Metal W-beam guard fence adjustment, TxDOT 540-7009
Low bidders on TxDOT contracts carried a median of $8.50 per LF for this item, over the 24 months to 19 NOV 2026, across 26 low bids. Half of all 108 bids fell between $4.75 and $20.00.
- Owner
- Texas DOT
- Item
- 540-7009
- Unit
- LF
- Data through
- 19 NOV 2026
TxDOT prints this item as “MTL W-BEAM GD FEN ADJUSTMENT”.
TxDOT has bid this work under more than one code: 5406010001 on lettings from 06 FEB 2020 to 05 JUN 2024 (162 bids); 5406010 on lettings from 04 SEP 2020 to 04 SEP 2020 (3 bids); 540-7009 on lettings from 04 DEC 2024 to 12 AUG 2026 (111 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $12.32 | 41 | $13.13 |
| 2021 | 7 | 7 | $10.00 | 36 | $10.75 |
| 2022 | 6 | 6 | $20.45 | 22 | $18.00 |
| 2023 | 12 | 12 | $23.00 | 37 | $20.00 |
| 2024 | 8 | 8 | $13.40 | 35 | $12.00 |
| 2025 | 17 | 17 | $10.00 | 70 | $13.45 |
| 2026 | 8 | 8 | $5.00 | 32 | $13.38 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Beaumont District | 4 | $10.00 | 19 | $10.00 |
| Bryan District | 5 | $1.00 | 17 | $1.00 |
| Fort Worth District | 3 | $1.00 | 13 | $8.00 |
| Dallas District | 3 | $30.00 | 7 | $35.00 |
| Tyler District | 4 | $4.50 | 6 | $4.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 1 to 25 | 6 | $20.00 |
| 25 to 100 | 7 | $10.00 |
| 200 to 750 | 6 | $3.00 |
| 816 to 7,250 | 7 | $7.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Rhino Equity, LLC | 10 | 7 (70%) |
| T&L Cleaning Services LLC | 8 | 6 (75%) |
| Ragle Construction, Inc. | 7 | 5 (71%) |
| Roy Jorgensen Associates, Inc. | 11 | 3 (27%) |
| James Construction Group, LLC | 5 | 3 (60%) |
| Ross Sa Enterprise LLC | 9 | 2 (22%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12 AUG 2026 | A00223094 | Bryan District | 25 | $1.00 | $1.00 | $20.00 | 2 | Rhino Equity, LLC | TxDOT |
| 11 AUG 2026 | A00223019 | Bryan District | 25 | $3.00 | $2.00 | $20.00 | 2 | T&L Cleaning Services LLC | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 350 | $20.00 | $20.71 | n/a | 4 | Williams Brothers Construction Co., Inc. | TxDOT |
| 12 MAY 2026 | A00220799 | Tyler District | 1,000 | $5.00 | $5.00 | $5.00 | 1 | Catocon, Inc. | TxDOT |
| 12 MAY 2026 | A00218435 | Tyler District | 200 | $5.00 | $5.00 | $5.00 | 1 | Catocon, Inc. | TxDOT |
| 19 FEB 2026 | A00218062 | Paris District | 750 | $1.00 | $2.00 | $6.00 | 4 | Catocon, Inc. | TxDOT |
| 10 FEB 2026 | A00216549 | Beaumont District | 100 | $10.00 | $13.00 | $20.00 | 6 | Rhino Equity, LLC | TxDOT |
| 05 FEB 2026 | A00186405 | Corpus Christi District | 816 | $19.50 | $16.25 | $12.00 | 12 | Liska Construction Company, Inc. | TxDOT |
| 10 DEC 2025 | A00218315 | Bryan District | 25 | $1.00 | $10.00 | $20.00 | 5 | Rhino Equity, LLC | TxDOT |
| 09 DEC 2025 | A00218314 | Bryan District | 25 | $1.00 | $1.00 | $20.00 | 4 | T&L Cleaning Services LLC | TxDOT |
| 05 NOV 2025 | A00217120 | Dallas District | 1 | $400.00 | $225.00 | $75.00 | 2 | Cross Plus Construction, LLC | TxDOT |
| 05 NOV 2025 | A00217511 | Fort Worth District | 250 | $1.00 | $6.00 | $25.00 | 3 | Short-Line Corporation | TxDOT |
| 13 AUG 2025 | A00211544 | Dallas District | 475 | $1.00 | $3.00 | $15.00 | 2 | Fireman Excavating, Inc. | TxDOT |
| 08 JUL 2025 | A00216167 | Tyler District | 2,000 | $4.00 | $4.00 | $10.00 | 3 | BK Field Operations LLC | TxDOT |
| 02 JUL 2025 | A00178488 | Austin District | 7,250 | $16.00 | $17.00 | $12.00 | 7 | Texas Materials Group, Inc. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.