mixes SP-B PG64-22 (344-7001) | TON | 4,313 | $146.00 | $170.00 | $170.00 | $201.00 | $150.00 |
| 19 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 111 | $175.00 | $181.00 | $182.00 | $310.00 | $250.00 |
| 20 | Concrete pavement (CRCP) (10") (360-7004) | SY | 15,512 | $120.00 | $130.00 | $108.75 | $155.00 | $100.00 |
| 21 | Concrete pavement (CRCP)(hes) (10") (360-7049) | SY | 1,527 | $175.00 | $140.00 | $188.25 | $235.00 | $150.00 |
| 22 | Trench excavation protection (402-7001) | LF | 2,728 | $7.80 | $25.00 | $32.59 | $2.50 | $10.00 |
| 23 | Temporary special shoring (403-7001) | SF | 10,521.80 | $50.00 | $57.00 | $71.16 | $80.00 | $55.00 |
| 24 | Drilled shaft (36 in) (416-7006) | LF | 596 | $255.00 | $420.00 | $357.28 | $380.92 | $400.00 |
| 25 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 11 | $650.00 | $520.00 | $255.00 | $495.00 | $550.00 |
| 26 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 39 | $700.00 | $660.00 | $330.00 | $628.00 | $600.00 |
| 27 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 44 | $800.00 | $776.00 | $550.00 | $739.00 | $750.00 |
| 28 | Class C concrete (abutment)(HPC) (420-7013) | CY | 38.70 | $1,550.00 | $2,800.00 | $3,068.26 | $2,800.00 | $2,000.00 |
| 29 | Class C concrete (cap)(HPC) (420-7023) | CY | 20.50 | $1,825.00 | $2,800.00 | $2,836.58 | $3,000.00 | $2,000.00 |
| 30 | Class C concrete (column)(HPC) (420-7039) | CY | 19.80 | $1,590.00 | $2,800.00 | $2,355.08 | $2,400.00 | $2,000.00 |
| 31 | Reinforced concrete slab (HPC) (422-7002) | SF | 5,797 | $35.00 | $40.00 | $42.16 | $40.00 | $20.00 |
| 32 | Bridge sidewalk (422-7012) | SF | 904 | $17.00 | $32.00 | $29.41 | $15.00 | $50.00 |
| 33 | Approach slab (422-7013) | CY | 82 | $842.00 | $1,200.00 | $1,430.80 | $1,000.00 | $2,000.00 |
| 34 | Retaining wall (MSE) (423-7001) | SF | 9,014.40 | $87.00 | $110.00 | $157.10 | $125.00 | $150.00 |
| 35 | Retaining wall (spread footing) (423-7015) | SF | 975 | $85.00 | $140.00 | $182.10 | $150.00 | $85.00 |
| 36 | Prestressed concrete girder (TX28) (425-7001) | LF | 908.22 | $200.00 | $330.00 | $464.35 | $250.00 | $210.00 |
| 37 | Riprap (concrete)(4 in) (432-7001) | CY | 94.40 | $726.00 | $1,100.00 | $1,025.09 | $935.42 | $550.00 |
| 38 | Riprap (concrete)(CL B)(5 in) (432-7008) | CY | 2 | $700.00 | $2,000.00 | $2,010.82 | $800.19 | $650.00 |
| 39 | Riprap (stone protection)(24 in) (432-7045) | CY | 1,286 | $235.00 | $185.00 | $229.43 | $150.00 | $200.00 |
| 40 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 178 | $12.00 | $55.00 | $24.31 | $25.00 | $50.00 |
| 41 | Rail (type T221) (450-7004) | LF | 160.40 | $70.00 | $190.00 | $123.96 | $125.00 | $185.00 |
| 42 | Rail (type T221)(HPC) (450-7005) | LF | 120 | $78.00 | $195.00 | $172.77 | $150.00 | $250.00 |
| 43 | Rail (type C221) (450-7032) | LF | 707.20 | $125.00 | $225.00 | $247.98 | $275.00 | $200.00 |
| 44 | Rail (type C221)(HPC) (450-7033) | LF | 120.90 | $110.00 | $230.00 | $255.22 | $150.00 | $250.00 |
| 45 | Rail (type PR11) (450-7044) | LF | 121 | $200.00 | $200.00 | $188.66 | $150.00 | $200.00 |
