TxDOT contract A00216549 bid tabulation
METAL BEAM GUARD FENCE REPAIR, IH0010 (VARIOUS to VARIOUS). Let by Texas DOT on February 10, 2026, Chambers, Beaumont District. 6 bids received; low bid $342,306 by Rhino Equity, LLC, -29% against the engineer's estimate of $484,870.
- Owner
- Texas DOT
- Letting
- 10 FEB 2026
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rhino Equity, LLC | $342,306 | Low | -29% |
| 2 | Roy Jorgensen Associates, Inc. | $357,360 | +4.0% | -26% |
| 3 | BK Field Operations LLC | $428,000 | +25% | -12% |
| 4 | Isi Contracting, Inc. | $641,354 | +87% | +32% |
| 5 | Hazmat International, Inc. | $758,107 | +121% | +56% |
| 6 | Above All Contracting LLC | $763,050 | +123% | +57% |
Engineer's estimate: $484,870.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Rhino Equity, LLC | 2. Roy Jorgensen Associates, Inc. | 3. BK Field Operations LLC | 4. Isi Contracting, Inc. | 5. Hazmat International, Inc. | 6. Above All Contracting LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 15 | $85.00 | $1.00 | $15.00 | $100.00 | $15.00 | $2.50 | $50.00 |
| 2 | Concrete structure repair (standard) (429-7009) | SF | 15 | $500.00 | $10.00 | $150.00 | $10.00 | $76.00 | $35.00 | $50.00 |
| 3 | Riprap (mow strip)(4 in) (432-7013) | CY | 30 | $350.00 | $200.00 | $450.00 | $700.00 | $530.00 | $600.00 | $600.00 |
| 4 | Rail (type T402)(HPC) (450-7013) | LF | 150 | $20.00 | $20.00 | $35.00 | $100.00 | $203.00 | $25.00 | $100.00 |
| 5 | Mobilization (callout) (500-7002) | EACH | 15 | $1.00 | $1.00 | $500.00 | $1.00 | $260.00 | $1.00 | $1.00 |
| 6 | Mobilization (emergency) (500-7033) | EACH | 5 | $500.00 | $500.00 | $2,500.00 | $1.00 | $520.00 | $1,000.00 | $500.00 |
| 7 | Portable changeable message sign (503-7001) | DAY | 15 | $350.00 | $25.00 | $50.00 | $300.00 | $170.00 | $50.00 | $300.00 |
| 8 | TMA (stationary) (505-7001) | DAY | 56 | $350.00 | $750.00 | $450.00 | $1.00 | $350.00 | $250.00 | $250.00 |
| 9 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 120 | $100.00 | $5.00 | $70.00 | $40.00 | $4.10 | $50.00 | $200.00 |
| 10 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 120 | $100.00 | $5.00 | $15.00 | $40.00 | $11.00 | $2.00 | $50.00 |
| 11 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $100.00 | $10.00 | $25.00 | $20.00 | $36.00 | $25.00 | $35.00 |
| 12 | Metal thrie-beam guard fence (timber post) (540-7003) | LF | 25 | $100.00 | $15.00 | $20.00 | $110.00 | $69.00 | $25.00 | $55.00 |
| 13 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $1,800.00 | $2,000.00 | $1,600.00 | $3,000.00 | $1,720.00 | $2,000.00 | $700.00 |
| 14 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 1 | $500.00 | $500.00 | $1,000.00 | $500.00 | $1,468.00 | $1.00 | $1,000.00 |
| 15 | Metal beam guard fence trans (T101) (540-7007) | EACH | 1 | $500.00 | $500.00 | $1,000.00 | $800.00 | $1,016.00 | $1.00 | $1,000.00 |
| 16 | Metal W-beam guard fence adjustment (540-7009) | LF | 100 | $20.00 | $10.00 | $2.00 | $12.00 | $14.00 | $25.00 | $30.00 |
| 17 | Transition adjustment (540-7012) | EACH | 5 | $350.00 | $1.00 | $150.00 | $1.00 | $79.00 | $50.00 | $1,000.00 |
| 18 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,400.00 | $900.00 | $1,250.00 | $1,600.00 | $1,918.00 | $2,000.00 | $2,000.00 |
| 19 | Metal beam guard fence (long span system) (540-7027) | EACH | 25 | $150.00 | $5.00 | $50.00 | $1.00 | $394.00 | $100.00 | $1,000.00 |
| 20 | Remove metal beam guard fence (542-7001) | LF | 500 | $25.00 | $1.00 | $2.00 | $2.00 | $7.90 | $2.50 | $5.00 |
| 21 | Remove terminal anchor section (542-7002) | EACH | 5 | $100.00 | $1.00 | $100.00 | $1.00 | $455.00 | $1.00 | $500.00 |
| 22 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $2,700.00 | $3,000.00 | $2,600.00 | $2,250.00 | $3,439.00 | $3,000.00 | $4,000.00 |
| 23 | Guardrail end treatment (move & reset) (544-7002) | EACH | 3 | $250.00 | $100.00 | $100.00 | $300.00 | $715.00 | $50.00 | $500.00 |
| 24 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $200.00 | $50.00 | $100.00 | $1.00 | $904.00 | $1.00 | $500.00 |
| 25 | Crash cushion attenuator (des source) (545-7001) | EACH | 2 | $1,500.00 | $1,000.00 | $500.00 | $2,000.00 | $641.00 | $5,000.00 | $5,000.00 |
| 26 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,050.00 | $1.00 | $500.00 | $1.00 | $365.00 | $250.00 | $1,000.00 |
| 27 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 20 | $150.00 | $1.00 | $80.00 | $1.00 | $25.00 | $1.00 | $50.00 |
| 28 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 20 | $77.00 | $1.00 | $80.00 | $1.00 | $25.00 | $1.00 | $50.00 |
| 29 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 9 | $60.00 | $10.00 | $100.00 | $30.00 | $45.00 | $20.00 | $100.00 |
| 30 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 5 | $60.00 | $1.00 | $50.00 | $30.00 | $39.00 | $20.00 | $100.00 |
| 31 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 2 | $60.00 | $10.00 | $50.00 | $30.00 | $25.00 | $5.00 | $1,000.00 |
| 32 | Replace rail element (W-beam) (770-7001) | LF | 1,500 | $80.00 | $10.00 | $20.00 | $5.00 | $25.00 | $10.00 | $35.00 |
| 33 | Replace rail element (thrie-beam) (770-7002) | LF | 25 | $80.00 | $20.00 | $15.00 | $30.00 | $36.00 | $13.50 | $60.00 |
| 34 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 5 | $80.00 | $300.00 | $250.00 | $200.00 | $926.00 | $350.00 | $750.00 |
| 35 | Replace timber post W/O concrete FND (770-7006) | EACH | 22 | $350.00 | $50.00 | $500.00 | $800.00 | $104.00 | $50.00 | $60.00 |
| 36 | Replace steel post W/O concrete FND (770-7007) | EACH | 10 | $350.00 | $1.00 | $20.00 | $100.00 | $142.00 | $50.00 | $100.00 |
| 37 | Replace timber post W/ concrete FND (770-7008) | EACH | 10 | $550.00 | $75.00 | $500.00 | $800.00 | $141.00 | $100.00 | $200.00 |
| 38 | Realign posts (770-7010) | EACH | 75 | $10.00 | $50.00 | $50.00 | $300.00 | $16.00 | $100.00 | $100.00 |
| 39 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 10 | $2,700.00 | $3,000.00 | $2,950.00 | $5,000.00 | $2,956.00 | $4,500.00 | $6,000.00 |
| 40 | Repl single gdrail terminal impact head (770-7015) | EACH | 30 | $850.00 | $700.00 | $1,050.00 | $1,665.00 | $1,247.00 | $1,500.00 | $900.00 |
| 41 | Replace single gdrail terminal rail (770-7016) | LF | 1,000 | $15.00 | $120.00 | $40.00 | $40.00 | $36.00 | $150.00 | $50.00 |
| 42 | Replace single gdrail terminal post (770-7017) | EACH | 140 | $50.00 | $100.00 | $120.00 | $1.00 | $52.00 | $50.00 | $120.00 |
| 43 | Replace blockout (770-7018) | EACH | 150 | $20.00 | $50.00 | $25.00 | $15.00 | $25.00 | $50.00 | $50.00 |
| 44 | Reset SGT impact head (770-7020) | EACH | 12 | $100.00 | $100.00 | $150.00 | $900.00 | $319.00 | $250.00 | $200.00 |
| 45 | Replace SGT object marker (770-7021) | EACH | 20 | $50.00 | $55.00 | $50.00 | $1.00 | $35.00 | $25.00 | $30.00 |
| 46 | Replace SGT cable assembly (770-7023) | EACH | 30 | $20.00 | $100.00 | $80.00 | $50.00 | $154.00 | $100.00 | $120.00 |
| 47 | Replace SGT strut (770-7024) | EACH | 7 | $10.00 | $100.00 | $80.00 | $50.00 | $108.00 | $50.00 | $120.00 |
| 48 | Replace posts (TL-4)(gibraltar) (771-7005) | EACH | 50 | $50.00 | $200.00 | $5.00 | $200.00 | $366.00 | $200.00 | $250.00 |
| 49 | Replace posts (TL-4)(NU-cable) (771-7006) | EACH | 50 | $5.00 | $1.00 | $5.00 | $1.00 | $366.00 | $225.00 | $200.00 |
| 50 | Replace posts (TL-4)(trinity) (771-7007) | EACH | 50 | $50.00 | $240.00 | $250.00 | $200.00 | $366.00 | $350.00 | $250.00 |
| 51 | Replace posts (TL-4)(brifen) (771-7008) | EACH | 50 | $50.00 | $1.00 | $5.00 | $1.00 | $366.00 | $300.00 | $350.00 |
| 52 | Cable splice / turnbuckle (TL-4) (771-7010) | EACH | 10 | $100.00 | $1.00 | $100.00 | $1.00 | $366.00 | $25.00 | $500.00 |
| 53 | Repair concrete foundation (TL-4) (771-7012) | EACH | 2 | $100.00 | $50.00 | $100.00 | $1.00 | $1,205.00 | $1.00 | $1,000.00 |
| 54 | Repair or replace cable barrier terminal sec(TL-4) (771-7014) | EACH | 20 | $3,500.00 | $100.00 | $50.00 | $1.00 | $3,600.00 | $6,500.00 | $3,000.00 |
| 55 | Replace cable (TL-4) (771-7016) | LF | 1,000 | $5.00 | $0.25 | $1.50 | $1.00 | $10.00 | $5.00 | $10.00 |
| 56 | Check / RE-tension cable (TL-4) (771-7018) | EACH | 10 | $600.00 | $200.00 | $300.00 | $1,500.00 | $7.60 | $150.00 | $250.00 |
| 57 | Remove (tau II-R) narrow (774-7019) | EACH | 10 | $100.00 | $1.00 | $150.00 | $5.00 | $365.00 | $1.00 | $1,000.00 |
| 58 | Replace (tau II-R) narrow (774-7020) | EACH | 2 | $2,500.00 | $2,000.00 | $5,000.00 | $27,000 | $40,311 | $20,000 | $28,000 |
| 59 | Remove (narrow quad) (774-7025) | EACH | 1 | $160.00 | $1.00 | $150.00 | $1.00 | $365.00 | $1.00 | $1,000.00 |
| 60 | Replace (narrow quad) (774-7026) | EACH | 1 | $6,500.00 | $500.00 | $5,000.00 | $28,000 | $40,311 | $20,000 | $28,000 |
| 61 | Repair (narrow quad bay) (774-7029) | EACH | 6 | $2,000.00 | $2,000.00 | $1,250.00 | $1,400.00 | $916.00 | $2,000.00 | $1,500.00 |
| 62 | Repair (wide quad bay) (774-7034) | EACH | 1 | $800.00 | $500.00 | $1,250.00 | $1,000.00 | $916.00 | $4,500.00 | $8,000.00 |
| 63 | Remove (tau II) wide (774-7039) | EACH | 1 | $50.00 | $1.00 | $150.00 | $1.00 | $365.00 | $0.10 | $2,000.00 |
| 64 | Replace (tau II) wide (774-7040) | EACH | 1 | $3,000.00 | $100.00 | $5,000.00 | $5.00 | $39,484 | $20,000 | $35,000 |
| 65 | Remove (narrow tracc) (774-7048) | EACH | 1 | $3,000.00 | $100.00 | $150.00 | $2,000.00 | $1,500.00 | $0.10 | $750.00 |
| 66 | Replace (narrow tracc) (774-7049) | EACH | 1 | $3,000.00 | $100.00 | $150.00 | $1.00 | $2,500.00 | $22,500 | $28,000 |
| 67 | Remove (wide tracc) (774-7050) | EACH | 1 | $100.00 | $1.00 | $150.00 | $1.00 | $1,500.00 | $0.10 | $1,500.00 |
| 68 | Replace (wide tracc) (774-7051) | EACH | 1 | $4,700.00 | $100.00 | $5,000.00 | $1.00 | $1,500.00 | $50,625 | $30,000 |
| 69 | Repair (wide tracc) (774-7052) | LF | 12 | $205.00 | $200.00 | $100.00 | $1.00 | $150.00 | $500.00 | $1,000.00 |
| 70 | Repair (wide tracc bay) (774-7054) | EACH | 1 | $240.00 | $1.00 | $2,500.00 | $1.00 | $1,500.00 | $500.00 | $3,000.00 |
| 71 | Concrete rail repair (in-kind) (778-7001) | LF | 11 | $300.00 | $300.00 | $1,500.00 | $800.00 | $122.00 | $2,000.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 10, 2026. Compiled by Mirage Metrics.