TxDOT contract A00213021 bid tabulation
MILL AND INLAY, US0290 (RM 676 + 0.56 to RM 678 + 0.06). Let by Texas DOT on March 5, 2025, Washington, Bryan District. 9 bids received; low bid $1,299,406 by Cornerstone Paving and Construction, L.L.C., -11% against the engineer's estimate of $1,454,685.
- Owner
- Texas DOT
- Letting
- 05 MAR 2025
- Pay items
- 22
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Paving and Construction, L.L.C. | $1,299,406 | Low | -11% |
| 2 | Big Creek Construction, LTD. | $1,362,797 | +5.0% | -6.0% |
| 3 | Elite Kings Construction, LLC | $1,368,898 | +5.0% | -6.0% |
| 4 | Knife River Corporation - South | $1,412,359 | +9.0% | -3.0% |
| 5 | Texas Materials Group, Inc. | $1,615,428 | +24% | +11% |
| 6 | Environmental Allies, Inc. | $1,680,102 | +29% | +15% |
| 7 | Forde Construction Company, Inc. | $1,791,834 | +38% | +23% |
| 8 | Vulcan Materials Asphalt and Construction, LLC | $1,810,781 | +39% | +24% |
| 9 | Brazos Paving, Inc. | $1,898,546 | +46% | +31% |
Engineer's estimate: $1,454,685.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Cornerstone Paving and Construction, L.L.C. | 2. Big Creek Construction, LTD. | 3. Elite Kings Construction, LLC | 4. Knife River Corporation - South | 5. Texas Materials Group, Inc. | 6. Environmental Allies, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Backfill (type A or B) (134-7004) | STA | 73 | $200.00 | $400.00 | $350.00 | $100.00 | $278.00 | $400.00 | $600.00 |
| 2 | PFC-C PG76-22 sac-A (342-7001) | TON | 3,887 | $150.00 | $174.00 | $165.00 | $150.00 | $172.85 | $182.00 | $206.00 |
| 3 | Tack coat (342-7015) | GAL | 6,688 | $6.26 | $3.40 | $3.50 | $3.00 | $4.25 | $4.00 | $5.50 |
| 4 | Tom-C PG76-22 sac-B (347-7002) | TON | 2,759 | $144.35 | $150.00 | $145.00 | $130.00 | $161.90 | $232.00 | $165.50 |
| 5 | Tack coat (347-7011) | GAL | 6,688 | $6.26 | $3.40 | $3.50 | $3.00 | $4.25 | $4.00 | $5.50 |
| 6 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 66,880 | $3.00 | $0.50 | $1.50 | $3.00 | $0.94 | $1.00 | $2.25 |
| 7 | Mobilization (500-7001) | LS | 1 | $55,116 | $45,000 | $65,000 | $10,000 | $56,980 | $58,000 | $75,000 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 2 | $4,000.00 | $3,000.00 | $5,000.00 | $12,500 | $5,750.00 | $1,100.00 | $2,500.00 |
| 9 | Portable changeable message sign (503-7001) | DAY | 28 | $100.00 | $75.00 | $200.00 | $350.00 | $280.00 | $95.00 | $110.00 |
| 10 | TMA (stationary) (505-7001) | DAY | 12 | $200.00 | $125.00 | $250.00 | $325.00 | $580.00 | $200.00 | $375.00 |
| 11 | TMA (mobile operation) (505-7003) | DAY | 6 | $200.00 | $125.00 | $500.00 | $450.00 | $940.00 | $400.00 | $500.00 |
| 12 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 27,100 | $1.05 | $0.10 | $0.55 | $1.50 | $0.32 | $0.10 | $0.35 |
| 13 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 3,960 | $0.42 | $0.50 | $0.40 | $2.30 | $0.42 | $0.45 | $0.45 |
| 14 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 15,840 | $0.65 | $0.39 | $0.40 | $1.00 | $0.42 | $0.45 | $0.40 |
| 15 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 720 | $0.62 | $0.80 | $1.00 | $1.20 | $1.10 | $0.90 | $0.75 |
| 16 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 15,840 | $0.75 | $0.39 | $0.40 | $1.20 | $0.42 | $0.45 | $0.45 |
| 17 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,980 | $1.00 | $1.45 | $1.50 | $1.00 | $2.20 | $0.85 | $2.00 |
| 18 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 720 | $1.65 | $1.45 | $1.00 | $1.00 | $1.42 | $1.15 | $1.55 |
| 19 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 3,960 | $1.00 | $0.70 | $0.75 | $1.00 | $0.92 | $0.75 | $0.95 |
| 20 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 15,840 | $1.31 | $0.62 | $0.75 | $1.00 | $0.92 | $0.75 | $0.85 |
| 21 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 15,840 | $1.43 | $0.62 | $0.75 | $1.00 | $0.92 | $0.75 | $0.85 |
| 22 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 300 | $5.38 | $6.00 | $6.00 | $13.00 | $7.60 | $6.75 | $11.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.