| 46 | Rail (handrail)(type F) (450-7063) | LF | 134 | $161.00 | $250.00 | $290.39 | $50.00 | $185.00 |
| 47 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 102 | $176.00 | $320.00 | $291.57 | $434.68 | $100.00 |
| 48 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 205 | $475.00 | $575.00 | $968.75 | $1,500.00 | $1,000.00 |
| 49 | Concrete box culvert (10 FT X 10 FT) (462-7038) | LF | 1,370 | $1,800.00 | $975.00 | $1,080.66 | $1,550.00 | $2,200.00 |
| 50 | RC pipe (CL III)(18 in) (464-7003) | LF | 265 | $99.50 | $75.00 | $187.83 | $213.94 | $85.00 |
| 51 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,174 | $142.00 | $110.00 | $215.72 | $250.00 | $125.00 |
| 52 | RC pipe (CL III)(30 in) (464-7007) | LF | 961 | $150.00 | $145.00 | $268.64 | $260.00 | $150.00 |
| 53 | RC pipe (CL III)(36 in) (464-7009) | LF | 497 | $190.00 | $200.00 | $289.53 | $270.00 | $200.00 |
| 54 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 1 | $5,890.00 | $7,000.00 | $12,562 | $10,000 | $15,000 |
| 55 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 3 | $4,475.00 | $9,800.00 | $8,035.92 | $10,100 | $12,500 |
| 56 | Inlet (complete)(pcu)(3FT)(none) (465-7029) | EACH | 2 | $6,045.00 | $9,500.00 | $15,818 | $12,000 | $12,500 |
| 57 | Inlet (complete)(pcu)(3FT)(left) (465-7030) | EACH | 3 | $7,035.00 | $9,100.00 | $17,018 | $12,500 | $13,500 |
| 58 | Inlet (complete)(pcu)(3FT)(right) (465-7031) | EACH | 2 | $6,800.00 | $11,500 | $17,018 | $12,500 | $13,500 |
| 59 | Inlet (complete)(pcu)(3FT)(both) (465-7032) | EACH | 6 | $10,000 | $10,800 | $18,512 | $13,000 | $15,000 |
| 60 | Inlet (complete)(PMBD)(4FT) (465-7045) | EACH | 1 | $6,500.00 | $9,200.00 | $17,727 | $10,000 | $12,500 |
| 61 | Inlet (complete)(PMBD)(5FT) (465-7046) | EACH | 1 | $7,500.00 | $10,200 | $25,226 | $12,200 | $15,000 |
| 62 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 1 | $8,625.00 | $9,200.00 | $11,253 | $10,000 | $14,500 |
| 63 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 6 | $9,561.00 | $8,400.00 | $10,984 | $12,500 | $14,500 |
| 64 | Inlet (complete)(cob)(10 FT)(FTW) (465-7201) | EACH | 1 | $12,000 | $7,000.00 | $14,134 | $22,000 | $20,000 |
| 65 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $24,200 | $30,000 | $39,985 | $34,000 | $55,500 |
| 66 | Wingwall (PW-MSE) (466-7216) | EACH | 1 | $50,620 | $50,000 | $49,207 | $130,000 | $100,000 |
| 67 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 3 | $1,500.00 | $1,500.00 | $1,554.67 | $2,000.00 | $1,850.00 |
| 68 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 9 | $1,900.00 | $2,000.00 | $2,079.87 | $5,000.00 | $2,500.00 |
| 69 | Adjusting manholes (479-7001) | EACH | 5 | $2,540.00 | $2,000.00 | $7,588.50 | $4,000.00 | $2,500.00 |
| 70 | Removing structure (inlet) (496-7002) | EACH | 3 | $1,225.00 | $2,000.00 | $1,907.23 | $1,300.00 | $2,500.00 |
| 71 | Removing structure (set) (496-7004) | EACH | 7 | $605.00 | $500.00 | $341.11 | $500.00 | $500.00 |
| 72 | Removing structure (wingwall) (496-7005) | EACH | 3 | $3,500.00 | $6,000.00 | $5,085.91 | $2,100.00 | $5,000.00 |
| 73 | Removing structure (pipe) (496-7007) | LF | 846 | $36.00 | $20.00 | $25.40 | $20.00 | $50.00 |
| 74 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $24,000 | $100,000 | $47,112 | $40,000 | $150,000 |
| 75 | Removing structure (ret wall) (496-7019) | LF | 88 | $40.00 | $150.00 | $115.52 | $60.00 | $150.00 |
| 76 | Mobilization (500-7001) | LS | 1 | $1,512,275 | $1,640,001 | $1,700,000 | $1,905,098 | $2,000,000 |
| 77 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $30,000 | $25,000 | $51,750 | $19,000 | $15,000 |
| 78 | Portable changeable message sign (503-7002) | EACH | 4 | $14,000 | $35,000 | $15,000 | $17,000 | $20,000 |
| 79 | TMA (stationary) (505-7001) | DAY | 61 | $250.00 | $150.00 | $420.00 | $191.67 | $250.00 |
| 80 | TMA (mobile operation) (505-7003) | DAY | 15 | $390.00 | $300.00 | $1,575.00 | $850.00 | $550.00 |
| 81 | Rock filter dams (install) (type 2) (506-7002) | LF | 652 | $36.50 | $48.00 | $69.88 | $35.00 | $50.00 |
| 82 | Rock filter dams (install) (type 3) (506-7003) | LF | 158 | $84.00 | $58.00 | $80.63 | $65.00 | $50.00 |
| 83 | Rock filter dams (install) (type 4) (506-7004) | LF | 31 | $73.00 | $79.00 | $91.38 | $80.00 | $50.00 |
| 84 | Rock filter dams (remove) (506-7011) | LF | 842 | $14.00 | $37.00 | $48.38 | $13.00 | $20.00 |
| 85 | Construction exits (install) (type 1) (506-7020) | SY | 1,832 | $26.50 | $20.00 | $32.25 | $35.00 | $55.00 |
| 86 | Construction exits (remove) (506-7024) | SY | 1,832 | $10.00 | $16.00 | $17.74 | $11.00 | $20.00 |
| 87 | Temporary sediment control fence (install) (506-7039) | LF | 4,054 | $3.50 | $5.00 | $2.96 | $3.50 | $4.00 |
| 88 | Temporary sediment control fence (remove) (506-7041) | LF | 4,054 | $1.10 | $2.00 | $1.34 | $1.10 | $2.00 |
| 89 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 435 | $5.00 | $10.00 | $5.38 | $5.75 | $18.00 |
| 90 | Biodegradable erosion control logs (remove) (506-7046) | LF | 435 | $2.20 | $5.00 | $2.69 | $1.25 | $9.00 |
| 91 | Constructing detours (508-7001) | SY | 5,455 | $150.00 | $122.00 | $151.00 | $150.00 | $55.00 |
| 92 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 120 | $77.00 | $150.00 | $163.43 | $140.00 | $120.00 |
| 93 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 1,200 | $40.00 | $60.00 | $30.87 | $81.69 | $100.00 |
| 94 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 200 | $60.00 | $60.00 | $57.91 | $115.90 | $100.00 |
| 95 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 140 | $7.00 | $25.00 | $24.56 | $27.60 | $30.00 |
| 96 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 60 | $14.00 | $25.00 | $57.30 | $91.40 | $30.00 |
| 97 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 1,200 | $10.00 | $30.00 | $14.81 | $11.78 | $30.00 |
| 98 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 200 | $12.50 | $30.00 | $34.38 | $19.32 | $30.00 |
| 99 | Portable concrete traffic barrier (pinning) (512-7071) | EACH | 14 | $72.00 | $350.00 | $100.00 | $196.51 | $500.00 |
| 100 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 714 | $115.00 | $150.00 | $180.39 | $244.26 | $250.00 |
| 101 | Concrete curb (mono) (type II) (529-7007) | LF | 6,529 | $17.00 | $12.00 | $6.50 | $13.80 | $20.00 |
| 102 | Driveways (concrete) (530-7006) | SY | 786 | $115.00 | $127.00 | $153.45 | $141.33 | $100.00 |
| 103 | Concrete sidewalks (4") (531-7001) | SY | 1,257 | $125.00 | $110.00 | $106.16 | $140.00 | $55.00 |
| 104 | Curb ramps (type 2) (531-7006) | EACH | 2 | $3,450.00 | $3,200.00 | $3,553.50 | $3,300.00 | $3,250.00 |
| 105 | Curb ramps (type 5) (531-7008) | EACH | 3 | $2,750.00 | $3,900.00 | $5,257.93 | $3,100.00 | $3,250.00 |
| 106 | Curb ramps (type 7) (531-7010) | EACH | 5 | $2,900.00 | $3,300.00 | $4,094.47 | $3,100.00 | $3,250.00 |
| 107 | Curb ramps (type 10) (531-7011) | EACH | 2 | $2,700.00 | $3,300.00 | $4,094.47 | $2,800.00 | $3,250.00 |
| 108 | Concrete median (536-7002) | SY | 27 | $125.00 | $160.00 | $408.47 | $200.00 | $250.00 |
| 109 | Right of way markers (538-7001) | EACH | 10 | $306.00 | $600.00 | $600.00 | $500.00 | $500.00 |
| 110 | Metal W-beam guard fence (steel post) (540-7002) | LF | 143 | $40.00 | $34.00 | $32.25 | $32.00 | $30.00 |
| 111 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,300.00 | $2,200.00 | $3,245.84 | $2,100.00 | $1,850.00 |
| 112 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,540.00 | $1,250.00 | $2,100.00 | $1,190.00 | $1,850.00 |
| 113 | Remove metal beam guard fence (542-7001) | LF | 496 | $5.00 | $10.00 | $5.25 | $3.00 | $5.00 |
| 114 | Remove terminal anchor section (542-7002) | EACH | 3 | $135.00 | $500.00 | $630.00 | $215.00 | $500.00 |
| 115 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 6 | $247.00 | $500.00 | $630.00 | $250.00 | $500.00 |
| 116 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,390.00 | $3,100.00 | $3,360.00 | $2,900.00 | $3,520.00 |
| 117 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $335.00 | $500.00 | $735.00 | $325.00 | $1,500.00 |
| 118 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $800.00 | $2,500.00 | $735.00 | $800.00 | $3,000.00 |
| 119 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 1 | $26,000 | $35,000 | $36,500 | $28,000 | $31,000 |
| 120 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 3 | $12,000 | $11,000 | $11,000 | $7,755.00 | $21,000 |
| 121 | Chain link fence (install) (6') (550-7001) | LF | 18 | $40.00 | $67.00 | $105.00 | $63.00 | $20.00 |
| 122 | Chain link fence (remove) (550-7007) | LF | 28 | $15.00 | $30.00 | $21.00 | $11.00 | $3.00 |
| 123 | Gate (install)(6'X10') (550-7014) | EACH | 1 | $2,000.00 | $1,700.00 | $2,625.00 | $1,600.00 | $5,000.00 |
| 124 | Pipe underdrains (type 6) (6") (556-7006) | LF | 1,026.60 | $41.50 | $15.00 | $45.00 | $62.83 | $60.00 |
| 125 | Relocate existing mailbox (560-7012) | EACH | 1 | $550.00 | $1,500.00 | $500.00 | $500.00 | $1,500.00 |
| 126 | Remove RD IL asm (trans-base) (610-7009) | EACH | 4 | $1,055.00 | $1,400.00 | $945.00 | $1,328.00 | $1,500.00 |
| 127 | Remove RD IL asm (U/P) (610-7010) | EACH | 6 | $525.00 | $735.00 | $525.00 | $700.00 | $1,500.00 |
| 128 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 6 | $1,470.00 | $2,265.00 | $1,155.00 | $2,155.00 | $8,500.00 |
| 129 | In RD IL (U/P) (type 2) (150W EQ) LED (610-7016) | EACH | 2 | $2,100.00 | $2,540.00 | $1,155.00 | $2,418.00 | $10,000 |
| 130 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 452 | $19.00 | $13.00 | $10.00 | $11.76 | $30.00 |
| 131 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 717 | $45.00 | $35.00 | $25.00 | $33.00 | $60.00 |
| 132 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 1,355 | $20.00 | $14.00 | $16.00 | $13.21 | $40.00 |
| 133 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 888 | $68.00 | $43.00 | $33.00 | $41.00 | $70.00 |
| 134 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 218 | $20.00 | $27.00 | $18.00 | $25.48 | $50.00 |
| 135 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 167 | $34.00 | $54.00 | $36.00 | $51.00 | $80.00 |
| 136 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 30 | $21.50 | $15.00 | $14.00 | $14.00 | $35.00 |
| 137 | Conduit (RM) (3/4") (618-7070) | LF | 70 | $22.00 | $41.00 | $26.50 | $39.00 | $95.00 |
| 138 | Conduit (RM) (1") (618-7072) | LF | 420 | $30.00 | $46.00 | $37.00 | $43.00 | $100.00 |
| 139 | Conduit (RM) (2") (618-7078) | LF | 100 | $45.00 | $58.00 | $48.00 | $55.00 | $150.00 |
| 140 | Conduit (prepare) (618-7090) | LF | 40 | $4.50 | $8.00 | $4.25 | $7.37 | $50.00 |
| 141 | ITS multi-duct CND (PVC-40) (619-7001) | LF | 570 | $25.50 | $41.00 | $42.00 | $38.55 | $200.00 |
| 142 | ITS multi-duct CND (RMC) (619-7008) | LF | 490 | $147.60 | $296.00 | $120.00 | $281.75 | $500.00 |
| 143 | Electrical conductor (no.8) bare (620-7007) | LF | 1,365 | $1.75 | $2.00 | $2.20 | $1.89 | $4.00 |
| 144 | Electrical conductor (no.8) insulated (620-7008) | LF | 5,819 | $2.15 | $3.00 | $2.20 | $1.95 | $4.00 |
| 145 | Electrical conductor (no.6) bare (620-7009) | LF | 2,778 | $2.00 | $4.00 | $2.70 | $2.93 | $4.00 |
| 146 | Electrical conductor (no.6) insulated (620-7010) | LF | 1,987 | $2.90 | $4.00 | $2.70 | $3.43 | $4.00 |
| 147 | ITS GND box(pcast) type 2 (366060)W/aprn (623-7012) | EACH | 1 | $8,635.00 | $9,220.00 | $6,100.00 | $8,780.00 | $5,000.00 |
| 148 | Remove ITS ground box (623-7041) | EACH | 1 | $835.00 | $1,630.00 | $2,700.00 | $1,550.00 | $500.00 |
| 149 | Ground box type A (122311)W/apron (624-7002) | EACH | 6 | $1,170.00 | $2,226.00 | $1,400.00 | $2,119.95 | $1,500.00 |
| 150 | Ground box type C (162911)W/apron (624-7006) | EACH | 6 | $1,825.00 | $2,930.00 | $1,500.00 | $2,788.99 | $1,500.00 |
| 151 | Ground box type D (162922)W/apron (624-7008) | EACH | 6 | $2,450.00 | $2,750.00 | $1,600.00 | $2,617.18 | $1,500.00 |
| 152 | Remove ground box (624-7013) | EACH | 4 | $495.00 | $268.00 | $550.00 | $255.00 | $150.00 |
| 153 | Zinc-coat steel wire strand (3/8") (625-7004) | LF | 100 | $11.00 | $7.00 | $6.30 | $6.30 | $10.00 |
| 154 | Timber pole (CL 2) 40 FT (627-7003) | EACH | 2 | $2,325.00 | $5,850.00 | $2,750.00 | $5,570.00 | $5,000.00 |
| 155 | Remove electrical services (628-7002) | EACH | 1 | $450.00 | $735.00 | $1,100.00 | $700.00 | $6,500.00 |
| 156 | Elc SRV type D 120/240 060(NS)SS(N)PS(U) (628-7154) | EACH | 1 | $10,136 | $17,530 | $8,200.00 | $16,696 | $12,500 |
| 157 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 1 | $11,507 | $15,450 | $9,000.00 | $14,715 | $12,500 |
| 158 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 9 | $785.00 | $750.00 | $750.00 | $705.00 | $1,500.00 |
| 159 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 9 | $950.00 | $980.00 | $900.00 | $930.00 | $1,500.00 |
| 160 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,260.00 | $1,250.00 | $1,300.00 | $1,190.00 | $1,500.00 |
| 161 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 2 | $1,400.00 | $1,360.00 | $1,500.00 | $1,295.00 | $1,500.00 |
| 162 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $3,500.00 | $2,170.00 | $3,100.00 | $2,060.00 | $5,000.00 |
| 163 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 2 | $4,500.00 | $2,780.00 | $3,150.00 | $2,640.00 | $5,000.00 |
| 164 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 2 | $1,340.00 | $720.00 | $800.00 | $670.00 | $1,150.00 |
| 165 | Remove BRDG MNT clearance sign assembly (644-7074) | EACH | 2 | $360.00 | $120.00 | $900.00 | $110.00 | $250.00 |
| 166 | In SRSS & AM (rail)(130 MPH)(P mount) (644-7083) | EACH | 2 | $5,000.00 | $4,450.00 | $7,000.00 | $4,220.00 | $15,000 |
| 167 | In SRSS & AM (rail)(130 MPH)(T mount) (644-7085) | EACH | 2 | $7,000.00 | $4,600.00 | $7,000.00 | $4,370.00 | $15,000 |
| 168 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 6 | $75.00 | $50.00 | $150.00 | $44.00 | $100.00 |
| 169 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 17 | $26.50 | $25.00 | $80.00 | $22.00 | $100.00 |
| 170 | Install object marker assembly (OM-3R)(TWT)GND (658-7070) | EACH | 4 | $250.00 | $275.00 | $250.00 | $260.00 | $100.00 |
| 171 | Work zone pavement marking removing (W)4"(DOT) (662-7062) | LF | 517 | $2.00 | $3.00 | $3.23 | $2.30 | $1.00 |
| 172 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 17,675 | $1.00 | $1.00 | $1.56 | $0.90 | $1.00 |
| 173 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 542 | $7.80 | $7.00 | $16.93 | $6.85 | $20.00 |
| 174 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 9,884 | $1.00 | $1.00 | $1.56 | $0.90 | $1.00 |
| 175 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 118 | $1.70 | $3.00 | $3.23 | $2.10 | $6.00 |
| 176 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,639 | $1.20 | $2.00 | $2.42 | $1.05 | $6.00 |
| 177 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 20 | $4.00 | $5.00 | $10.75 | $4.40 | $6.00 |
| 178 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 721 | $9.00 | $9.00 | $16.13 | $8.00 | $20.00 |
| 179 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 14 | $55.00 | $72.00 | $129.00 | $69.00 | $150.00 |
| 180 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 246 | $7.30 | $9.00 | $16.13 | $8.15 | $20.00 |
| 181 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 370 | $0.75 | $1.00 | $5.38 | $0.78 | $1.00 |
| 182 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 4,554 | $0.55 | $1.00 | $3.23 | $0.69 | $1.00 |
| 183 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 6,038 | $0.60 | $1.00 | $3.23 | $0.69 | $1.00 |
| 184 | Pavement sler 6" (666-7347) | LF | 10,962 | $0.57 | $0.25 | $0.54 | $0.19 | $1.00 |
| 185 | Pavement sler 8" (666-7348) | LF | 1,757 | $0.59 | $0.50 | $1.08 | $0.29 | $1.00 |
| 186 | Pavement sler 12" (666-7350) | LF | 20 | $1.20 | $1.00 | $3.23 | $0.87 | $5.00 |
| 187 | Pavement sler 24" (666-7352) | LF | 967 | $3.00 | $2.00 | $6.45 | $1.65 | $20.00 |
| 188 | Pavement sler (yld tri) (666-7365) | EACH | 14 | $52.00 | $15.00 | $53.75 | $13.50 | $150.00 |
| 189 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 10 | $215.00 | $290.00 | $392.38 | $277.00 | $250.00 |
| 190 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 3 | $420.00 | $492.00 | $833.13 | $468.00 | $250.00 |
| 191 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 10 | $250.00 | $384.00 | $559.00 | $365.00 | $250.00 |
| 192 | Reflectorized pavement marker type I-C (672-7002) | EACH | 93 | $4.20 | $6.00 | $16.13 | $5.00 | $6.00 |
| 193 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 88 | $3.90 | $6.00 | $16.13 | $5.00 | $6.00 |
| 194 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 26 | $5.20 | $6.00 | $16.13 | $5.00 | $6.00 |
| 195 | Pavement surface preparation for marking (6") (678-7002) | LF | 10,962 | $0.36 | $0.05 | $0.48 | $0.02 | $1.00 |
| 196 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,757 | $0.35 | $0.10 | $0.81 | $0.08 | $3.00 |
| 197 | Pavement surface preparation for marking (12") (678-7006) | LF | 20 | $0.90 | $0.50 | $2.96 | $0.27 | $6.00 |
| 198 | Pavement surface preparation for marking (24") (678-7008) | LF | 967 | $1.40 | $0.75 | $5.91 | $0.58 | $20.00 |
| 199 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 14 | $15.50 | $7.00 | $43.00 | $6.65 | $150.00 |
| 200 | Install highway traffic signal (system) (680-7003) | EACH | 1 | $35,950 | $51,200 | $60,000 | $48,760 | $65,000 |
| 201 | Removing traffic signals (680-7004) | EACH | 1 | $8,000.00 | $10,230 | $6,000.00 | $9,740.00 | $15,000 |
| 202 | Temporary traffic signals (681-7001) | EACH | 1 | $90,000 | $91,770 | $125,000 | $87,400 | $95,000 |
| 203 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 10 | $345.00 | $480.00 | $450.00 | $455.00 | $325.00 |
| 204 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 7 | $344.00 | $492.00 | $450.00 | $468.00 | $325.00 |
| 205 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 14 | $344.00 | $480.00 | $450.00 | $455.00 | $325.00 |
| 206 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 6 | $345.00 | $492.00 | $450.00 | $468.00 | $325.00 |
| 207 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 14 | $344.00 | $480.00 | $450.00 | $455.00 | $325.00 |
| 208 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 6 | $347.00 | $492.00 | $450.00 | $468.00 | $325.00 |
| 209 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 12 | $925.00 | $925.00 | $800.00 | $881.00 | $6,500.00 |
| 210 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 14 | $295.00 | $270.00 | $350.00 | $256.00 | $200.00 |
| 211 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 3 | $315.00 | $285.00 | $360.00 | $267.00 | $250.00 |
| 212 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 4,853 | $3.00 | $4.00 | $3.20 | $3.28 | $1.00 |
| 213 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 203 | $4.00 | $4.00 | $3.20 | $3.55 | $1.00 |
| 214 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 1,782 | $5.00 | $5.00 | $8.50 | $3.98 | $1.00 |
| 215 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 4,392 | $6.00 | $4.00 | $2.15 | $2.95 | $1.00 |
| 216 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 1 | $14,500 | $15,270 | $16,000 | $14,539 | $32,500 |
| 217 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $16,500 | $17,710 | $18,000 | $16,865 | $35,000 |
| 218 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 1 | $15,515 | $18,555 | $20,000 | $17,670 | $40,000 |
| 219 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $20,015 | $22,650 | $22,000 | $21,540 | $45,000 |
| 220 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 2 | $32,275 | $41,510 | $45,000 | $39,530 | $50,000 |
| 221 | Pedestrian pole assembly (687-7001) | EACH | 11 | $3,920.00 | $4,100.00 | $2,500.00 | $3,895.00 | $6,500.00 |
| 222 | Pedestrian detect push button (APS) (688-7001) | EACH | 12 | $1,260.00 | $930.00 | $1,200.00 | $882.00 | $1,850.00 |
| 223 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,150.00 | $4,200.00 | $4,000.00 | $4,000.00 | $6,500.00 |
| 224 | Removal of conduit (690-7001) | LF | 360 | $3.80 | $5.00 | $1.10 | $4.58 | $20.00 |
| 225 | Removal of timber poles (690-7021) | EACH | 2 | $560.00 | $1,725.00 | $1,100.00 | $1,540.00 | $1,500.00 |
| 226 | Install down guy W/guard (690-7078) | EACH | 2 | $1,040.00 | $525.00 | $700.00 | $500.00 | $1,500.00 |
| 227 | Remove down guy W/guard (690-7080) | EACH | 2 | $280.00 | $265.00 | $300.00 | $250.00 | $500.00 |
| 228 | Anti-graffiti coating (permnent-type II) (740-7005) | SF | 6,069.80 | $1.70 | $5.00 | $3.00 | $1.50 | $5.00 |
| 229 | VIVDS temporary (6006-7006) | EACH | 1 | $7,720.00 | $80,000 | $18,000 | $75,380 | $80,000 |
| 230 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $43,775 | $11,500 | $10,000 | $10,896 | $8,500.00 |
| 231 | RVDS (presence detection only) (6008-7001) | EACH | 6 | $8,070.00 | $10,500 | $9,000.00 | $9,895.00 | $20,000 |
| 232 | RVDS (advance detection only) (6008-7002) | EACH | 4 | $8,830.00 | $13,200 | $9,000.00 | $12,530 | $20,000 |
| 233 | Ground box (prepare) (6013-7006) | EACH | 3 | $540.00 | $1,210.00 | $500.00 | $1,145.78 | $2,500.00 |
| 234 | Fiber optic CBL (single-mode)(36 fiber) (6027-7002) | LF | 2,480 | $2.00 | $15.00 | $4.25 | $13.86 | $25.00 |
| 235 | Fiber optic fusion splice (6027-7004) | EACH | 144 | $275.00 | $261.00 | $60.00 | $248.00 | $500.00 |
| 236 | FO splice enclosure (type 1) (6027-7009) | EACH | 4 | $1,920.00 | $3,900.00 | $1,000.00 | $3,675.00 | $6,500.00 |
| 237 | Fiber optic CBL (single-mode)(6 fiber) (6027-7011) | LF | 130 | $7.50 | $13.00 | $3.50 | $11.65 | $20.00 |
| 238 | Remove fiber optic cable (6027-7018) | LF | 2,190 | $1.40 | $2.00 | $1.60 | $1.18 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.