TxDOT contract A00213021 bid tabulation

MILL AND INLAY, US0290 (RM 676 + 0.56 to RM 678 + 0.06). Let by Texas DOT on March 5, 2025, Washington, Bryan District. 9 bids received; low bid $1,299,406 by Cornerstone Paving and Construction, L.L.C., -11% against the engineer's estimate of $1,454,685.

Owner
Texas DOT
Letting
05 MAR 2025
Pay items
22
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Paving and Construction, L.L.C.$1,299,406Low-11%
2Big Creek Construction, LTD.$1,362,797+5.0%-6.0%
3Elite Kings Construction, LLC$1,368,898+5.0%-6.0%
4Knife River Corporation - South$1,412,359+9.0%-3.0%
5Texas Materials Group, Inc.$1,615,428+24%+11%
6Environmental Allies, Inc.$1,680,102+29%+15%
7Forde Construction Company, Inc.$1,791,834+38%+23%
8Vulcan Materials Asphalt and Construction, LLC$1,810,781+39%+24%
9Brazos Paving, Inc.$1,898,546+46%+31%
TxDOT contract A00213021: bids by rank

Engineer's estimate: $1,454,685.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Cornerstone Paving and Construction, L.L.C.2. Big Creek Construction, LTD.3. Elite Kings Construction, LLC4. Knife River Corporation - South5. Texas Materials Group, Inc.6. Environmental Allies, Inc.
1Backfill (type A or B) (134-7004)STA73$200.00$400.00$350.00$100.00$278.00$400.00$600.00
2PFC-C PG76-22 sac-A (342-7001)TON3,887$150.00$174.00$165.00$150.00$172.85$182.00$206.00
3Tack coat (342-7015)GAL6,688$6.26$3.40$3.50$3.00$4.25$4.00$5.50
4Tom-C PG76-22 sac-B (347-7002)TON2,759$144.35$150.00$145.00$130.00$161.90$232.00$165.50
5Tack coat (347-7011)GAL6,688$6.26$3.40$3.50$3.00$4.25$4.00$5.50
6Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY66,880$3.00$0.50$1.50$3.00$0.94$1.00$2.25
7Mobilization (500-7001)LS1$55,116$45,000$65,000$10,000$56,980$58,000$75,000
8Barricades, signs and traffic handling (502-7001)MO2$4,000.00$3,000.00$5,000.00$12,500$5,750.00$1,100.00$2,500.00
9Portable changeable message sign (503-7001)DAY28$100.00$75.00$200.00$350.00$280.00$95.00$110.00
10TMA (stationary) (505-7001)DAY12$200.00$125.00$250.00$325.00$580.00$200.00$375.00
11TMA (mobile operation) (505-7003)DAY6$200.00$125.00$500.00$450.00$940.00$400.00$500.00
12Mill rumble strips (asphalt) (shoulder) (533-7001)LF27,100$1.05$0.10$0.55$1.50$0.32$0.10$0.35
13Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF3,960$0.42$0.50$0.40$2.30$0.42$0.45$0.45
14Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF15,840$0.65$0.39$0.40$1.00$0.42$0.45$0.40
15Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF720$0.62$0.80$1.00$1.20$1.10$0.90$0.75
16Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF15,840$0.75$0.39$0.40$1.20$0.42$0.45$0.45
17Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,980$1.00$1.45$1.50$1.00$2.20$0.85$2.00
18Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF720$1.65$1.45$1.00$1.00$1.42$1.15$1.55
19Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF3,960$1.00$0.70$0.75$1.00$0.92$0.75$0.95
20Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF15,840$1.31$0.62$0.75$1.00$0.92$0.75$0.85
21Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF15,840$1.43$0.62$0.75$1.00$0.92$0.75$0.85
22Reflectorized pavement marker type II-C-R (672-7006)EACH300$5.38$6.00$6.00$13.00$7.60$6.75$11.00
TxDOT contract A00213021: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy