LARGE SIGN REPLACEMENT, IH0030 (Various Roadways in the to Dallas District). Let by Texas DOT on March 5, 2025, Dallas, Dallas District. 3 bids received; low bid $2,186,275 by Rise Up Construction LLC, -16% against the engineer's estimate of $2,605,832.

Owner
Texas DOT
Letting
05 MAR 2025
Pay items
48
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Rise Up Construction LLC$2,186,275Low-16%
2WG Engineering & Construction, LLC$2,600,108+19%0.0%
3Synergy Signs & Services LLC$2,729,763+25%+5.0%
TxDOT contract A00209741: bids by rank

Engineer's estimate: $2,605,832.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Rise Up Construction LLC2. WG Engineering & Construction, LLC3. Synergy Signs & Services LLC
1Removing concrete (riprap) (104-7006)SY20$462.00$450.00$266.00$1,000.00
2Removing concrete (foundations) (104-7024)CY12$1,239.00$500.00$797.90$1,000.00
3Drilled shaft (sign mounts) (24 in) (416-7028)LF180$367.50$500.00$350.10$350.00
4Drilled shaft (sign mounts) (30 in) (416-7029)LF240$420.00$600.00$418.20$550.00
5Drilled shaft (sign mounts) (36 in) (416-7030)LF120$472.50$800.00$531.90$550.00
6Drilled shaft (sign mounts) (42 in) (416-7031)LF16$787.50$1,000.00$577.50$675.00
7Drilled shaft (sign mounts) (48 in) (416-7032)LF32$861.00$1,200.00$763.70$750.00
8Drilled shaft (sign mounts) (54 in) (416-7033)LF129$892.50$1,200.00$835.90$850.00
9Riprap (mow strip)(4 in) (432-7013)CY30$1,590.75$1,155.00$1,082.80$1,000.00
10Mobilization (callout) (500-7002)EACH20$13,808$1.00$18,046$35,000
11Portable changeable message sign (503-7001)DAY50$530.25$100.00$342.00$250.00
12TMA (stationary) (505-7001)DAY200$400.00$300.00$386.30$250.00
13TMA (mobile operation) (505-7003)DAY5$600.00$1,000.00$386.30$500.00
14Biodegradable erosion control logs (install) (18") (506-7045)LF40$18.90$1.00$6.00$10.00
15Biodegradable erosion control logs (remove) (506-7046)LF40$9.45$1.00$0.90$5.00
16Metal W-beam guard fence (steel post) (540-7002)LF600$56.70$40.00$69.70$35.00
17Metal beam guard fence trans (thrie-beam) (540-7005)EACH1$3,990.00$2,500.00$4,432.50$2,600.00
18Metal W-beam guard fence adjustment (540-7009)LF25$53.55$30.00$158.40$35.00
19Metal thrie-beam guard fence adjustment (540-7010)LF25$65.10$33.00$190.00$500.00
20Terminal anchor section adjustment (540-7011)EACH1$1,365.00$100.00$1,899.70$500.00
21Downstream anchor terminal section (540-7015)EACH8$2,047.50$1,355.00$4,432.50$2,000.00
22Remove metal beam guard fence (542-7001)LF200$9.45$5.00$26.60$10.00
23Remove terminal anchor section (542-7002)EACH2$693.00$220.00$1,241.10$350.00
24Remove downstream anchor terminal (542-7003)EACH2$813.75$200.00$1,241.10$350.00
25Guardrail end treatment (install) (544-7001)EACH4$4,275.00$4,000.00$5,698.90$3,500.00
26Guardrail end treatment (remove) (544-7003)EACH1$1,627.50$300.00$2,849.50$350.00
27Aluminum signs (type A) (636-7001)SF350$51.45$25.00$30.30$35.00
28Aluminum signs (type G) (636-7002)SF4,200$40.95$39.00$45.60$35.00
29Aluminum signs (type O) (636-7003)SF2,000$47.25$75.00$56.40$35.00
30Replace existing aluminum signs(type A) (636-7004)SF300$61.95$25.00$35.60$35.00
31Replace existing aluminum signs(type G) (636-7005)SF120$65.10$95.00$61.60$35.00
32Replace existing aluminum signs(type O) (636-7006)SF1,900$73.50$75.00$74.30$35.00
33Install LRSS (struct steel) (647-7001)LB16,440$10.24$8.00$8.30$8.95
34Remove lrsa (647-7003)EACH8$1,590.75$500.00$1,595.70$2,000.00
35Install overhead sign support(25 FT bal tee) (650-7021)EACH1$40,194$40,000$38,625$44,000
36Install overhead sign support(30 FT cant) (650-7032)EACH1$43,785$50,000$38,625$42,000
37Install overhead sign support(35 FT cant) (650-7038)EACH2$50,925$50,000$41,538$45,000
38Install overhead sign support(40 FT cant) (650-7045)EACH4$57,771$50,000$44,704$47,000
39Install overhead sign support(70 FT BRDG) (650-7079)EACH1$70,875$100,000$71,299$63,000
40Install overhead sign support(80 FT BRDG) (650-7089)EACH1$77,280$100,000$77,757$84,000
41Install overhead sign support(90 FT BRDG) (650-7099)EACH1$92,505$60,000$88,015$75,000
42Install overhead sign support(100 FT BRDG) (650-7109)EACH1$103,425$60,000$100,299$87,000
43Install overhead sign support(110 FT BRDG) (650-7119)EACH1$113,610$60,000$111,317$95,000
44Install overhead sign support(120 FT BRDG) (650-7129)EACH1$131,145$60,000$127,401$110,000
45Remove overhd sign sup (650-7193)EACH3$10,499$3,500.00$9,498.10$15,000
46Remove overhd sign sup (sign only) (650-7194)EACH2$1,785.00$2,500.00$4,229.80$2,000.00
47Remove sign walkway (654-7007)EACH8$1,590.75$500.00$2,659.50$3,000.00
48Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH12$63.00$100.00$117.80$75.00
TxDOT contract A00209741: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy